Buford v. Inge Const. Co.

279 S.W. 513
CourtCourt of Appeals of Texas
DecidedNovember 28, 1925
DocketNo. 9426.
StatusPublished
Cited by25 cases

This text of 279 S.W. 513 (Buford v. Inge Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buford v. Inge Const. Co., 279 S.W. 513 (Tex. Ct. App. 1925).

Opinion

JONES, C. J.

Appellee, Inge Construction Company, a corporation, recovered judgment in the county court of Dallas county at law No. 2, against appellee in the sum of $340.10, from which judgment appellant has duly perfected his appeal.

Appellee is engaged in the business of a building contractor, and maintains its office in the city of Dallas. Cedric Burgher is 'the vice president and manager of appellee. Appellant conducts a business college in the city of Dallas. At the time under -inquiry, appel-lee was constructing a building on Main street in the city of Dallas as a contractor, and appellant had arranged to occupy a portion of said building in which to conduct his business college. Certain work required to adapt this space for appellant’s purpose was required to be done by him. This work, in the main, seemed to be' the construction of certain partition walls on the floor of the building to be occupied by appellant, so as to cut off an office, construct a large cabinet, arrange cloakrooms, and to install blackboards, etc. Appellee, through an agreement entered into through its said manager with appellant, performed this work, and'the judgment rendered is a balance claimed by appel-lee to be due it under its said contract. Against this claim, appellant alleged an “accord and satisfaction,” the nature of which was fully alleged in his answer, and will appear from the statement herein.

Appellee’s theory of the case, as disclosed by its petition, and the evidence offered to sustain the allegations of the petition, was that one of its employees received from appellant specifications of the work he wanted done, and that, with these specifications as a basis, submitted a bid of $605.40; that after-wards, and before this bid was acted upon by appellant, appellee’s said manager had a conversation with appellant in which it was disclosed that the specifications did not cover the entire work desired to be performed, but that items of considerable cost had been omitted therefrom. In this conversation, in which these omissions were discussed, the said manager told appellant that it would be better and perhaps cheaper for him to contract with appellee on the “cost plus” plan, under which plan appellant would pay to ap-pellee the cost of material and labor that en *514 tered into the work, and, in addition thereto, pay 8 per cent, thereof for appellee’s services ; that this proposition was accepted, and that on this basis the completed work amounted to the sum of $1,047.60; that an itemized bill for this amount, accompanied by checks and vouchers showing its correctness, was submitted to appellant, and appellant sent a check to appellee in thé sum of $707.50, which left a balance of $340.10 still due appellee, and for the recovery of which this suit was filed.

Appellant’s theory of the case, as disclosed by his pleading and evidence, wad that the specifications furnished to appellee contained all the work required to be done except some minor items, such as a partition in the cloakroom; that, in his conversation with appel-lee’s manager in reference to the said hid, he informed said manager that he would like for appellee to do the work as it was constructing the building, but that its bid was higher than several other bids he had received; that the said manager had admitted that the bid was made high because of certain contingencies that might happen, and that it would be cheaper for him to have the work done by the said “cost plus” plan, and that he believ.ed appellee could save appellant as much as $100 from that bid on the work being done under such plan, and that it would not cost him more than said bid; that, with this assurance, and with the understanding that the limit of the cost under said plan would be the amount of the bid for the work embraced in the specifications, he agreed to the said “cost plus” plan; that he was handed the bill for the work, at his request, by appellee’s said manager, on the street, and that he carried the same to his office, and, as soon as he became acquainted with the amount of the bill, he at once notified the said manager that the bill was entirely too high; that later an interview occurred between him and said manager, in which the differences were unsuccessfully tried, to be adjusted; that soon thereafter he sent appel-lee a check for $707.50, with the stipulation that such was sent as the full amount of the bill for the work, and could only be accepted by appellee as a full settlement of his indebtedness ; that, without notice to him that same was not accepted under the terms of his said offer, it was cashed by appellee, and then he was notified by appellee that he would be held for the said balance.

Appellee suppqrted its theory by competent evidence, which evidence is clear and explicit that the contract entered into was a “cost plus” contract, and that there was no assurance as to what the cost would be. Appellee also established the amount of the claim by vouchers and checks showing what had been actually expended by it in the performance of the said work. Appellant also supported his theory by his .own evidence, corroborated by that of his wife, which evidence would have been sufficient to authorize a finding in his favor as to the character of contract entered into. The check sent by appellant as full payment for appellee’s work was accompanied by a letter, both letter and check bearing date of July 25th, 1923. The check had the following indorsement placed thereon by appellant:

“Indorsement of this check constitutes acceptance in full settlement of all claims.”

The letter is as follows:

“Inclosed find our cheek for $707.50 in full payment of work done in connection with partitions, etc., at 2021% Main street. We have added to your original bid $100, which I consider ample to cover the small additions that were made. The bill for electrical wiring, I would suggest that you take up with Mr. Owens, as we have written him with reference to the $35 bid that was given us for this work. If settlement of this account on this basis is not satisfactory, the matter will have to be arbitrated. I consider that I am paying more than I should, and -I assure you that I am greatly disappointed at the way this entire matter was handled.”

When this check and accompanying letter was received by appellee’s manager, he at once went to the bank on which the check was drawn and had it certified and then deposited it in another bank. Before depositing same, he placed the following indorsement thereon: “Inge Construction Company, by Cedric Burgher, V. Pres.” The check was paid on July 27, 1923. At the time the said manager deposited the check in the bank and took credit for same, 'his attorneys wrote the following letter to appellant, of date July 27, 1923:

“The claim of Inge Construction Company against you in the sum o'f $1,047.60, bearing a credit of $707.50, leaving a balance of $340.10, has been placed with us for attention. ,In accordance with your letter of July 25th, our client has decided to deposit the check and advise you that the settlement is not satisfactory so that the matter can be arbitrated as you suggest. If you are unwilling to remit this balance, please let us know at once, and we will take up with you the question of arbitrating the amount still due. Our client insists that you have had value received and that the amount claimed by it is fully collectible.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mashuda v. Western Beef, Inc.
527 F. Supp. 887 (W.D. Pennsylvania, 1981)
Avent v. Stinnett
513 S.W.2d 89 (Court of Appeals of Texas, 1974)
Jenkins v. Henry C. Beck Co.
440 S.W.2d 85 (Court of Appeals of Texas, 1969)
Southwestern Investment Co. v. Neeley
412 S.W.2d 925 (Court of Appeals of Texas, 1967)
Marsalis v. Garre
391 S.W.2d 522 (Court of Appeals of Texas, 1965)
Industrial Life Insurance Company v. Finley
382 S.W.2d 100 (Texas Supreme Court, 1964)
Brown Supply Co. v. Crabtree
337 S.W.2d 832 (Court of Appeals of Texas, 1960)
Burgamy v. Davis
313 S.W.2d 365 (Court of Appeals of Texas, 1958)
Slaughter v. Temple Lumber Company
307 S.W.2d 108 (Court of Appeals of Texas, 1957)
Ensley v. Spickard
232 S.W.2d 780 (Court of Appeals of Texas, 1950)
Minchen v. Vernor's Ginger Ale Co. of Houston, Inc.
198 S.W.2d 613 (Court of Appeals of Texas, 1946)
Haynes v. Southwest Natural Gas Co.
123 F.2d 1011 (Fifth Circuit, 1941)
Great Western Garment Co. v. Malouf
105 S.W.2d 262 (Court of Appeals of Texas, 1937)
Humble Oil & Refining Co. v. Wood
94 S.W.2d 573 (Court of Appeals of Texas, 1936)
Great Southern Life Ins. Co. v. Heavin
39 S.W.2d 851 (Texas Commission of Appeals, 1931)
King v. Cliett
31 S.W.2d 350 (Court of Appeals of Texas, 1930)
Root & Fehl v. Murray Tool Co.
26 S.W.2d 189 (Texas Commission of Appeals, 1930)
Robertson v. National Spiritualists' Ass'n of the United States
25 S.W.2d 889 (Court of Appeals of Texas, 1929)
Great Southern Life Ins. Co. v. Heavin
21 S.W.2d 1086 (Court of Appeals of Texas, 1929)
Murray Tool Co. v. Root Fehl
16 S.W.2d 316 (Court of Appeals of Texas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W. 513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buford-v-inge-const-co-texapp-1925.