Buckwalter v. Mannella, No. Cv88 02 62 97s (Sep. 12, 1990)

1990 Conn. Super. Ct. 1930
CourtConnecticut Superior Court
DecidedSeptember 12, 1990
DocketNo. CV88 02 62 97S
StatusUnpublished

This text of 1990 Conn. Super. Ct. 1930 (Buckwalter v. Mannella, No. Cv88 02 62 97s (Sep. 12, 1990)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buckwalter v. Mannella, No. Cv88 02 62 97s (Sep. 12, 1990), 1990 Conn. Super. Ct. 1930 (Colo. Ct. App. 1990).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION On August 31, 1988, the plaintiff, Terry Buckwalter, a contractor, filed a two count complaint which alleged that the defendant homeowners, Ralph David Mannella and Elizabeth Tolles Mannella, had breached a contract for the construction of a new home. The first count of the complaint sounded in contract and the second count alleged unjust enrichment to the defendants. On September 6, 1988, the defendants filed their answer and a counterclaim which alleged that the work had been performed in a defective and unworkmanlike manner. Subsequent to the commencement of trial the plaintiff filed an amended two count complaint, based on the same theories, on April 30, 1990. The case was tried to the court on April 9, April 18, May 9, and May 10, 1990. Thereafter, the CT Page 1931 parties submitted briefs.

Facts

On November 7, 1987, the plaintiff contractor and defendant homeowners entered into a written contract for the construction of a new residence for the defendants in Middlebury, Connecticut. The contract provided:

LORD AND LION HOMES — Terry Buckwalter — does hereby enter into contract to build the new residence of Ralph D. Mannella at Tranquillity Road, Middlebury, Ct. LORD AND LION HOMES — will furnish necessary insurance and Labor to install and perform all work according to the plans of the General Contractor as outlined in contract: 1. complete framing 2. build chimney 3. complete exterior trim including jam and trim for garage door 4. install tyvek 5. install windows 6. install exterior door units 7. install subfloors 8. build and install substairs and platforms 9. install lally columns 10. complete siding 11. complete finish roofing

The total contract price for the above work was $18,750.00. The contract, which was signed by the plaintiff contractor and the defendant, R. David Mannella, did not specify a completion date.

The written contract provided that the plaintiff agreed that all work was to be performed under the approval of the general contractor, Ralph A. Mannella, the father of the first named defendant. The contract also provided that it would be the right of the general contractor to specify construction details. Additionally, the contract provided: "In compliance with the General Contractor's direction and construction details Terry Buckwalter will receive an additional $1,000.00 Bonus when the terms of this contract are completed."

The general contractor's plans specify that one-half by eight inch cedar siding was to be installed on the new residence. According to the plaintiff contractor, one-half by six inch siding is generally used because the wider siding CT Page 1932 can lead to problems including "cupping". According to the plaintiff, a larger shingle has a tendency to warp and cup because of the greater exposure to the elements. However, the plaintiff installed the shingles according to the specifications of the general contractor. It took the plaintiff contractor approximately five to six weeks to install the cedar siding over Tyvek. According to the contractor, he received no complaints whatsoever from either the defendants or the general contractor concerning the installation of the siding.

During the course of construction, the plaintiff contractor did certain additional work ("extras") which had not been provided for in the written contract. The extras included the removal of concrete which had been improperly poured by the concrete contractors and the installation of a garage ceiling. The plaintiff's total charge for all extras was $3,665.00.

Under the terms of the original contract, which was for labor only, the plaintiff contractor was to be paid a total of $18,750.00. The contract provided that the defendant would pay the plaintiff a daily rate of $100.00 per man and $300.00 per day for work completed, payable each Friday. The plaintiff contractor commenced work on November 17, 1987 and completed his work sometime in April, 1988. Pursuant to the terms of the contract, during the course of his work, the plaintiff contractor had been paid $15,800.00 by the defendants. Including the extras, the total contract price was $21,995.00 and as of the completion date, there was a balance due of $7,615.00.

The plaintiff submitted a bill to the defendants at their residence after completion of his work. The defendants agreed to pay all but the bonus clause of $1,000.00. The bonus clause had provided that the plaintiff's work was to be performed "in compliance with the General Contractor's direction and construction details". Because he believed that he had complied with all provisions under the contract including the general contractor provision and because the defendants would not enumerate reasons that he had not, the plaintiff refused the proffered payment. The plaintiff contractor first learned of complaints concerning the quality of his work through his attorney in this matter.

The general contractor, who is the father of the first named defendant, testified that he is retired but had been a general contractor and building manager for a number of years. The general contractor did have experience building smaller homes. The general contractor testified that he CT Page 1933 lived one hour away from the job site and that he visited the same approximately once every week or two weeks, and that he never visited the job site during the actual construction. The general contractor ordered the siding for the residence, but it wasn't his choice, he would have preferred vinyl or the smaller six inch cedar shingles.

The defendant, Ralph D. Mannella, testified that the plaintiff did do extra work on his residence, that he (the defendant) was never told prices for any of this work and that he had therefore assumed that there would be no charge for the extra work. The defendant had made this assumption because of his having helped the plaintiff with some work on the residence during the course of the construction, for example, the installation of Tyvek. The defendant had chosen the one by eight cedar siding because he liked the looks of the wider board. The defendant did recall the plaintiff's approach to him in April, 1988, concerning the remainder of the bill and his (the defendant's) refusal to pay the $1,000.00 bonus.

At trial, the defendants called two experts concerning the quality of the plaintiff's workmanship on their residence. According to the defendants' experts, it is normal for a certain amount of clapboard to crack during the first year after installation. However, the defendants' experts stated that here there has been excessive cracking due to the nailing by the plaintiff contractor. However, in this regard, the Court fully credits the testimony of the plaintiff that the nailing and exposure had been determined by the general contractor and the defendants.

There was also considerable disagreement over whose responsibility it was to sort lumber which had been delivered to the job site. In the present case, the plaintiff contractor had been required to stop his work and sort lumber which had been delivered to the site. The plaintiff's expert's testimony, which is credited by the Court, was that it was the responsibility of the general contractor to provide for such sorting and that if craftsmen at the site were required to sort he would consider this an extra charge.

According to the plaintiff's expert, Russell Choate, a mechanical engineer and general contractor who has built over 20 homes, the prices charged in the present case by the plaintiff contractor for the "extras" were on the low side. Mr. Choate testified that cracking may be caused by wood predisposed to cracking and by the quality of the wood utilized. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coburn v. Lenox Homes, Inc.
441 A.2d 620 (Supreme Court of Connecticut, 1982)
DuBose v. Carabetta
287 A.2d 357 (Supreme Court of Connecticut, 1971)
Charter Oak Estates, Inc. v. Kearney
280 A.2d 885 (Supreme Court of Connecticut, 1971)
Monarch Accounting Supplies, Inc. v. Prezioso
368 A.2d 6 (Supreme Court of Connecticut, 1976)
Bruni v. Behnke
128 A.2d 543 (Supreme Court of Connecticut, 1956)
Scribner v. O'Brien, Inc.
363 A.2d 160 (Supreme Court of Connecticut, 1975)
Johnson v. Flammia
363 A.2d 1048 (Supreme Court of Connecticut, 1975)
Kelley v. Hance
142 A. 683 (Supreme Court of Connecticut, 1928)
Commercial Discount Co. v. Town of Plainfield
180 A. 311 (Supreme Court of Connecticut, 1935)
Automobile Insurance v. Model Family Laundries, Inc.
52 A.2d 137 (Supreme Court of Connecticut, 1947)
Providence Electric Co. v. Sutton Place, Inc.
287 A.2d 379 (Supreme Court of Connecticut, 1971)
First Hartford Realty Corp. v. Ellis
434 A.2d 314 (Supreme Court of Connecticut, 1980)
Burns v. Koellmer
527 A.2d 1210 (Connecticut Appellate Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
1990 Conn. Super. Ct. 1930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buckwalter-v-mannella-no-cv88-02-62-97s-sep-12-1990-connsuperct-1990.