Brown v. WellTech, Inc.

769 S.W.2d 637, 110 Oil & Gas Rep. 521, 1989 Tex. App. LEXIS 666, 1989 WL 28197
CourtCourt of Appeals of Texas
DecidedMarch 29, 1989
DocketNo. 08-88-00175-CV
StatusPublished
Cited by1 cases

This text of 769 S.W.2d 637 (Brown v. WellTech, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. WellTech, Inc., 769 S.W.2d 637, 110 Oil & Gas Rep. 521, 1989 Tex. App. LEXIS 666, 1989 WL 28197 (Tex. Ct. App. 1989).

Opinion

[638]*638OPINION

KOEHLER, Justice.

This is an oil and gas suit brought by the operator, H.L. Brown, Jr., against the driller, WellTech, Inc., for damages arising out of the loss of an oil and gas well and the drilling of a replacement well, and a counterclaim brought by the driller against the operator on a sworn account. Following a jury trial, judgment was rendered denying the operator any recovery on his claim and awarding the driller the sum of $153,108.95 together with prejudgment interest against the operator on the sworn account. From such judgment, both parties appeal. We reverse and render.

Brown is an independent oil operator doing business in Midland, Texas. In 1981, Brown acquired a lease in Lea County, New Mexico. The lease had an existing well on it that had been previously drilled to 9,700 feet, plugged and abandoned. Brown decided initially to deepen the well, known as Shell State No. 1, by an additional 3,000 feet, which was carried out successfully by another driller not a party to this lawsuit. Brown, encouraged by the results, then decided to deepen the well by another 700 feet in hopes of encountering another formation. Brown contacted Well-Tech, an oil field service company, and the parties then entered into an oral agreement whereby WellTech agreed to furnish the rig, certain equipment and the crew to drill the well 700 feet deeper at a price of $5,850.00 per day for the first five days and $5,300.00 per day thereafter. On or about March 5, 1983, WellTech’s crew arrived at the well site and began work on the project. On March 12, 1983, while the crew was in the process of pulling the drill pipe out of the hole, the elevators which held the pipe came open and the pipe string fell back into the hole. Unsuccessful efforts were made by the WellTech crew under the direction of a “fisher” employed by Brown to retrieve — or fish — the pipe from the hole. As a result of the materials remaining in the hole, the well was lost and unrecoverable. Upon concluding that the well could not be saved, Brown authorized another company to drill a replacement well.

Brown’s trial pleadings alleged damages resulting from the loss of Shell State No. 1 and the drilling of the replacement well on theories of negligence, breach of express and implied warranties, deceptive trade practices, and breach of an alleged agreement by WellTech to pay for “the cost and expense of recovering the hole as long as they stayed in the casing....” In addition to a general denial, WellTech asserted defenses of contributory negligence, unavoidable accident and “day work” allegations amounting to a kind of “respondent superi- or” relationship between Brown and Well-Tech’s crew. In its counterclaim, WellTech alleged a sworn account for “goods and materials” sold and delivered to Brown while its crew was at the well site. Both parties sought their attorney’s fees.

Testimony during the trial centered around what kind of contract was actually entered into by the parties. Brown contended that WellTech had contracted to complete the entire project, i.e., by drilling the well 700 feet deeper, while WellTech asserted that the parties had agreed on a “day work” contract whereby Brown paid WellTech at the daily rate and had the overall control of WellTech's rig, equipment and crew and as such, Brown should bear the risk and the loss that occurred. The jury, in answers to the questions submitted to it, found no negligence by either party, and further found that WellTech did not “fail to perform ... [the services it was retained to perform] ... in a good and workmanlike manner by failing to properly close the elevators,” and that it did not “fail to perform such services in a good and workmanlike manner by continuing to use the elevators after they discovered the elevators would not always close properly.” Brown did not plead a breach of contract theory on the overall agreement nor was there a request for a trial amendment or jury questions for breach of contract. WellTech did not request any questions on its sworn account. Neither party requested a question relating to the nature of the contract, i.e., whether WellTech had agreed to deliver a completed well or was working [639]*639on a strict day work basis only. Brown was refused a requested question with instructions relating to whether the WellTech crew was acting as employees of Brown and WellTech requested a question on its attorney’s fees, which was refused.

In his four points of error, Brown avers that the trial court erred in entering a take nothing judgment against him and a judgment in favor of WellTech on its claim for the reasons that: (1) the evidence conclusively established that WellTech had agreed to deepen the well and had failed to do so without fault of either party and therefore, Brown was entitled to a judgment as a matter of law on WellTech’s breach of contract; (2) since it was conclusively established that WellTech had failed to complete the well as required by the agreement, it was not entitled to recover on its sworn account; (3) WellTech had failed to request any jury questions on its sworn account and therefore, there was nothing in the verdict to support its recovery; and (4) the question tendered by Brown and refused by the court relating to whether WellTech’s crew was acting as employees of Brown should have been given if there was a fact issue concerning Brown’s right to recover for WellTech’s breach. For its part, WellTech claims that the judgment is proper since Brown failed to request any jury questions on contract, and the evidence conclusively established its right to recover on the sworn account. In its sole cross-point, WellTech asserts that the court erred in failing to submit a question on its attorney’s fees.

The parties to this appeal do not challenge the findings of the jury on either legal or factual sufficiency grounds. Since neither party requested an appropriate jury question relating to the nature of the contract, there is no finding on this subject. It is fundamental that failure to request a special issue or issues necessary to support an independent theory of recovery provides no basis for a favorable judgment on that theory and nothing for the appellate court to review unless that theory of recovery was conclusively proved by the evidence. Tex.R.Civ.P. 273 and 278 (the latter formerly a part of Rule 279). Hunt Construction Company v. Cavazos, 689 S.W.2d 211, 212 (Tex.1985); Akin v. Dahl, 661 S.W.2d 911, 913 (Tex.1983); Hearn v. Frazier, 241 S.W. 2d 171 (Tex.Civ.App.—Eastland 1951, no writ). There were no findings by the court in the judgment or elsewhere to support the judgment and the parties cannot rely on the provisions of Tex.R.Civ.P. 279 to supply any necessary implied findings. Indust-Ri-Chem Laboratory, Inc. v. Par-Pak Company, Inc., 602 S.W.2d 282, 289 (Tex.Civ.App.—Dallas 1980, no writ). See 3 R. McDonald, Texas Civil Practice sec. 12.36.1, et seq. (rev. 1983).

Since both parties now claim that the evidence in the case conclusively established their respective positions, we must look at all of the evidence to determine whether either party did as a matter of law prove its position. An issue is conclusively established when the evidence is such that there is no room for ordinary minds to differ as to the conclusion to be drawn from it. Triton Oil and Gas Corporation v. Marine Contractors and Supply, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abraxas Petroleum Corp. v. Hornburg
20 S.W.3d 741 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
769 S.W.2d 637, 110 Oil & Gas Rep. 521, 1989 Tex. App. LEXIS 666, 1989 WL 28197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-welltech-inc-texapp-1989.