Buehler v. Staudenmayer

130 N.W. 955, 146 Wis. 25, 1911 Wisc. LEXIS 91
CourtWisconsin Supreme Court
DecidedApril 5, 1911
StatusPublished

This text of 130 N.W. 955 (Buehler v. Staudenmayer) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buehler v. Staudenmayer, 130 N.W. 955, 146 Wis. 25, 1911 Wisc. LEXIS 91 (Wis. 1911).

Opinion

BabNes, T.

A number of errors are assigned and argued ■on this appeal. But one of them warrants any discussion. The jury intended to permit the defendant to recover on his alleged counterclaim the sum of $90 as damages because of the failure of the plaintiff to do a good and workmanlike job •of cement work at the farm. It found that such sum represented the difference between the reasonable value of the cement work and what its reasonable value would have been had it been done in accordance with the contract. After the verdict the defendant moved to amend his counterclaim by stating the facts necessary to constitute a good cause of action and by increasing the ad daunnum clause from $50 to $97. 'The original pleading was defective in that it did not allege a contract and breach thereof or make any reference to or adopt the allegations of the defensive portion of the answer reciting such facts. The plaintiff opposed the granting of this motion an'd also made a motion to amend his reply to the counterclaim so as to plead acceptance of the work as a compliance with the contract and waiver of any right to claim damages because it was not done as agreed.

The court granted the motion of the plaintiff, and we assume that for this reason it refused to grant the motion of the defendant. If the court was correct in holding that the defendant had waived the right to recover the damages which .he was claiming, it would be futile to allow the amendment [29]*29asked for by him. Tbe original counterclaim was not challenged by a demurrer to its sufficiency or by a demurrer ore temos, and nearly all of tbe evidence tending to show damages was received without objection, and no objection to any of it was taken on tbe ground that tbe counterclaim did not state a cause of action. Under these circumstances we entertain no doubt that tbe trial court would have allowed tbe counterclaim to be amended so as to conform to tbe proofs and to tbe verdict bad it been of tbe opinion that any recovery could be bad on tbe pleading as amended. To bold otherwise would, we think, have amounted to an abuse of discretion.

There was sufficient evidence to warrant the jury in finding as it did in reference to tbe character of tbe work done at tbe farm and in reference to tbe amount of damages suffered by tbe defendant as a result of poor workmanship. Tbe question of acceptance or waiver was not submitted to tbe jury. Such a submission would~be proper under appropriate instructions if there was any dispute as to what tbe facts were which were relied up.on to constitute acceptance. In tbe absence of a finding by tbe jury we would be obliged to presume one by tbe court in support of tbe judgment, under sec. 2858m, Stats. (Laws of 1907,.cb. 316).

So tbe real question in tbe case is: Do tbe facts, construed as favorably to tbe defendant as they reasonably can be, justify tbe conclusion that there was an acceptance of tbe work and a waiver of tbe right to claim damages for tbe breach of tbe contract which provided what tbe character of tbe work should be? In support of tbe conclusion of tbe trial court it is urged that tbe defendant accepted tbe work (1) because be was present while tbe work was being done and knew bow it was being done; (2) because be used tbe concrete wall with knowledge of tbe defective work done; and (3) because be made payments after tbe work was completed and with knowledge of the defective work.

Tbe work consisted of building a foundation wall for a [30]*30barn, a floor or platform for a windmill, and some walks and steps. Tbe defects complained of were that the wall was neither straight, plumb, nor square; that the north wall was two inches too long and the south wall was three inches too short; that the wall was rough and had large holes in it and that a part of it did not set properly; that the cement walks ■cracked badly; and that the floor of the windmill settled, as well as some other minor defects.

The work was completed on November 7, 1907, and the first payment of $80 was made five days later. We do not find any proof that the defendant had actual knowledge of the defects when this payment was made. The evidence to show when the walks began to crack was very indefinite. 'The form or cribbing in which the cement wall was inclosed was not removed until November 15th, so that there was no ■opportunity to discover any defects in the sides of the walls prior to that time. It was easy enough to determine after the building was placed on the wall that either the wall or the building was not a rectangle, but the slight deviation could not have been very noticeable before, and there is no claim that defendant did know of it on November 12th. He had given the plaintiff the correct measurements and had a right to assume that they would be followed. In fact there was ■apparently very little discoverable in the way of defects on November 12th without making a critical examination of the work, and some of the defects were not discoverable on such ■an examination. The fact that the defendant was around while the work was being done we do not consider very significant. There is no pretense that he was an expert in the business of cement construction or that he had any knowledge that improper materials were being used or that the proper proportions of the different ingredients in the construction were not used or that there was an improper mixture of such ingredients. It would be unreasonable to say that, where an ordinary person makes a contract for the con[31]*31struction of a cement wall or walk and stipulates tbat it must be constructed in a good and workmanlike manner, be accepts whatever may be tendered to him simply because he happens to be around while the work is being done, although he has no knowledge that the contract is being violated. So we do not discover any evidence in the record of acceptance up to ■and including the time when the first payment, was made. A second payment of $70 was made on November 21, 1907, and on the 13th of January following the defendant sold.to the plaintiff a load of oats worth $24.50. There was no agreement that this latter amount was to be applied on the cement contract, but the defendant never made any demand for payment for the oats and we will assume that he intended that the amount stated should be applied on the contract. It is undisputed that before the barn had been moved on to the •cement wall and before the second payment was made the defendant called up the plaintiff by telephone and in substance informed him that the work done was not right and did not ■comply with the contract and asked him to come out and inspect it. The plaintiff stated in reply that he could not then do so, but would come later. Thereupon the defendant informed the plaintiff that he would make no further payments ■until the work was made right. The plaintiff did go out to inspect the work the nest day and the parties do not disagree in the essential details as to what took place. The plaintiff does not admit that the defendant found fault with as many things as the defendant says he did, and he does not admit having agreed to do as much in the way of remedying alleged •defects as the defendant asserts that he did, but he does admit 'that he found defects of a somewhat serious nature and that he agreed to remedy at least some of -them. He stated, however, that as the season was far advanced the additional work should be done in the spring and that he would do it at that time, and to this the defendant assented. Plaintiff never went back to do the work which he -admits he agreed to do, [32]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ekstrand v. Barth
83 P. 305 (Washington Supreme Court, 1906)
Trustees of the Monroe Female University v. Broadfield
30 Ga. 1 (Supreme Court of Georgia, 1859)
Moulton v. McOwen
103 Mass. 587 (Massachusetts Supreme Judicial Court, 1870)
Morrison v. Cummings
26 Vt. 486 (Supreme Court of Vermont, 1854)
Buskirk v. Murden
22 Ill. 446 (Illinois Supreme Court, 1859)
Barker v. Nichols
3 Colo. App. 25 (Colorado Court of Appeals, 1892)
Eaton v. Gladwell
66 N.W. 598 (Michigan Supreme Court, 1896)
Johnson County v. Lowe
72 Mo. 637 (Supreme Court of Missouri, 1880)
Pormann v. Walsh
72 N.W. 881 (Wisconsin Supreme Court, 1897)
Pabst Brewing Co. v. City of Milwaukee
105 N.W. 563 (Wisconsin Supreme Court, 1905)
Griffiths v. Cretney
126 N.W. 875 (Wisconsin Supreme Court, 1910)
Gerbig v. Bell
126 N.W. 871 (Wisconsin Supreme Court, 1910)
Hankwitz v. Barrett
128 N.W. 430 (Wisconsin Supreme Court, 1910)
Utah Lumber Co. v. James
71 P. 986 (Utah Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.W. 955, 146 Wis. 25, 1911 Wisc. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buehler-v-staudenmayer-wis-1911.