Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC

CourtDistrict Court, D. Nevada
DecidedApril 7, 2023
Docket2:16-cv-01439
StatusUnknown

This text of Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC (Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC, (D. Nev. 2023).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 DISTRICT OF NEVADA 6 * * *

7 BUESING CORPORATION, Case No. 2:16-CV-1439 JCM (NJK)

8 Plaintiff(s), ORDER

9 v.

10 HELIX ELECTRIC OF NEVADA, LLC,

11 Defendant(s).

12 13 Presently before the court are defendant/counterclaimant Helix Electric of Nevada, LLC 14 (“Helix”)’s three motions in limine. (ECF Nos. 108, 109, 110). Plaintiff/counterdefendant Buesing Corporation (“Buesing”) responded. (ECF Nos. 114, 115, 116). 15 I. INTRODUCTION 16 In August 2015, Helix hired Buesing pursuant to a subcontract for the performance of 17 certain pile driving construction work at a project in Henderson, Nevada (the “subcontract”). The 18 contract required Buesing to install 7,898 piles at a total cost of $313,296.00 in accordance with 19 certain project documents, including a SNWA Ninyo & Moore pile test report. The pile test report 20 contained an analysis on the site, including a soils report. Based on the information in the report, 21 Buesing anticipated that it would install approximately 527 piles per day. 22 Once Buesing began work, it almost immediately encountered soil conditions that were 23 different than those disclosed in the pile test report. After four days of work, Buesing had installed only 500 piles, many of which were damaged and required removal. 24 Buesing subsequently informed Helix that it encountered differing soil conditions, and the 25 parties modified the contract in the amount of $130,000.00 for “pulling and drilling for remediation 26 of piles.” Despite the modification, Buesing encountered ongoing difficulties, and the parties 27 ultimately agreed to temporarily stop installing piles. 28 1 Shortly thereafter, Buesing informed Helix that it could no longer perform the pile work 2 due to the differing soil conditions. In response, Helix sent Buesing a written notice of default for 3 Buesing’s abandonment of the subcontract. The next day, Buesing notified Helix that it would be on the site the following day resolve the issues thwarting remediation efforts. Buesing allegedly 4 did not cure its default, but instead ceased its operations. 5 Several days later, Helix terminated the subcontract, asserting that Buesing failed to 6 perform and abandoned the job. On that same day, Buesing sent a letter to Helix, in which Buesing 7 stated that it had not abandoned the subcontract, but that it could not complete performance without 8 further modification of the subcontract. Thereafter, Helix contracted with another company to 9 compete the pile driving work and did not compensate Buesing. 10 Buesing initiated the instant action, bringing three causes of action: (1) declaratory 11 judgment; (2) breach of contract; and (3) breach of the implied covenant of good faith and fair 12 dealing. Helix filed an answer and counterclaim, asserting the same three causes of action against Buesing. The matter is set for a bench trial on April 24, 2023. Helix now moves the court to 13 exclude certain witness testimony in advance of the trial. 14 II. LEGAL STANDARD 15 “The court must decide any preliminary question about whether . . . evidence is 16 admissible.” Fed. R. Evid. 104. Motions in limine are procedural mechanisms by which the court 17 can make evidentiary rulings in advance of trial, often to preclude the use of unfairly prejudicial 18 evidence. United States v. Heller, 551 F.3d 1108, 1111-12 (9th Cir. 2009); Brodit v. Cambra, 350 19 F.3d 985, 1004-05 (9th Cir. 2003). 20 “Although the Federal Rules of Evidence do not explicitly authorize in limine rulings, the 21 practice has developed pursuant to the district court’s inherent authority to manage the course of trials.” Luce v. United States, 469 U.S. 38, 41 n.4 (1980). Motions in limine may be used to 22 exclude or admit evidence in advance of trial. See Fed. R. Evid. 103; United States v. Williams, 23 939 F.2d 721, 723 (9th Cir. 1991) (affirming district court’s ruling in limine that prosecution could 24 admit impeachment evidence under Federal Rule of Evidence 609). 25 Judges have broad discretion when ruling on motions in limine. See Jenkins v. Chrysler 26 Motors Corp., 316 F.3d 663, 664 (7th Cir. 2002); see also Trevino v. Gates, 99 F.3d 911, 922 (9th 27 Cir. 1999) (“The district court has considerable latitude in performing a Rule 403 balancing test 28 and we will uphold its decision absent clear abuse of discretion.”). 1 “[I]n limine rulings are not binding on the trial judge [who] may always change his mind 2 during the course of a trial.” Ohler v. United States, 529 U.S. 753, 758 n.3 (2000); accord Luce, 3 469 U.S. at 41 (noting that in limine rulings are always subject to change, especially if the evidence unfolds in an unanticipated manner). “Denial of a motion in limine does not necessarily mean that 4 all evidence contemplated by the motion will be admitted at trial. Denial merely means that 5 without the context of trial, the court is unable to determine whether the evidence in question 6 should be excluded.” Conboy v. Wynn Las Vegas, LLC, no. 2:11-cv-1649-JCM-CWH, 2013 WL 7 1701069, at *1 (D. Nev. April 18, 2013). 8 The primary purpose of a motion in limine is to resolve evidentiary disputes without having 9 to present potentially prejudicial evidence in front of a jury. See Pinal Creek Group v. Newmont 10 Mining Corp., No. CV–91–1764–PHX–DAE, 2006 WL 1766494, at *1 (D. Ariz. June 26, 2006). 11 Thus, “in the case of a bench trial, a threshold ruling is generally superfluous.” United States v. 12 Heller, 551 F.3d 1108, 1112 (9th Cir. 2009). The court will be in a better position to rule upon challenges to evidence during trial when 13 there will be a fuller understanding of the issues and evidence in the case. Therefore, the more 14 prudent course in a bench trial is to resolve evidentiary doubts in favor of admissibility. See Shaw 15 v. Citimortgage, Inc., 3:13-cv-0445-LRH-VPC, 2016 WL 1659973 at *2 (D. Nev. April 26, 2016). 16 III. DISCUSSION 17 a. Motion in limine #1 18 Helix seeks to exclude testimony and reports Buesing’s expert witness Philip Coppola 19 (“Coppola”) regarding different soil conditions, asserting that Coppola is not qualified as an expert 20 to render such opinions. 21 i. Expert witnesses Federal Rule of Evidence 702 provides that a witness qualified as an expert may testify if 22 “(a) the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to 23 understand the evidence or to determine a fact in issue; (b) the testimony is based on sufficient 24 facts or data; (c) the testimony is the product of reliable principles and methods; and (d) the expert 25 has reliably applied the principles and methods to the facts of the case.” Fed. R. Evid. 702.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luce v. United States
469 U.S. 38 (Supreme Court, 1984)
Rock v. Arkansas
483 U.S. 44 (Supreme Court, 1987)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
Ohler v. United States
529 U.S. 753 (Supreme Court, 2000)
United States v. Gerald Mark Williams
939 F.2d 721 (Ninth Circuit, 1991)
Boyd v. City and County of San Francisco
576 F.3d 938 (Ninth Circuit, 2009)
United States v. Heller
551 F.3d 1108 (Ninth Circuit, 2009)
Estate of Henry Barabin v. Astenjohnson, Inc.
740 F.3d 457 (Ninth Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Buesing Corporation, an Arizona corporation v. Helix Electric of Nevada LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buesing-corporation-an-arizona-corporation-v-helix-electric-of-nevada-llc-nvd-2023.