OPINION

SANDERS, Judge.

This appeal involves the question of the right to enforce a mechanic’s lien.

In October, 1977, the Plaintiffs-Appellants, R. D. Brumit and R. W. Brumit, d/b/a B&B Investment Company, entered into a contract with Consortium Construction Company for the construction of a Judy’s hamburger restaurant in Elizabeth-ton. The Plaintiffs were to pay Consortium $114,777 for the construction of the building. Construction was to start within seven days after a building permit was issued and to be completed within 90 calendar days.

Consortium let a number of subcontracts on the job including one to the Defendant-Appellee, Graybeal Glass Company, Inc. The testimony fails to show what the Defendant’s, Graybeal’s, subcontract was for but the exhibits indicate it consisted of some bronze glass with frames, five sets of 3'0 X 7'0 doors, two windows and a transom, for which it charged $5,601.79. It submitted one bill to the contractor on April 27, 1978, and its final bill on May 25. The building was completed in May except for the small item here in dispute and the place was open for business between May 30 and June 2.

The Plaintiff filed three separate notices of completion of improvements as provided in T.C.A. § 64-1145. The first notice was filed on May ■ 15. After that date some paving was done around the building and a second notice was filed on June 12. At a later date the attorney representing a lending institution which was financing the building questioned the acknowledgment on the previous notice and a third one was filed on July 11.

The Defendant did not give notice it was claiming a lien within 10 days after the filing of either of the notices by the Plaintiffs, as required by T.C.A. § 64-1147.

On or about August 10 one of the Plaintiffs called the Defendant and told one of its officers there was a door that needed adjusting and requested they send a workman out to complete the work. In response to this call a workman was sent out and he did some work on the door and perhaps other work but the record fails to disclose what it was.

In October the Plaintiffs had learned the contractor, Consortium, had not paid all of its subcontractors. The Plaintiffs were still holding some funds due under the contract price and on October 9 they filed a bill of interpleader in the circuit court against the contractor and four subcontractors and tendered into court $8,407.10 and asked the court to make a distribution of the funds.

The Defendant was not a party to this suit but on October 10 it filed a mechanic’s lien on the property under T.C.A. § 64-1101, et seq.

On January 15 the Plaintiffs filed an amendment to their interpleader complaint interpleading the Defendant and three additional subcontractors and at the same time paid into court an additional $11,477.70 which they had held as retainage under their contract with Consortium.

Upon the hearing of the interpleader case it was determined that the funds paid into court were sufficient to pay approximately 75% of the claims of all of the subcontractors. All of the other subcontractors accepted the prorata payment except the Defendant, Graybeal Glass Company, Inc. It insisted it was entitled to a lien on the property for the remaining portion of its claim.

[523]*523This issue was tried before the circuit judge who found in favor of the Defendant and allowed it a lien on the property for $1,256.81. The Plaintiff has appealed and presented the following issues:

“I. Whether the trial court erred as a matter of law in finding that the telephone conversation between one of the Plaintiffs-Appellants and an employee of Defendant-Appellee regarding the correction of defective work served to renew the period of time within which Defendant-Appellee could file its lien.
“II. Whether the trial court erred as a matter of law in finding that the lien of Defendant-Appellee was valid because it was filed within ninety (90) days of the Notice of Completion filed by Plaintiffs-Appellants.
“III. Whether the trial court erred as a matter of law in finding that the lien of Defendant-Appellee was valid even though no action to enforce same pursuant to T.G.A. § 64-1115 was commenced within ninety (90) days after Notice of Lien was given.
“IV. Whether the trial court erred in considering the validity of the lien of Defendant-Appellee when Defendant-Appel-lee had filed no action to enforce said lien.”

In his determination of the case the trial court said: “Gentlemen, the Court finds that by a preponderance of the evidence in this matter that the Graybeal lien is valid, really for two reasons. First of all, the Court notes that within the ninety day period of the third Notice of Completion the lien was actually filed within ninety days. Second, the Court is of the opinion that the telephone call by Mr. Brumit which is not denied and is testified to positively by Mr. Graybeal of August 10th of 1978 serves to renew the period of time within which the lien could be filed.”

We most respectfully disagree with the trial court in its findings. However, we need to go further for a proper disposition of the case.

Addressing first the question of whether or not the Defendant’s lien was filed within 90 days of the Plaintiffs’ third notice, the third notice was given on July 11 and the Defendant’s lien was filed on October 10, which is 91 days. So if the court was considering July 11 as the date of completion of the building, the lien was not timely filed.

As to the proposition that the August 10 telephone conversation served to renew the period of time within which the lien could be filed seems, to be without precedent. We have been cited to no authority, nor have we found any, that would indicate that a request by an owner of property for a contractor to correct or complete his work would have any bearing on when the lien should be filed. It is the performance of the work that is controlling.

This brings us to consideration of what work was performed. The witness for the Defendant did not go to the premises and had no personal knowledge of what work was done. He says an employee was sent to the job on two days and worked about six hours each day. He also said some materials were sent to the job but was unable to say what they consisted of except he said it was metal. He estimated the cost of labor and materials at about $325. The witness for the Plaintiff testified the only work to be done was the adjustment of a “squeaky” door. He said there were some screws out of the door or the threshold. The Defendant made no charge for the work or materials furnished. The statement which the Defendant made out in connection with the work read as follows: “Repaired doors-furnished equipment to complete contract. Charged on original bill-No charge.”

The Plaintiffs rely upon the case of Cooper v. Hunter, Tenn.App., 569 S.W.2d 852, as support for their insistence that the work performed by the Defendant on August 10 was trivial and insufficient to relate the date of completion of the work to that date, and we agree.

We think it is significant that the Defendant’s billing shows that the only labor performed was “Repaired doors.” The [524]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weill v. Evans Lumber Co. (In Re Johnson)
25 B.R. 889 (E.D. Tennessee, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
609 S.W.2d 521, 1980 Tenn. App. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brumit-v-graybeal-glass-co-tennctapp-1980.