Bryant v. Bigelow Carpet Co.

131 Mass. 491, 1881 Mass. LEXIS 302
CourtMassachusetts Supreme Judicial Court
DecidedOctober 17, 1881
StatusPublished
Cited by19 cases

This text of 131 Mass. 491 (Bryant v. Bigelow Carpet Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bryant v. Bigelow Carpet Co., 131 Mass. 491, 1881 Mass. LEXIS 302 (Mass. 1881).

Opinion

Morton, J.

In considering this case we must assume as established the facts found by the auditors. In order to intelligently discuss the questions of law raised, it seems necessary to make a statement of the principal facts.

[496]*496Prior to 1845, the Clinton Company, predecessors in title to the Bigelow Carpet Company, owned and occupied for manufacturing purposes a mill-site and dam upon South Meadow Brook, in Clinton, at the easterly end of a pond, flowed by the dam, known as Clinton Pond. Northerly of Clinton Pond was another pond called Mossy Pond, which was a self-contained pond without inlet or outlet, and not connected with the waters of said brook nor in any way affected by the flowage of the Clinton Company. In 1845 the Clinton Company formed its plans, and late in that year or early in 1846 began operations to increase its power and capacity for storage of water by raising its dam to such height as to raise the water of Clinton Pond about thirteen or fourteen feet above its- then level. For this purpose the company acquired by sundry deeds from time to time the ownership of, or rights of flowage over, the various parcels of land which would be covered by the water so raised, and established a water level or flowage line, with reference to which its dam, waste-way and other works were designed and constructed. The level or line so fixed was at the height of the top of a certain beam in the waste-way which was then constructed, beneath which were flash-boards for retaining or drawing down the waters of the pond to this level, and it was not intended or designed in the construction of the works of the Clinton Company that the water should, even in case of freshets, exceed this line by more than a-few inches.

The construction of the dam at the height thus fixed would cause the waters of Clinton Pond to flow back into Mossy Pond, and, as the level of the flowage line established as above stated was about seven or eight feet above the level of the natural bank of Mossy Pond at its northeasterly end, would cause the water so raised to flow over that bank and down a steep descent into and through a valley below, in which the tannery of the plaintiffs was situated.

The Clinton- Company, for the purpose of retaining the water at this point, purchased in April 1846 the land then forming the natural-bank of Mossy Pond, and built upon it an embankment "or -iktaining-daln^heremafter called Mossy Pond dam, the breaking' of ' which' caused the.-disaster which is the subject of this suit.

[497]*497The new dam and waste-way of the Clinton Company were completed in the fall of 1847, and Mossy Pond dam was built in March 1847, at about the same time as the main dam; and the waters of Clinton Pond were so far raised in the spring of 1847 that boats could pass from it into Mossy Pond, but it was not flowed to its full height until 1848.

At about the same time when the Clinton Company was engaged in building its new dam, the Worcester and Nashua Railroad Company was engaged in laying out and constructing its railroad. Its act of incorporation was passed March 5, 1845; its route in Clinton was established by vote of its directors on November 7, 1846, and its location was filed March 4, 1848. The railroad, as located and constructed, crossed South Meadow Brook by an embankment of from twenty to thirty feet in height at a point just above where that brook entered Clinton Pond as it was prior to 1846, and thence ran easterly along the northerly side of that pond. This embankment was partly built in 1847, and completed in the spring of 1848. In building it, the railroad company constructed two culverts, designed for the passage of the water from the north to the south side of the railroad, and through which alone the waters of South Meadow Brook could pass, said embankment being otherwise of solid earth filling. These culverts were located at a point more than seventy-five feet westward from the point where the natural stream of the brook crossed the line of the railroad, and the bottom of the culverts was from two to three feet above the surface of the brook in its ordinary stage, and the natural earth at the entrance of the culverts, over which the water must flow to enter them, was two or three feet above the bottom of the culverts. The natural bed of the brook where it crossed the line of the railroad was filled up so that the water of the stream was not only diverted from its natural course, but raised above its natural level about five feet and accumulated to that height against the embankment of the railroad without any reference to or aid from the dam of the Clinton Company below. And this accumulation in time of high water would cause the water to flow over the northeast bank • of Mossy Pond in its natural condition. The flowing of Clinton Pond by the new dam to the height of the established level of flowage raised the water to [498]*498the height of six or seven feet above the top of these culverts. These culverts were designed to act as submerged culverts, and .were Constructed in view of, and as adapted to, the plan of the Clinton Company to raise the pond by the new dam as it was in fact built; and, in regard to their location and construction, the constructing engineer of the railroad company consulted with the agent and hydraulic engineer engaged in constructing the dam of the Clinton Company, and they were determined upon such consultation, and the Clinton Company and the railroad company respectively built their works, railroad and culverts with the full understanding of the plans and purposes of each other, as those plans and purposes were actually carried out. The area of the water-shed furnishing water to the ponds on the north side of the railroad was about five times that of the water-shed furnishing water to the pond on the south side.

The Bigelow Carpet Company purchased the property of the Clinton Company on November 13, 1863, and has since used, as its reservoir and source of water power, the ponds on both sides of the railroad. On March 26, 1876, owing to a storm the two preceding days, there was a great accumulation of water in the ponds, the water in the pond north of the railroad standing more than two feet higher than the water in the pond south of the railroad. It finally rose so as to flow over the top of Mossy Pond dam, broke through and carried away the dam, and the. waters were precipitated upon the plaintiffs’ tannery situated in the valley below. For the injury thus done them- the plaintiffs brought this suit against the railroad company and the Bigelow Carpet Company.

The auditors have found that the storm, and all the operations of nature attending it and contributing to raise the waters of Mossy Pond and to produce the disaster, were not extraordinary, but were such as might at any time be reasonably expected to occur, and which might and ought to be anticipated and provided for by reasonable precaution. They have also found that the defendants, and each of them,, were negligent in the construction, maintenance and management of their respective works, and that the negligence of each contributed to the disaster and to the injury-resulting therefrom to the plaintiffs.

[499]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Clark-Aiken Co. v. Cromwell-Wright Co. Inc.
323 N.E.2d 876 (Massachusetts Supreme Judicial Court, 1975)
Hoosac Tunnel & Wilmington Railroad v. New England Power Co.
42 N.E.2d 832 (Massachusetts Supreme Judicial Court, 1942)
Towner v. City of Melrose
25 N.E.2d 336 (Massachusetts Supreme Judicial Court, 1940)
Maki v. New York, New Haven & Hartford Railroad
199 N.E. 760 (Massachusetts Supreme Judicial Court, 1936)
Bratton v. Rudnick
186 N.E. 669 (Massachusetts Supreme Judicial Court, 1933)
Lapeer County Road Commissioners v. Markley
245 N.W. 496 (Michigan Supreme Court, 1932)
Goede v. City of Colorado Springs
200 F. 99 (D. Colorado, 1912)
Arnold v. C. Hoffman & Son Milling Co.
119 P. 373 (Supreme Court of Kansas, 1911)
Wm. Tackaberry Co. v. Sioux City Service Co.
154 Iowa 358 (Supreme Court of Iowa, 1911)
Darks v. Scudder-Gale Grocer Co.
130 S.W. 430 (Missouri Court of Appeals, 1910)
Feneff v. Boston & Maine Railroad
82 N.E. 705 (Massachusetts Supreme Judicial Court, 1907)
Clement v. Crosby & Co.
111 N.W. 745 (Michigan Supreme Court, 1907)
Boston Belting Co. v. City of Boston
67 N.E. 428 (Massachusetts Supreme Judicial Court, 1903)
Chicago, Bock Island & Pacific Railway Co. v. Andreesen
87 N.W. 167 (Nebraska Supreme Court, 1901)
Orchard Place Land Co. v. Brady
53 Kan. 420 (Supreme Court of Kansas, 1894)
City of Kansas City v. Slangstrom
53 Kan. 431 (Supreme Court of Kansas, 1894)
City of Kansas City v. Brady
52 Kan. 297 (Supreme Court of Kansas, 1893)
Frazer v. Bigelow Carpet Co.
4 N.E. 620 (Massachusetts Supreme Judicial Court, 1886)

Cite This Page — Counsel Stack

Bluebook (online)
131 Mass. 491, 1881 Mass. LEXIS 302, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bryant-v-bigelow-carpet-co-mass-1881.