Buck-Leiter Palm Avenue Development, LLC v. City of Sarasota

212 So. 3d 1078, 2017 WL 835326, 2017 Fla. App. LEXIS 2854
CourtDistrict Court of Appeal of Florida
DecidedMarch 3, 2017
DocketCase 2D15-2879
StatusPublished
Cited by3 cases

This text of 212 So. 3d 1078 (Buck-Leiter Palm Avenue Development, LLC v. City of Sarasota) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buck-Leiter Palm Avenue Development, LLC v. City of Sarasota, 212 So. 3d 1078, 2017 WL 835326, 2017 Fla. App. LEXIS 2854 (Fla. Ct. App. 2017).

Opinion

MORRIS, Judge.

Buck-Leiter Palm Avenue Development, LLC (the developer) appeals a final order granting summary judgment in favor of the City of Sarasota (the City). We reverse because the City was not entitled to summary judgment as a matter of law.

I. Background

In June 2006, the City requested proposals for the development of City-owned land on Palm Avenue in downtown Sarasota. In March 2007, the City selected the developer pursuant to the proposal process. The City and the developer engaged in extensive negotiations, and on November 13, 2007, the City and the developer entered into an Initial Redevelopment Agreement (IRA).

The IRA states that its provisions “shall be carried forth and incorporated into a subsequent final Redevelopment Agreement.” The IRA describes in detail the parties’ respective obligations regarding the development project. It provides that the project will be developed in two phases, with phase I consisting of a 453-space parking structure, a 77,000-square-foot hotel, 18,500 square feet of retail space, and a paved parking area. Phase II will include 150 condominium units, an additional 6000 square feet of retail space, and an expansion of the parking garage. The IRA further describes details of the project, such as the operation and maintenance of the project and the sharing of costs and revenues. The IRA also provides that the developer will lease land from the City and be granted an option to purchase the land, with a formula for the computation of lease *1080 payments and the purchase price for the option tract in phase II. Further, the IRA contains provisions regarding financing of the project with the issuance of bonds, attainable housing units, the developer’s payment of taxes, the developer’s compliance with code and regulations, the conceptual architectural design approval, terms for disposition of the property, the project schedule, title to the property, and notices.

The IRA also, states that “each party shall be entitled to written notice of and the opportunity to cure any alleged defaults” and that “[fjailure of a party to enforce a covenant or condition contained in this [IRA] shall not be deemed a waiver of any future default or breach, whether or not of a similar character.” The IRA further provides that “[i]n the event of any litigation between the parties in respect to this [IRA] or the Redevelopment Agreement, the prevailing party shah be entitled to reasonable attorney’s fees and costs.” Last, the IRA provides that “[i]n the event that the parties hereto have not approved and executed a final Redevelopment Agreement by February 15, 2007, then this [IRA] shall terminate and shall have no farther force and effect.”

On March 21, 2008, the City approved a conceptual architectural design for the project. After further extensive negotiations on key issues, on April 7, 2008, the City and the developer executed an Open Issue Term Summary (the summary) that addressed parking, access during phase II construction, infrastructure costs, architecture efforts, and timing. On June 2, 2008, the City acknowledged that significant impediments existed that prevented the parties from arriving at a final agreement, and the City Commission imposed a deadline of July 21, 2008, “as the date to determine if the City and [the developer] can reach” a final agreement. At a special meeting of the City Commission on July 17, 2008, the City Commission voted to accept the City’s staff ■ recommendation that the “current redevelopment proposal [is] unacceptable,” effectively terminating the negotiations with the City and the developer and the developer’s involvement in the project.

In June 2010, the developer filed a complaint against the City for breach of contract, promissory estoppel, and imposition of equitable liens. In June 2012, the trial court granted the City’s motion for summary judgment on the third count. In December 2013, the developer was granted leave to file an amended complaint alleging breach of contract. In the amended complaint, the developer alleged that the terms of the IRA indicate that the IRA was intended to be binding and enforceable by both parties. The developer also alleged that the summary constituted a further binding agreement between the parties. The developer alleged that “[t]hese documents formed a binding contract which required both parties to do certain specified tasks and to negotiate the ‘open terms’ in good faith to finalize the agreement” and that the City breached the IRA by “voting to terminate discussions and failing to obtain an economic analysis of [the developer’s] proposal.”

In February 2015, the City filed a motion for summary judgment, arguing that the IRA did not constitute a final, binding contract. The City asserted that there were outstanding issues requiring negotiation and that the IRA was merely an agreement to agree, which is unenforceable as a matter of law. The City also argued that the summary was not binding on the City because the city manager did not have authority to bind the City to a contract and that the summary was not a final contract because it contemplated a final development agreement. The City further contended that even if a contract *1081 was created, the developer breached the land lease provision. The developer responded that when all of the evidence is considered in the light most favorable to the developer, the court could not conclude that no contract was formed. The developer argued that if the parties “did not intend to be bound [by the IRA,] there would have been no need for notice provisions, default language and prevailing party attorney’s fees in the event of litigation.” As for the City’s alternative claim that the developer breached the contract, the developer argued that this was a question of fact to be determined by the jury.

On June 3, 2015, the trial court entered an order granting the City’s motion for summary judgment. The trial court ruled that the “undisputed facts and record evidence demonstrate that no contract was formed by virtue of the expired [IRA] and the subsequent [summary]” and that “no breach of contract could have occurred.” On July 23, 2015, the trial court entered final judgment in favor of the City.

II. Analysis

On appeal, the developer argues that the trial court erred in granting summary judgment because questions of fact exist regarding whether a contract was formed and whether the IRA expired. The developer contends that the trial court found that no contract was formed but also that the IRA had expired; the developer argues that the trial court’s ruling is illogical because a contract cannot expire if it was not formed.

We review de novo a trial court’s granting of summary judgment. Volusia County v. Aberdeen at Ormond Beach, L.P., 760 So. 2d 126, 130 (Fla. 2000). A movant is entitled to summary judgment if the pleadings and the summary judgment evidence show “that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fla. R. Civ. P. 1.510(c). In reviewing a summary judgment ruling, we must consider the evidence in the light most favorable to the nonmoving party, and if the record raises the slightest doubt that an issue might exist, we must reverse the summary judgment. Atria Grp., LLC v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CHAKRA 5, INC. v. THE CITY OF MIAMI BEACH
District Court of Appeal of Florida, 2023
Wesner v. JMS Marinas, LLC
224 So. 3d 912 (District Court of Appeal of Florida, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
212 So. 3d 1078, 2017 WL 835326, 2017 Fla. App. LEXIS 2854, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buck-leiter-palm-avenue-development-llc-v-city-of-sarasota-fladistctapp-2017.