Buccino v. Cable Technology, Inc., No. Cv 88-39541 (Sep. 17, 1990)

1990 Conn. Super. Ct. 1973
CourtConnecticut Superior Court
DecidedSeptember 17, 1990
DocketNo. CV 88-39541
StatusUnpublished

This text of 1990 Conn. Super. Ct. 1973 (Buccino v. Cable Technology, Inc., No. Cv 88-39541 (Sep. 17, 1990)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buccino v. Cable Technology, Inc., No. Cv 88-39541 (Sep. 17, 1990), 1990 Conn. Super. Ct. 1973 (Colo. Ct. App. 1990).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION Plaintiffs allege a breach of contract — two lease agreements for an industrial building — the first lease being executed in 1982 for the rental of 19,000 square feet, and in the following year the parties leased an additional 11,000 square feet in the same building. The building in question was originally built circa 1860 and in 1916 an annex or addition was added on. Although the building is old it was, and remains, structurally sound. Between 1962 and 1980 the Buccinos used the premises for a machine shop. Cable Technology operated a wire and cable processing facility.

The plaintiffs claim some eighteen various breaches and the defendants have filed a counterclaim.

The issues were tried to the Court, which makes the following findings and judgments.

1. Rent: The plaintiffs claim non-payment of rent for the CT Page 1974 months of August and September, 1986, and for the first eight days of June, 1987. The defendants had made their rental payments timely until a disagreement arose over parking and the cost of making changes to the sprinkler system. That dispute led to the service of a Notice to Quit alleging as reasons failure to maintain the property, failure to maintain the sprinkler system, and failure to paint the second floor ceiling, all in violation of conditions of the leases. Upon receipt of the Notice to Quit Cable Tech stopped paying rent for the months of August and September, 1986. Thereafter they resumed paying use and occupancy per Court order. Plaintiffs mischaracterize monies owed for August and September, 1986 as rent. It is in fact use and occupancy which Cable Tech owes, and freely admits they do. The Buccinos, who ultimately lost their summary process action, are not entitled to interest on use and occupancy which their action precipitated. They are entitled to recover $9,199.48 for those two months.

The Court finds that the defendants remained in possession of the premises until June 8, 1987, when the key was returned to Mr. Buccino. Although Cable Tech had moved its equipment out of the building by May 30, 1987, it did not communicate to the Buccinos, who lived across the street from the property in question, that they were no longer in possession. It was not the plaintiff's obligation to determine whether the defendants had completely moved out. A couple of automobiles belonging to employees of Cable Tech remained on the property after May 30, 1989, and Cable Tech retained the key. It is fairly the responsibility of the tenant to notify the landlord that he has vacated. Holmes v. Freeman, 23 Conn. Sup. 504 (1962). Accordingly the plaintiffs shall recover $1,226.56 for unpaid rental for the first eight days of June 1987.

2. Waste: The plaintiffs allege that Cable Tech left the property extensively damaged and in an overall poor condition. The various claims will be taken up separately, as follows:

A. Beams and Walls: The Court is not persuaded that nicks, gouges or scratches to beams and walls went beyond the ordinary wear and tear to be reasonably expected from five or six years of industrial use. The plaintiffs seek $11,000.00 to repaint the area occupied by Cable Tech. This issue rests on a factual determination to be made by the trier and the Court does not find the plaintiffs are entitled to compensation for this claim.

B. Fluorescent Lights: Some of the lights were not in CT Page 1975 working order when Cable Tech vacated. Mr. Buccino testified that he purchased and installed replacement lights for those that were invariable while Mr. Cariglia of Cable Tech testified that some lights were so old that replacement parts could not be found. He also testified that some lights were left stored on the premises when they took occupancy. As to this item, the Court does not find , the plaintiffs have proved that the defendants caused damage by abuse or unreasonable lack of due care.

C. Windows: Plaintiffs claim $155.25 for material and labor to replace broken windows. They submitted a receipt for glass purchased in December 1987, some six months after Cable Tech vacated. Mr. Cariglia stated they repaired any broken windows before they left. The Court is not persuaded that any broken windows were left by the defendants.

D. Compressor: When Cable Tech leased the property there was a compressor which was in working order. When :it failed the defendants installed a new compressor which it took when it vacated the premises. Cable Tech had used the old compressor for about one year when it failed. It was originally installed years before the defendants took possession. The plaintiffs seek $1,300.00 — the cost of a new compressor. The Court does not find they are entitled to that under the facts of this case.

E. Plumbing Repairs: Plaintiffs claim the drinking fountains and bathrooms were left filthy and in disrepair, and seek $789.00 for this item. Buccino testified that a toilet had to be replaced and submitted a check in the foregoing amount made out to a plumber. As in many of his claims, he submits no invoices to corroborate what the check covered, nor was there any other corroboration, for example, from the plumber. The validity of his claim is questioned and his offer of proof does no satisfy those questions. It is, of course, the plaintiff's burden to prove their damages and to prove the their claims are fair and reasonable. They have not met that burder.

F. Metal Door: This is a claim for $348.68 to replace a door allegedly left damaged. The door may have been as old as the original building. A photograph appears to show some damage to the door jamb, however the plaintiffs submitted no evidence of the cost to repair or its value. The door itself appears to be intact. The Court declines to award the cost of a new door to replace one which could be more than 100 years old, and which may, in fact, still be serviceable.

3. Personal Property Removed by Cable Tech: Plaintiffs CT Page 1976 claim the defendants took scaffolding, a cabinet, a table, a window frame and skid boxes. The Court finds the plaintiffs have sustained their burden of proof only as to the filing cabinet and awards $125.00 for said item.

4. Reinstallation of Office Partitions: When Cable Tech moved into the building, it relocated an office by moving some partitions and adding some new ones. The partitions were basically 2' x 4's for framing, and panelling nailed to the frame. They installed a dropped ceiling, a tile floor and electrical service to the new office area. The office was left intact when they vacated. Mr. Cariglia testified the cost of building the new office was approximately $600.00. The plaintiff seeks $8000.00 to replace or restore the original one. Again there is a question about the validity of the claim and little or nothing in the way of corroboration. Plaintiff's Exhibit II, a quotation from the AR Company is of minimal probative value and the Court would have to indulge in speculation as to a fair and reasonable amount to move the off ice to its original location. The building is essentially a factory loft and office partitions can be put up in any of a number of locations in accordance with the desires of a particular tenant. As with Cable Tech, this should not be a major undertaking and involves primarily relocating framing and paneling. The Court believes the claim of $8,800.00 is exaggerated and unwarranted by the evidence.

5. Boilers: According to the terms of the lease Cable Tech was required to maintain, repair and service the steam boilers. The plaintiff Buccino testified the boilers did not work after Cable Tech left and that it cost him $2,298.54 for necessary boiler repairs. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holmes v. Freeman
185 A.2d 88 (Connecticut Superior Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
1990 Conn. Super. Ct. 1973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buccino-v-cable-technology-inc-no-cv-88-39541-sep-17-1990-connsuperct-1990.