Brucker v. Manistee & Grand Rapids Railroad

130 N.W. 822, 166 Mich. 330, 1911 Mich. LEXIS 521
CourtMichigan Supreme Court
DecidedMarch 31, 1911
DocketDocket No. 80
StatusPublished
Cited by5 cases

This text of 130 N.W. 822 (Brucker v. Manistee & Grand Rapids Railroad) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brucker v. Manistee & Grand Rapids Railroad, 130 N.W. 822, 166 Mich. 330, 1911 Mich. LEXIS 521 (Mich. 1911).

Opinion

Hooker, J.

The plaintiffs contracted with defendant to grade a railroad; their compensation to be by the yard for fills and cuts, and by the acre for clearing land. They performed a portion of the contract, and defendant finished the work. The declaration is in assumpsit for damages for the breach of the contract, and on the common counts for work and labor done and materials furnished; A trial was had and a verdict and judgment for the plaintiffs followed. Defendant appealed.

Defendant asserts:

First. That the trial judge allowed the jury to find that the defendant and its engineers were guilty of fraud or gross or serious error, which deprived plaintiffs of a share of their legitimate earnings, previous to the time that defendant took over the work.
Second. That the defendant by its engineers fraudulently and negligently failed to lay out the work, and fraudulently compelled the plaintiffs to work disadvantageously to their damage.
Third. That the defendant wrongfully took over the work, whereby the plaintiffs were deprived of profits. Error is assigned upon the ground that there was no testimony tending to prove these things, and they should not have been allowed to go to the jury.
Fourth. Defendant claims that the plaintiffs should not have been allowed to recover, under the declaration and in this form of action, the value of personal property taken from plaintiffs when it took over the work.
Fifth. Error is assigned on the refusal of the court to compel plaintiffs to elect whether they would seek to recover under the contract or upon the quantum meruit.
Sixth. Error is predicated on the refusal to grant a new trial.
Seventh. A fatal variance between the declaration and proofs on the subject of the right to recover for personal property of the plaintiffs taken by defendant.
Eighth. Error is assigned upon several points that will be alluded to later if it is found necessary.

This work was begun under a written contract which contains somewhat exceptional provisions in relation to the rights of defendant, regarding the conduct of the work, the binding effect of directions and estimates of the [333]*333defendant’s engineer, and his decisions on controversies growing out of the contract and the dealing of the parties. We do not set forth the contract, which is long, but will refer to its provisions as it shall become necessary in our discussion of the questions raised. It required, that the work be completed on or before May 30, 1905.

On August 2, 1905, the defendant being dissatisfied at the noncompletion of the work, and plaintiffs being out of funds, the parties executed an agreement, which we include in this opinion. It is as follows:

“Agreement made this 2d day of August, 1905, by and between Brucker & Roberts, parties of the first part, and Manistee & Grand Rapids Railroad Company, party of the second part, witnesseth that: Whereas, said parties of the first part have been doing work under a certain contract executed between them and second party and dated December 5, 1904, and they have received from time to time payments of money under estimates made by the chief engineer of second party, and there is still unfinished work to be performed under said agreement; and, whereas, the first parties, in order to fully complete the work under said contract and in accordance therewith, desire second party to advance to them the amount of three thousand dollars ($3,000.00) for which no estimate has yet been made by the said engineer of second party, and said party is willing to make said advance by way of loan to said first parties in order to insure the faithful completion of said work: Now, therefore said second party agrees to advance and loan said amount of three thousand dollars ($3,000.00) to said first parties for the purpose of assisting them in fully completing said work, the said sum to be repaid to second party out of the moneys yet to be realized by first parties under said contract. In consideration thereof, first parties agree that said entire plant belonging to said first parties and now being used upon said work, consisting of 10 western dump cars; ■£• mile 30 lb. railroad track; 17 No. 3 wheel scrapers; 18 drag scrapers; 1 buggy and harness; 1 blacksmith outfit; 1 camp outfit complete; 1 pile driver and tools connected therewith — shall be mortgaged and pledged to said second party to secure the payment of said three thousand dollars, and that said second party shall have possession of said plant until said work is fully com[334]*334pleted. Said first parties further agree to promptly go forward with said work, and have the roadbed thereof fully completed by the 15th day of September, 1905, in strict accordance with the provisions of said contract, and in the event that said work is not fully completed in accordance with said contract by September 15, 1905, then, and in that case, said Brucker & Roberts agree that the railroad company may complete the said work itself or engage other contractors to complete said work, and that said railroad company or other contractors engaged by it to complete said work shall have the use until said work is completed of all of the said plant, tools, etc., herein described. It is further agreed that from time to time said engineer of said second party shall make estimates of the work as it progresses and that said first parties shall receive payments therefor under and in accordance with the terms of said contract.”

On August 23, 1905, defendant took possession of plaintiffs’ tools, etc., and proceeded with the work, completing it on December, 11, 1905. The action was brought in 1908. The plaintiffs claim that they were wrongfully prevented from fully performing the contract, and claim the right to recover the value of the work actually done by them and not paid for, at a price not exceeding the contract rates, upon the common counts. This, according to the plaintiffs’ brief, amounted to upwards of $6,000 and interest. There were other items based on the common counts for work done, such as extra work provided for in the contract, and extra work caused by changing the line of road. The special count was for damages arising from the conduct of the defendant, in hindering, delaying and preventing the completion of performance and may be divided into two clasees, one of matters growing out of the first contract only, and the other arising after the second agreement was made, and these are alleged to be based on fraudulent conduct, and collusion between defendant and its engineer, and gross and serious error on their part which deprived plaintiffs of their legitimate earnings. This latter included the taking of plaintiffs’ property, i. e., tools, etc.

[335]*335We will discuss the case by topics in accordance with the propositions in defendant’s brief, but perhaps not in the same numerical order.

First Topic. “Is there any evidence in the case which properly takes it to the jury upon the proposition that defendant or its engineers were guilty of fraud or gross or serious error which deprived the plaintiffs of their legitimate earnings under the contract before the work was taken over by the defendant ? ”

(a) There was testimony from which fraud might be inferred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson’s Vehicle Sales, Inc v. Omc-Lincoln
287 N.W.2d 247 (Michigan Court of Appeals, 1979)
Busam Motor Sales v. Ford Motor Co.
203 F.2d 469 (Sixth Circuit, 1953)
J. R. Watkins Co. v. Rich
235 N.W. 845 (Michigan Supreme Court, 1931)
Isbell v. Anderson Carriage Co.
136 N.W. 457 (Michigan Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.W. 822, 166 Mich. 330, 1911 Mich. LEXIS 521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brucker-v-manistee-grand-rapids-railroad-mich-1911.