Buck Kreihs Co. v. United States

331 F. Supp. 1173, 1971 U.S. Dist. LEXIS 11717
CourtDistrict Court, E.D. Louisiana
DecidedSeptember 9, 1971
DocketCiv. A. No. 70-1573
StatusPublished
Cited by1 cases

This text of 331 F. Supp. 1173 (Buck Kreihs Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buck Kreihs Co. v. United States, 331 F. Supp. 1173, 1971 U.S. Dist. LEXIS 11717 (E.D. La. 1971).

Opinion

ALVIN B. RUBIN, District Judge:

Kreihs contracted with the United States on July 30, 1965, to recondition vessels in the New Orleans area. Article 41 of the contract imposed a ten per cent profit limitation. Pursuant to this contract, eight job orders were issued in 1966, and the work done in that year amounted to $1,871,826.50. Thereafter the United States through the Maritime Administration, audited Kreihs’ books and billed it for $54,437.96, an amount determined to be the amount of profits realized by Kreihs in 1966 in excess of 10% of the contract price on these job orders. The Maritime Administration agreed to accept $45,717.01, pending resolution of a dispute concerning depreciation (which is not here involved). Kreihs seeks refund of this sum. It concedes that this sum is the correct amount due the government under Section 41 of the contract, but contends that the Section was not validly incorporated into the agreement.

I. The Nature of the Plaintiff’s Payment

The United States contends that the plaintiff’s voluntary payment of the amount demanded precludes a suit for refund. Generally, “money voluntarily paid under a claim of right, and with knowledge of the facts by the payor, cannot be recovered back on the ground that * * * there was no liability to pay in the first instance.” American Metal Co. v. M/V Belleville, S.D.N.Y. 1968, 284 F.Supp. 1002. However, it is equally well recognized that the payment is involuntary if failure to pay will lead the government to take steps that are likely to cause the financial ruin of the debtor, Richfield Oil Corp. v. United States, 9 Cir. 1957, 248 F.2d 217.

While there is some dispute about the exact circumstances surrounding the payment, I find that, when the U. S. made its claim, plaintiff’s president protested vigorously. The protests culminated in a conference with Mr. Schumm, a government contracting officer. At this conference, Mr. Schumm stated that Kreihs would be placed on the government-wide debt list if it failed to pay. In addition, Mr. Schumm wrote Kreihs to that effect. The purpose of this threat was to coerce Kreihs to pay; it had that result. The company paid, protesting all the while, asking that its funds be put in escrow, and stating that it intended to file suit immediately to recover, as it in fact did.

Kreihs related that Mr. Schumm further informed him that the list was circulated to all government agencies, and that, if the company were listed, it would receive no more government work. He testified that his company could not survive without such work. The evidence does not support this interpretation of the effect of a listing; apparently the sole result would have been to enable other government agencies to withhold money due Kreihs. But, knowing nothing of the inner workings of the Maritime Administration, Kreihs was justifiably apprehensive that the listing was a threat to his business welfare, and would have greater impact than merely the collection of funds claimed. Indeed, it is difficult to understand Mr. Schumm’s insistence if he did not intend to create apprehension, for a simple inquiry would have ascertained that the funds could readily have been collected by off-set.

[1175]*1175Accordingly, I find that, as in the Richfield Oil Corporation case, supra,, there was an understanding “between the United States on the one hand and [Buck Kreihs], on the other, * * * that [Buck Kreihs] might pay the demanded sum under protest and then proceed by suit to recover it back in order to litigate the question of its liability. * * * ” See Richfield Oil Corp. v. United States, 9 Cir. 1957, 248 F.2d 217, 224. It would, therefore, be improper to bar Buck Kreihs from maintaining this action.

II. The Renegotiation Act and the Contractual Profit Limitation

A preliminary issue may be easily disposed of. One article of the original master contract (Article 34) incorporated the profit limitation procedure of the Renegotiation Act by reference. The defendant has contended that this article was deleted by pen and ink prior to the execution of the contract with the request that a different profit limitation procedure was substituted. Kreihs argues that Article 34 was not eliminated and that two profit limitation procedures are provided for in the contract. It appears that the document was executed in multiple originals that differ in this regard: in one the paragraph is deleted, in the other it is not. Hence, each party has produced a copy of the contract that supports its position.

But we need not attempt to determine which copy reflects the intention of the parties. Both parties concede that the Renegotiation Act is applicable to contracts of the type involved here. Since Section 104 of that act, 50 U.S.C. App. § 1214, requires inclusion of a renegotiation clause in contracts of this kind, it is of little consequence whether the clause was physically left in the document or deleted from it. The only issue is whether in contracts of this type renegotiation is the exclusive profit limitation procedure, or whether the parties may contract for an alternative procedure. The search for an answer to this simple question leads into a statutory maze constructed by a legislative Daedalus.

Under the Renegotiation Act excess profits are determined on the basis of receipts, accruals and costs from all applicable contracts performed during the fiscal year. 50 U.S.C. App. § 1213(e). Article 41 of the master contract involved in this dispute proves for a ten per cent maximum profit and operates on a contract-by-contract basis. The plaintiff argues that the Renegotiation Act, where applicable, provides the exclusive method of profit limitation, and that contractual agreements to the contrary are invalid.

The statutory scheme negates this contention. The Act is made applicable to all contracts with certain government departments performed after a certain date. 50 U.S.C. App. § 1212(a). The Maritime Administration, MAR AD, with whom Kreihs contracted, is one such department, 50 U.S.C. App. § 1213(a). The Board is permitted to exempt from the renegotiation procedure “any contract * * * if, in the opinion of the Board, the provisions of the contract are otherwise adequate to prevent excessive profits. * * *” 50 U.S.C. App. § 1216(d) (3).

Section 1216(d) (3) assumes that a government contract may contain provisions adequate to prevent excessive profits other than renegotiation requirements. This clearly indicates that the contracting authority may bargain for some other kind of profit limitation. See Newport News Shipbuilding and Dry Dock Co. v. United States, 1967, 179 Ct.Cl. 97, 374 F.2d 516, 526-527.

This interpretation is buttressed by statutory language that intimates that on some occasions a contractual provision cannot supplant the renegotiation procedure. Section 1212(e) provides in part, “notwithstanding any agreement to the contrary, the profit-limitation provisions * * * of section 505(b) Merchant Marine Act, 1936, * * * shau not apply * * * to [1176]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buck Kreihs Company, Incorporated v. United States
462 F.2d 234 (Fifth Circuit, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
331 F. Supp. 1173, 1971 U.S. Dist. LEXIS 11717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buck-kreihs-co-v-united-states-laed-1971.