Builder's Kitchens of Stark County, Inc. v. Sibel

937 N.E.2d 570, 189 Ohio App. 3d 41
CourtOhio Court of Appeals
DecidedMarch 8, 2010
DocketNo. 2009CA00065
StatusPublished
Cited by2 cases

This text of 937 N.E.2d 570 (Builder's Kitchens of Stark County, Inc. v. Sibel) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builder's Kitchens of Stark County, Inc. v. Sibel, 937 N.E.2d 570, 189 Ohio App. 3d 41 (Ohio Ct. App. 2010).

Opinion

Delaney, Judge.

{¶ 1} Plaintiff-appellant, Builder’s Kitchens of Stark County, Inc., appeals the February 28, 2009 judgment entry of the Stark County Court of Common Pleas adopting the January 15, 2009 decision of the magistrate. Defendant-appellee is Kate Sibel.

STATEMENT OF THE FACTS AND THE CASE

{¶ 2} On January 11, 2008, appellant filed a complaint for account against appellee, moving for judgment in the amount of $27,413.19 based upon breach of contract and quantum meruit. Appellee counterclaimed against appellant, alleging breach of the same contract and requesting judgment for $8,239.85.

{¶ 3} The trial court assigned the matter to a magistrate, and a nonjury trial was held on November 6, 2008. The following evidence was adduced at trial.

{¶ 4} Appellant, located in Canton, Ohio, is in the business of designing and installing kitchen cabinetry, bath cabinetry, desks, and entertainment centers. In late 2005, appellee sought the services of appellant for the purpose of renovating the cabinetry in her home located in Canton, Ohio. Appellee’s existing cabinetry was constructed by Wood-Mode, and appellee wanted the new cabinetry to match in color and style what was already in place. Appellee chose to contract with appellant because appellant was a local Wood-Mode dealer.

[43]*43{¶ 5} David Horst, appellant’s owner and president, met with appellee several times in the spring of 2006 to discuss the remodeling project. As a result of the meetings, appellant prepared a proposal dated June 26, 2006, detailing the scope of the work to be done in appellee’s home. The parties do not dispute that they entered into an oral contract for the completion of the work contained in the June 26, 2006 proposal.

{¶ 6} Specific to this appeal, the June 26, 2006 proposal stated, “Install new kitchen cabinets as per layout to match existing cabinets.” In the dinette area, appellant was to install a Wood-Mode bar/hutch as per the layout designed by appellee, Horst, and a representative from Wood-Mode. In Plaintiffs Exhibit 4, a representative from Wood-Mode drew up a plan for the construction of the hutch as to its detailing, such as the style of door and drawer fronts. Horst testified that he showed appellee the drawing of the style of the hutch and she gave her approval.

{¶ 7} On June 29, 2006, Horst issued an itemized proposal to appellant. The total cost of the project was $96,264.43. The hutch cabinetry cost $21,467.76. Appellee made an initial deposit of $20,000 to begin the project.

{¶ 8} Horst subcontracted with Brian Eick to perform the installation and construction work in appellee’s home, as set forth in the June 26, 2006 proposal. Eick, Horst, and appellee met at appellee’s home and walked through the home to discuss the work that was to be completed pursuant to the June 26, 2006 proposal. Appellant paid Eick $20,000 to work on the project. Eick testified that at the time of the hearing, all of the work for appellant, but for a few small items, was complete; Eick had billed appellant for $20,000; and appellant had paid the bill.

{¶ 9} Appellant secured and delivered the cabinets for installation. Appellee was not present for the installation of the cabinets because she was out of the country. When appellee returned, she inspected the installed cabinetry in her home. Appellee voiced her complaints to Eick that the hutch did not match the existing cabinetry in color or style. Eick testified that he was working under appellant’s contract when appellee told him her complaints in regards to the hutch.

{¶ 10} Appellee testified at trial that the hutch had several problems. It did not match the drawing made by Wood-Mode’s representative in that the installed drawer fronts were flat panels, and appellee had specified raised panels. The specifications called for bead board in the interior of the hutch, and the installed hutch did not have the specified bead board. The color of the hutch did not match the color of the existing cabinetry. Eick testified that Horst and a Wood-Mode representative were present when the hutch was installed, and they knew that the hutch did not match the existing cabinets, but Horst told Eick to go ahead and install it. Horst testified that he did not have any knowledge prior to [44]*44appellee’s counterclaim that the hutch did not conform to appellee’s color specifications: However, Horst stated that he learned from Eick about the issues with the door fronts and bead board; appellant supplied new door fronts and bead board for the hutch to be installed by Eick. Eick was compensated by appellant for his work under the contract. Appellee also asked Eick to complete additional work after the installation of the cabinets and compensated him directly.

{¶ 11} In order to color-match the hutch, Eick testified that he would have to remove the hutch, take it to a finish shop, have it refinished, bring it back, and reinstall it. He estimated that it would cost $1,500 to remove the hutch and $3,000 to reinstall the hutch. At the time of trial, however, Eick testified that he had not been asked to refinish the hutch, and he could not give an estimate as to how much it would cost to refinish the hutch so that it matched the existing cabinets. Eick conjectured that it would cost less to refinish the hutch than to purchase and install a new conforming hutch. Eick stated that if the hutch were to be replaced with a new hutch with the correct color and style specifications, the project would cost $28,500.

{¶ 12} In total, appellee paid appellant $70,000 (including the $20,000 deposit). At trial, the parties stipulated that appellant did not complete work in the amount of $4,704.00. Appellant did do additional work in the amount of $5,852.76. The total cost of the project then was $97,413.19. The unpaid balance of the contract was $27,413.19.

{¶ 13} In the January 15, 2009 magistrate’s decision, the magistrate determined that there was a breach of the oral contract entered into by the parties as to the hutch. The magistrate found that appellant had breached the oral contract by knowingly providing a nonconforming product, as the hutch did not match the diagram provided by appellant based upon the existing main kitchen cabinetry as to either design or color. The magistrate found, based upon the findings of fact and conclusions of law, that appellee was entitled to offset the balance due on the final price of the project of $27,413.19 by the cost of the nonconforming hutch in the amount of $21,467.76.

{¶ 14} The magistrate granted judgment in favor of appellant in the amount of $5,945.43, with interest at the statutory rate from May 4, 2007.

{¶ 15} Appellant filed objections to the magistrate’s decision. Upon due consideration of the objections and response, the trial court adopted the magistrate’s decision on February 28, 2009.

{¶ 16} It is from this decision that appellant now appeals.

ASSIGNMENTS OF ERROR

{¶ 17} Appellant raises two assignments of error:

[45]*45{¶ 18} “I. Is an individual unjustly enriched when she is allowed to keep a personal item, without having to pay for it, where the only complaint is the color?

{¶ 19} “II. Can a buyer use as a defense non-conformity of a personal item when the buyer has failed to provide timely notice to the seller?”

I and II

{¶ 20} For ease of analysis, we will discuss appellant’s assignments of error together.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
937 N.E.2d 570, 189 Ohio App. 3d 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-kitchens-of-stark-county-inc-v-sibel-ohioctapp-2010.