Bruson Heights Corp. v. State

281 A.D. 371, 120 N.Y.S.2d 73, 1953 N.Y. App. Div. LEXIS 3055
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 11, 1953
DocketClaim No. 30244
StatusPublished
Cited by6 cases

This text of 281 A.D. 371 (Bruson Heights Corp. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bruson Heights Corp. v. State, 281 A.D. 371, 120 N.Y.S.2d 73, 1953 N.Y. App. Div. LEXIS 3055 (N.Y. Ct. App. 1953).

Opinion

Bergak, J.

The claimant Bruno, President of Bruson Heights, and the State of New York entered into a five-year lease for two stories of a new building in Queens County which the lessor was to construct. The lease was dated May 28, 1948, but the State approved it July 1st. The rented premises were to be used for an office of the Division of Placement and Unemployment Insurance of the Department of Labor. The rent was $92,400 a year.

The time of State occupancy was governed by two separate provisions. In one the landlord undertook to commence construction ” of the building “ as soon as possible”. He Avas to “ folloAV to completion ” Avith reasonable dispatch ” to have the premises available ” to the State October 1, 1948.

There was a provision to take care of the possibility that the premises would not be ready then. If there were delays ‘ ‘ beyond the Landlord’s control ” so that the October 1st occupancy cannot be realized ”, the lease was to commence when the premises shall be completed”. There was a further provision that if the premises were not available before December 1, 1948 “ then this lease shall be null and void ”.

These two provisions, of course, can be read consistently together. The marked elasticity in the delays “ beyond the Landlord’s control ” clause could be regarded as sharply ended by the “ null and void ” clause operative if occupancy were not available December 1st. But in dealing with language of this kind a great deal depends on what the parties intend and how they act toward performance.

Certainly one clause which liberally carries the time of occupancy to the day the premises shall be completed ” could very well have been intended in the event of delays beyond the landlord’s control, to have extended beyond December 1st, and the null and void ” clause could reasonably have been regarded as operative only if there were no delays beyond the landlord’s control. The final act of executing the lease on July 1st, only.five months before the “ null and void ” clause would be effective for an entirely new building which the lease describes as “ the proposed building to be erected ” has a significant additional bearing on intent.

The claimant argued on the trial that he had the premises ready for the State’s occupancy on December 1st and claimant himself testified unequivocally that it was substantially ready then. But the Court of Claims has found, and the proof is overwhelming on the point, that the premises were not ready then, and the finding of the court that they were not ready until February 12, 1949, seems to us entirely well-founded.

[374]*374Upon the finding that the premises were not ready December 1st, the State argues that under the “ conditional limitation ” of the lease it became “ void ” on that date. Where one party insists upon strict compliance with the time provisions of a contract, it is the usual rule that he himself must have done his part of the agreement on time and must not have contributed to the other party’s delay.

Two cases illustrate the rule. One is Watson & Co. v. Graves Elevator Co. (202 App. Div. 10) decided in this department in 1922 where the court considered an elevator construction contract with a three-week provision. It was held that it was for the jury to say as a question of fact whether the acts of the party insisting on the strict operation of the time clause had in turn helped to cause the delay. The other is Dannat v. Fuller (120 N. Y. 554), where the same rule was applied to the erection of a circular sawmill. Language of conditional limitation is always construed in aid of the intention of the parties (Bovin v. Galitzka, 250 N. Y. 228, 232).

Nothing decided or said in Allegany Oil Co. v. Bradford Oil Co. (21 Hun 26) or in 551 Fifth Ave v. Wellingbrook (199 Misc. 500) offers any authority to the contrary. In the Bradford case the owner of land had executed a lease to an oil driller with a provision that it be void if drilling were not started at a stated date. The date passed without the condition being met and the lessor who continued in possession leased the premises to another oil driller who maintained an action against the first lessee and the lessor to quiet title and for equitable relief. The question presented was, even conceding that the first lease was void, the procedural right of a second lessee to maintain the action “in the nature of bills quia timet”. (Pp. 27, 30.)

In the Wallingbroolc case the landlord had not shown itself entitled to possession on summary proceedings because it had not shown the conditions upon which a long-term lease rested had been met and which would have given the right to possession.

The Court of Claims has found that “ by its conduct ” the State “ contributed to the delay in the completion of the building ”. This finding also seems to us to be sustained fairly by the record. The lease required that the landlord install electrical fixtures in “ locations to be indicated by ” the State, and to install “ a suitable number ” of convenient electrical outlets for the State’s use. It was further provided that “ at the direction of ’ ’ the State the claimant was to subdivide the floors with ceiling-high partitions.

[375]*375Thus the State had the aErmative obligation, as the building went up, of showing where the electrical fixtures were to go and of giving the claimant a partition plan, each in time to fit in with the work in progress. A partition plan was given to the claimant’s architect before the lease was signed, but the architect testified that he understood that this was tentative and was to be changed. This seems to be corroborated by a letter to claimant’s architect from the acting director of business administration of the division on August 3, 1948, which indicated that the size of our smaller oEces ” had not been fixed and would depend on the locations of the window mullions.

Claimant’s architect also testified that no layout of the partition plan was ever received from the State and that the partitions were ultimately installed according to the plan which preceded the lease. The court readily could have found that the uncertainty in which such plans were left contributed to claimant’s delay.

On July 26th claimant’s architect wrote the State asking for information about the electric layout for which the State was required to give directions. This subject was likewise dealt with in the acting director’s letter of August 3d. He called attention to the fact it would be diEcult to submit “ a precise layout ” but he felt that a conference with another State oEcer and the architect “ within the next thirty days ” might result in working out the problem without “ a definite layout plan ”.

Two months later, October 6th, claimant wrote the State calling attention to the “ repeated requests ” for an electric layout and stating that this was ‘‘ holding-up all electrical work ”. The next day the layout was sent by the State with a letter of enclosure that “ We regret the unavoidable delay

The State having obligated itself by contract to “ indicate ” the locations of electrical fixtures, this last letter giving the plan and expressing regret at the “ unavoidable delay ” was nearly two and one-half months after the architect’s request of July 26th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lager Associates v. City of New York
304 A.D.2d 718 (Appellate Division of the Supreme Court of New York, 2003)
Tov Knitting Mills, Inc. v. Starr Realty Co.
148 A.D.2d 526 (Appellate Division of the Supreme Court of New York, 1989)
Walter Sign Corp. v. State
31 A.D.2d 729 (Appellate Division of the Supreme Court of New York, 1968)
Engelberg v. Morris
25 Misc. 2d 409 (Long Beach City Court, 1960)
Schwartz v. Donnenberg
10 Misc. 2d 490 (New York Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
281 A.D. 371, 120 N.Y.S.2d 73, 1953 N.Y. App. Div. LEXIS 3055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bruson-heights-corp-v-state-nyappdiv-1953.