Brundage v. Home Savings & Loan Ass'n

39 P. 666, 11 Wash. 277, 1895 Wash. LEXIS 294
Washington Supreme Court·Decided March 1, 1895·No. No. 1383·Published·Cited by 13 cases

Opinion

The opinion of the court was delivered by

Andeks, J.

The appellant is a corporation, organized and existing under the laws of the State of Minnesota, and was, at all times hereinafter mentioned, doing business in this state at the city of Spokane. The object for which the association was incorporated was, according to its charter, “ to assist its members to buy real estate, and build, enlarge or repair houses, paying for the same in weekly or monthly installments, and to accumulate funds from payments on stock subscribed by its members, and to loan such funds to its members on approved real estate security, or the paid up stock of its members.” It appears that, under its charter and the laws of Minnesota, it is empowered to loan its funds only to its members. It also appears that on or about July 28, 1892, the respondents made and signed an application for membership in this association, and subscribed for one hundred and sixty shares of its “running,” on installment, stock, and [279]*279agreed to abide by the terms and conditions of its charter and by-laws. The association thereupon issued and delivered its certificate for said shares of stock to the respondents, who thereby became members of said association. About the time respondents made their application for membership and subscribed for the stock above mentioned, they executed and delivered to the association a written application for a loan of sixteen thousand dollars, which they represented they desired for the purpose of paying off and discharging an encumbrance upon their property, situated upon the northwest corner of Monroe street and College avenue, in the city of Spokane, and erecting thereon a one-story brick building, to cost five thousand dollars. The association advanced the sum of sixteen thousand dollars to the respondents, and also the further sum of $3,200, for the purpose aforesaid, to secure which sums the respondents, on August 19,1892, executed and delivered to the appellant association two mortgages on the above mentioned property, one for'$16,000 and the other for $3,200, both of which -were recorded on the following day. Instead of erecting the building mentioned in their application for a loan to the appellant; the respondents entered upon the construction of a building of an entirely different character and of much greater cost, having two stories and a stone basement, not contemplated in the original plan for the building. When the building was partially erected they found they had not sufficient funds to complete it; that it was open and exposed to the elements and was being greatly damaged, and that liens to the extent of about three thousand dollars had been filed against the property. Being so circumstanced, the respondents urged the appellant to advance sufficient money to properly complete the building, and offered to give additional [280]*280security for the payment thereof. After some hesitation, the appellant agreed to advance the further sum of $7,500, and respondents, to secure this sum, executed a third mortgage covering the property upon which the other two mortgages were given and other property known as the Brundage block, on Post street, and also their homestead in Spokane. This mortgage, so far as the Brundage block was concerned, was subject to a first mortgage held by the defendant bank in the sum of ten thousand dollars. To further secure the sums advanced and owing, the respondents executed to appellant, simultaneously with this last mentioned mortgage, an agreement reciting that it was executed to secure the payment of the mortgages above mentioned, and in order to secure this loan, and providing that the rents and income should be collected and received by the defendant association and applied to the reduction and payment of the mortgages above mentioned; to the expense of caring for said property and collecting and disbursing said rents and paying light and water rates, and making repairs which the mortgagee might deem necessary to have made; to the payment of any other liens existing against the property which the appellant might deem advisable to have paid; and until all such sums were paid, the appellant was to “ take and hold the exclusive possession of all the property herein mentioned;” to rent any of said property upon such terms and conditions as seemed best to appellant; to make leases for such times and upon such terms as appellant might deem best for its interests; to care for the said property in such manner as appellant might deem proper; to employ such agents as it deemed proper, who were to have full power and authority, under the direction of appellant and at the expense of respondents, to do any and all [281]*281things in regard to the said property which the appellant might deem proper to do; to apply the moneys received as above stated and to return to the plaintiffs any moneys remaining in its hands after the foregoing application had been made; and at least once in every six months to render a true and itemized statement of all moneys received and disbursed.

This agreement was duly acknowledged and properly recorded in the auditor’s office of Spokane county. Before the expiration of the six months within which the appellant was, under the provisions of the contract, to furnish an itemized statement, the respondents instituted this action, praying for the appointment of a receiver, for the restitution and possession of the property, for five thousand dollars damages for the withholding thereof, for $2,750, the value of rents and profits, and for such other and further relief as to the court might seem just and proper.

The complaint alleges, in substance, that on the 31st day of March, 1893, the respondents were the owners in fee and seized and possessed and entitled to the possession of the property described in the complaint; that while so seized and possessed and entitled to the possession of said land and premises, the defendant did, on the day and year aforesaid, without right or title, enter into and upon the same, and oust and eject plaintiffs therefrom, and ever since that day has willfully withheld, and still withholds, the possession thereof, to plaintiffs’ damage in the sum of five thous- and dollars; that the value of the rents and profits of said land and premises from the 31st day of March, 1893, and while the plaintiffs have been excluded therefrom, is $2,750; that on the 31st day of March, 1893, a pretended agreement was prepared by defendant; whereby it was sought to have the plaintiffs deliver [282]

Free access — add to your briefcase to read the full text and ask questions with AI

Brundage v. Home Savings & Loan Ass'n, 39 P. 666, 11 Wash. 277, 1895 Wash. LEXIS 294 (Wash. 1895).

39 P. 666 (Brundage v. Home Savings & Loan Ass'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ekstrom v. D. Dierssen, Inc.
40 P.2d 138 (Washington Supreme Court, 1935)
Doggett v. Johnson
251 P. 145 (Montana Supreme Court, 1926)
Gahagan v. Wisner
247 P. 965 (Washington Supreme Court, 1926)
Keyes v. Citizens State Bank
224 P. 2 (Washington Supreme Court, 1924)
State ex rel. Silver Basin Mining Co. v. Superior Court
188 P. 384 (Washington Supreme Court, 1920)
Brayton & Lawbaugh v. Monarch Lumber Co.
169 P. 528 (Oregon Supreme Court, 1917)
Grays Harbor Commercial Co. v. Fifer
166 P. 770 (Washington Supreme Court, 1917)
Keane v. Kibble
154 P. 972 (Idaho Supreme Court, 1915)
Bergman Clay Manufacturing Co. v. M. L. Bergman
131 P. 485 (Washington Supreme Court, 1913)
Union Boom Co. v. Samish Boom Co.
74 P. 53 (Washington Supreme Court, 1903)
City of Spokane v. Amsterdamsch Trustees Kantoor
50 P. 1088 (Washington Supreme Court, 1897)
Sengfelder v. Hill
47 P. 757 (Washington Supreme Court, 1897)
Larsen v. Winder
44 P. 123 (Washington Supreme Court, 1896)