Buffalo Weaving & Belting Co. v. Harrington & Richardson, Inc.

225 F. Supp. 175, 1963 U.S. Dist. LEXIS 7718
District Court, D. Massachusetts·Decided December 31, 1963·No. Civ. A. No. 59-4·Published

Opinion

JULIAN, District Judge.

Plaintiff brought this action to recover damages for alleged breaches of contract. The defendant denies that it committed any breaches and asserts a counter-claim against the plaintiff.

The claims are alleged to arise out of transactions that occurred in 1952 and 1953.

The evidence received at the protracted trial was voluminous.

The issues of liability were severed from those relating to damages and the trial was limited to the issues of liability.

FINDINGS OF FACT

1. The plaintiff, Buffalo Weaving & Belting Company (Buffalo), is a New York corporation having its principal place of business in Buffalo, New York. The defendant, Harrington & Richardson, Inc. (H. & R.), is a Massachusetts corporation having its principal place of business in Worcester, Massachusetts. The amount in controversy exceeds $10.-000 exclusive of interest and costs.

2. On April 3, 1952, the defendant entered into a written contract with the United States for the manufacture and delivery of 100,000 rifles, U. S. caliber .30, Ml, and for the manufacture and delivery of 1,000 sets of spare parts for the rifle (Exh. N, — the prime contract). The contract provided for fixed unit prices for the rifles and for the sets of spare parts. The contract also required the defendant to manufacture or otherwise acquire special tooling suitable for the production of the rifles and the parts.

Payment for the special tooling was to be on a cost reimbursement basis not to exceed a stated ceiling.

The contract required the defendant to deliver 1,000 rifles in January 1953, 1,000 in February 1953, and increasing quantities each succeeding month through November 1953, totalling, in all, 100,000. The contract further required concurrent delivery of one set of spare parts for every 100 rifles.

3. The Court takes notice that at this time the United States was actively engaged in the Korean War. Active warfare did not cease until the signing of an armistice in July 1953.

4. After the award of the prime contract and sometime before July 8, 1952, a man named Fitzgerald who was vice president of Buffalo and general manager of its Philadelphia, Pennsylvania, plant, and a man named Berry who was president of Machines, Inc. (Machines), went together to Worcester, Massachusetts, and confex-red with the purchasing agent of H. & R. At that conference Berry, in the presence of Fitzgerald, tried to obtain subcontract work on the rifle from H. & R. for Machines but was refused. The two had another conference with H. & R.’s purchasing agexxt who made it clear to both that H. & R. would not enter into any contx-actual relations with Machines, and that if any subcontract materialized it would be between H. & R. and Buffalo. Thereafter-, by letter dated July 8, 1952 (Exh. 88), Buffalo quoted prices to H. & R. for the manufacture of six component parts of the rifle and for the special tooling required for their xxxanufacture. By telegram dated July 9, 1952 (Exh. 89), Buffalo quoted prices to H. & R. for the manufactux-e of an additional component part.

[177]*1775. Further negotiations followed and ón August 11 and 12, 1952, H. & R. mailed the following purchase orders to Buffalo at its Philadelphia office:

All the purchase orders enumerated were received by Buffalo in the regular course of mail.

Each of the five components is an essential part of the rifle.

6. At about the time that the first purchase orders were issued, H. & R., in substance, informed Buffalo that the acquisition of the special tooling and the manufacture and delivery of the components were a “crash program.” Because of the urgency of the program and the importance of delivering the completed components to the defendant at the times called for by the delivery schedules, the plaintiff and the defendant, in order to expedite the manufacture of the special tools necessary to manufacture the components, decided to begin performance under the purchase orders before completion of the contract documents and also waived the requirement that the manufacture of special tools was not to be started until purchase order supplements for such tools were issued by the defendant instructing the plaintiff to proceed with their manufacture.

7. Buffalo claims that a collateral oral agreement was entered into between H. & R. and Buffalo sometime prior to September 2, 1952, which, in substance, provided that Buffalo was merely to finance Buffalo’s subcontractors in the performance of the orders issued by H. & R. to Buffalo and to undertake actual performance of the orders only if [178]*178Buffalo’s subcontractors failed to perform. I find on the credible evidence that H. & R. and Buffalo never entered into such an agreement. I further find that at no time either before or after the issuance of the purchase orders in August 1952 did the defendant agree either •orally or in writing, or by its non-verbal conduct, to grant the plaintiff an extension of time to enable the plaintiff to take over the actual performance of the contracts from the plaintiff’s subcontractors, or to transfer operations from a subcontractor’s plant to the plaintiff’s own plants, whether in Alliance, Ohio, or elsewhere, in the event that a subcontractor of the plaintiff failed to perform.

8. Except as stated in paragraph 9 of these findings, the only agreements entered into by H. & R. and Buffalo are set forth in the following writings:

a) the five purchase orders for the manufacture and delivery of the five components (Exh. 2, 4, 6, 8, and 15);
b) the five special tooling orders related thereto (Exh. 1, 3, 5, 7, and 14);
c) the printed terms attached to the ten purchase orders (see Exh. 52 and 53);
d) the supplements to said purchase orders dated November 6, 1952, and November 24, 1952 (Exh. 16, 17, 18, 19, and 29);
e) supplements Nos. 1 and 2, which extended the times for the delivery of the components (Exh. 21, 23, 25, 27, 33, 35, 36, 37, and 38);
f) the special tooling purchase order No. M-4260-T (Exh. 45) consolidating the original five special tooling purchase orders.

9. Sometime before September 9, 1952, H. & R. agreed to deliver certain machine tools to Buffalo for the manufacture of the operating rod assembly. This agreement is evidenced in part by Exhibits 10 and 31.

10. On August 29, 1952, H. & R. informed Buffalo by telegram (Exh. 91) that the purchase order terms and conditions would be amended to conform to those discussed in the minutes of a meeting held on August 14, 1952 (Exh. 90). The amendments finally adopted are set forth in letter supplements to the purchase orders mailed to Buffalo by H. & R. (Exh. 16, 17, 18, 19, 29) and assented to by Buffalo (Exh. 28, 30).

11. By written agreement dated September 2, 1952 (Exh. 54), supplemented by an agreement dated September 19, 1952 (Exh. 55), Buffalo subcontracted all the purchase orders for the components and for the special tooling to Machines, Inc.

12. In subcontracting to Machines the plaintiff acted on its own initiative and responsibility and did not act for the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Buffalo Weaving & Belting Co. v. Harrington & Richardson, Inc., 225 F. Supp. 175, 1963 U.S. Dist. LEXIS 7718 (D. Mass. 1963).

225 F. Supp. 175 (Buffalo Weaving & Belting Co. v. Harrington & Richardson, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.