Builders Firstsource-Southeast v. MI Windows And Doors

CourtCourt of Appeals of South Carolina
DecidedFebruary 26, 2025
Docket2020-000415
StatusUnpublished

This text of Builders Firstsource-Southeast v. MI Windows And Doors (Builders Firstsource-Southeast v. MI Windows And Doors) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builders Firstsource-Southeast v. MI Windows And Doors, (S.C. Ct. App. 2025).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Builders Firstsource-Southeast Group, LLC, Appellant,

v.

MI Windows And Doors, INC.; ECC Contracting, LLC; Hurley Services, LLC; and Charleston Exteriors, LLC, Respondents.

Appellate Case No. 2020-000415

Appeal From Berkeley County Clifton Newman, Circuit Court Judge

Unpublished Opinion No. 2025-UP-072 Heard March 15, 2023 – Filed February 26, 2025

AFFIRMED IN PART, VACATED IN PART, AND REMANDED

Stephen P. Hughes and William Hewitt Cox, III, both of Howell Gibson & Hughes, PA, of Beaufort, for Appellant.

James H. Elliott, Jr. and Francis Heyward Grimball, both of Richardson Plowden & Robinson, PA, and L. Dean Best and Mark Shanter Chaparro, both of Best Law, P.A., all of Mount Pleasant, for Respondent ECC Contracting, LLC. Derek Michael Newberry, of Hall Booth Smith, PC, of Mount Pleasant, for Respondents MI Windows and Doors, Inc. and Hurley Services, LLC.

Christopher Clay Olson, of Gordon & Rees, LLP of Charleston, for Respondent Charleston Exteriors, LLC.

MCDONALD, J.: Builders FirstSource-Southeast Group (BFS) appeals an order granting summary judgment, arguing the circuit court erred in applying a "clear and unequivocal" standard to the analysis of its contractual indemnity language and in finding its claims against certain subcontractors were barred by the statute of limitations. We affirm in part, vacate in part, and remand.

Facts and Procedural History

In developing The Abbey at Spring Grove (The Abbey), a residential community in Berkeley County, Lennar Carolinas (Lennar) contracted with BFS to provide and install windows and doors with associated weatherproofing, flashing, and other necessary components. Two BFS subcontractors, ECC Contracting, LLC (ECC) and Charleston Exteriors, LLC (collectively, Respondents), installed the windows at The Abbey. In 2008, BFS entered a Master Subcontractor Agreement (the Agreement) with ECC. BFS entered an identical Agreement with Charleston Exteriors in 2012.

In October 2014, Patricia Damico and other property owners in The Abbey brought construction defect litigation against Lennar and others (the Damico litigation).1 In November 2015, the property owners amended their complaint to add claims related to the exterior windows. Lennar answered and brought third-party claims against various subcontractors, including BFS. Lennar's action against BFS included claims for indemnification, breach of warranty, breach of contract, negligence, and products liability. BFS answered Lennar's third-party complaint on December 15, 2015.

On December 21, 2018, BFS filed this action claiming Respondents were responsible for "provision of materials and/or services in connection with the

1 See Damico v. Lennar, 437 S.C. 596, 879 S.E.2d 746 (2022), cert. denied, 143 S.Ct. 2581 (2023). installation of the windows and doors of the subject structures" at The Abbey and sued them for equitable indemnification, contractual indemnification, breach of warranty, breach of contract, negligence, and contribution. BFS alleged it "has been subjected to liability and has incurred consequential damages in having to expend attorneys['] fees and costs" in defending itself in the Damico litigation.

In 2019, BFS moved to consolidate this matter with Damico, asserting the facts in controversy were identical and the cases involved common questions of law. ECC moved for summary judgment, arguing BFS's claims were barred by the statute of limitations applicable to contract claims. ECC further challenged BFS's contractual indemnity claims as meritless under the "clear and unequivocal" standard and alternatively argued BFS lacked standing because its claims were unripe. Charleston Exteriors raised similar dispositive arguments.

After a hearing, the circuit court granted Respondents summary judgment on BFS's claims for negligence, breach of contract, breach of warranty, and contractual indemnification. The circuit court found the Agreement's indemnification provisions were neither clear nor unequivocal; thus, BFS could not seek contractual indemnification from Respondents for its own negligence, whether concurrent or sole. The circuit court further found BFS's claims for contractual indemnification, negligence, breach of contract, and breach of warranty were barred by the applicable statute of limitations because BFS filed its action against the subcontractors more than three years after receiving notice of its potential claims. 2 As BFS's remaining non-indemnity claims were not separate and distinct from the claims made in Damico, the circuit court granted summary judgment on this ground as well. The circuit court found BFS's claims for equitable indemnification and contribution should be consolidated with Damico, which at the time of the circuit court arguments had been stayed. The court agreed with BFS that its equitable indemnification claim presented a question of fact and noted the contribution claim had not been challenged at summary judgment.

BFS filed a Rule 59(e), SCRCP, motion, asserting the circuit court erred in applying the statute of limitations to bar some of its claims. In this filing, BFS also addressed the circuit court's interpretation of Concord & Cumberland Horizontal

2 See S.C. Code Ann. § 15-3-530(1) (2005 & Supp. 2024) (providing a three-year statute of limitations for "an action upon a contract, obligation, or liability, express or implied"). Property Regime v. Concord & Cumberland, LLC, 424 S.C. 639, 655, 819 S.E.2d 166, 175 (Ct. App. 2018), stating:

This Court's December 6, 2019 Order correctly finds that the indemnity language at issue does not meet the elevated standard of being clear and unequivocal and thus the Plaintiff cannot maintain indemnification claims for Plaintiff's negligence. Nevertheless, pursuant to Concord and Cumberland the Plaintiff still has valid indemnification claims for Defendants' negligence.

At the hearing on its Rule 59(e) motion, BFS argued the circuit court should consider whether it lacked jurisdiction to hear the summary judgment motions in light of the Damico appeal because all matters affected by the appeal had been automatically stayed. Following this hearing, the circuit court issued an amended summary judgment order, noting BFS had actual notice of its potential claims against the subcontractors as of the date of its December 2015 answer to Lennar's third-party complaint. The circuit court further found the statute of limitations for BFS's contract-related claims began to run upon the filing of this responsive pleading and that these claims were time-barred. The circuit court again found the Agreement's language was confusing and contradictory, and that the indemnity provisions neither clearly nor unequivocally required Respondents to indemnify BFS for its own negligence. BFS filed a Rule 59(e) motion as to the amended summary judgment order, which the circuit court denied.

Analysis

"Rule 56(c) of the South Carolina Rules of Civil Procedure provides that the moving party is entitled to summary judgment 'if the [evidence before the court] show[s] that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.'" Kitchen Planners, LLC v. Friedman, 440 S.C. 456, 459, 892 S.E.2d 297, 299 (2023) (alterations by the court) (quoting Rule 56(c), SCRCP).

I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TNS Mills, Inc. v. South Carolina Department of Revenue
503 S.E.2d 471 (Supreme Court of South Carolina, 1998)
Piper v. American Fidelity & Casualty Co.
154 S.E. 106 (Supreme Court of South Carolina, 1930)
Concord & Cumberland Horizontal Prop. Regime v. Concord & Cumberland, LLC
819 S.E.2d 166 (Court of Appeals of South Carolina, 2018)
First General Services of Charleston, Inc. v. Servicemaster, Inc.
445 S.E.2d 446 (Supreme Court of South Carolina, 1994)
Tillman v. Oakes
728 S.E.2d 45 (Court of Appeals of South Carolina, 2012)
Jones v. Builders Investment Group, LLC
781 S.E.2d 737 (Court of Appeals of South Carolina, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Builders Firstsource-Southeast v. MI Windows And Doors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-firstsource-southeast-v-mi-windows-and-doors-scctapp-2025.