Brown v. Simonis (In re Simonis)

205 B.R. 939
CourtUnited States Bankruptcy Court, S.D. California
DecidedMarch 19, 1997
DocketBankruptcy No. 96-01433-JH; Adv. No. 96/90291
StatusPublished

This text of 205 B.R. 939 (Brown v. Simonis (In re Simonis)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Simonis (In re Simonis), 205 B.R. 939 (Cal. 1997).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW, and ORDER

JOHN L. PETERSON, Bankruptcy Judge.

In this adversary proceeding, after due notice, trial was held on December 2, 1996, on the Complaint to Determine Debt to be Nondisehargeable filed by Plaintiff, Ethan D. Brown (“Brown”) against Debtor/Defendant, Philip Simonis (“Simonis”), on May 6, 1996. The complaint alleges several grounds for non-dischargeability of Brown’s claims. At trial, however, Brown presented a case based solely on 11 U.S.C. § 523(a)(6). Both parties appeared represented by counsel. The parties first argued their respective positions on Brown’s motion for summary judgement, dated November 11, 1997, and received by the Court on November 12,1997. At close of oral arguments the Court found that at least one outstanding issue of material fact remained — to wit, whether Simonis injured Brown without just cause or excuse — and denied the motion for summary judgment. Brown testified on his own behalf, and introduced the testimony of Simonis. Simonis testified in defense. Exhibits 1-8, 9A-9M, 10,12-17,18A-18B, 19, 20, and 22, as well as A, B and D, were admitted into evidence. At close of trial the Court granted the parties ten days to submit proposed findings of fact and conclusions of law. Such filing deadline having now passed, the matter stands ripe for decision. Upon review of the record, the Court finds for Simonis.

I. FINDINGS OF FACT

Simonis and Brown entered into a written contract in which Simonis agreed to perform certain renovations on Brown’s home in Ramona, California. (Exhibits 1A and IB). Si-monis signed the writing on May 3, 1993, as “General Contractor.” Notwithstanding this designation, however, Simonis testified, and Brown does not dispute, that Simonis prepared the contract pro forma to satisfy the lender financing Brown’s remodel. (Tr. p. 103). In performing the contract, Brown acted as the “owner/builder,” obtain any permits and disbursing all funds for supplies, materials and labor. Simonis acted as subcontractor hiring laborers and supervising [941]*941work on the ground. (Tr. p. 104). In his role as owner/builder, Brown followed the terms of the written agreement only roughly. When making purchases, Simonis testified without dispute that Brown often upgraded building materials. Simonis seldom had control or prior knowledge over Brown’s choice of materials and supplies. When Simonis did make purchases, Brown would reimburse him only if he provided a receipt.

The written terms of the contract provide Brown would pay Simonis $38,260 for work described in the writing. (Tr. p. 18; Exhibits 1A and IB). The agreement also contemplated amendment of the contract price based on extras and other changes that Brown might request, providing for written modification if such changes occurred. The parties did not honor these provisions. (Tr. p. 103-104). The contract provided for progress payments, which the parties recorded on the back of the document. Next to each entry appears Simonis’ initials. (Tr. p. 75; Exhibit IB). By October 1,1993, Brown had made a total of $45,931.03 in progress payments, (Tr. p. 21; Exhibit 1C), when the parties met to discuss progress on the renovation. (Tr. p. 22). At the meeting, Simonis told Brown that Simonis should have the work finished in a week or two. Then, Brown added up the totals paid on the contract, and for the first time realizing how much he had spent on the project, informed Simonis that Brown had overpaid him, and that Simonis would have to complete the job without further remuneration.

On October 5, 1993, after Simonis continued to ask for additional payments, Brown sent Simonis a letter outlining Brown’s position. (Tr. pp. 23, 76; Exhibit 3). Upon receipt of this letter, Simonis left the job. Later, on October 14, 1993, Simonis made a written response to Brown’s assertions of overpayment, calculating that, because of changes in the original contract requested by Brown, Simonis had put $2,142.00 worth of extras into the job. (Tr. p. 24, 76-77; Exhibit 4). Brown wrote back to Simonis in reply to these assertions on October 18,1993. (Tr. pp. 24, 77; Exhibit 5). The letter informed Simonis that even with the extras, Brown had still overpaid him by $4,236.00, and that the contract listed at least a dozen items Simonis had failed to finish. (Exhibit 5).

In the meantime, after Simonis walked off the project, Brown reported Simonis conduct to the state board overseeing contractor licensing. (Tr. p. 24). The board told Simonis to get back on the job and finish the work. (Tr. p. 78). As a result of Brown’s report to the state board, Simonis and Brown negotiated a “finish agreement.” (Tr. pp. 25, 78-79; Exhibit 6). In the agreement, Brown and Simonis specify, as of October 26,1993, a list of 13 “items to be completed for the satisfaction of the contract” between the two “signed May 3, 1993.” (Exhibit 6). No mention appears in the finish agreement, however, of any additional monies owed Simonis by Brown on the contract. The only mention of further payments appears in the provisions for payment $1,000.00 to Simonis if he completes the 13 items before November 10, 1993, with an exception for inclement weather. Invocation of the weather exception eventually extended the completion date to December 5, 1993. (Id.) In negotiating the agreement, Simonis never raised an issue of whether Brown owed him any money under the original construction contract. (Tr. pp. 26, 80). In addition, the two signed no other written agreements in connection with the project. (Tr. pp. 31, 79).

Finally on December 16, 1993, with the work provided for in both the May contract and the October finish agreement still not completed, Brown sent Simonis a letter of termination. (Tr. pp. 30, 81; Exhibit 7). On December 17, 1993, the contractor’s license board issued a report indicating that it would take $11,000 worth of labor and material to finally complete Brown’s remodel. While Brown claims the board sent a copy of the report to Simonis, Simonis does not admit this. (Tr. pp. 31, 82). Simonis did, however, offer an explanation of a sort concerning the report, saying “that’s how much it cost to finish the job, but that wasn’t what I had to finish.” (Tr. p. 80). This statement implies that Simonis thought he had finished the part of the construction he bore responsibility for under the May and October agreements.

On February 17, 1994, despite his awareness of Brown’s claim that he had been over[942]*942paid on the contract, Simonis filed a mechanic’s lien (referred to hereinafter as “the first hen”) for $12,560.00 against Brown’s home. (Exhibit 12). Simonis filed this hen without adequately documenting the figure Simonis claimed Brown still owed. (Tr. p. 85). Then on March 28, 1994, Simonis sent a letter to counsel for Brown offering to withdraw the hen on Brown’s home in exchange for Brown’s withdrawing a complaint to the contractors hcense board. (Tr. p. 98; Exhibit 14). The offer of settlement contains no indication whatsoever that Brown owed Si-monis money.

Nevertheless, Simonis did bring to Brown’s attention Simonis’ contention that Brown still owed monies for work Simonis had done. On October 21, 1993, Simonis prepared a document totaling these numbers. (Exhibit D). The figures in Exhibit D, added to those of Exhibit 4, equal $11,591.64 in specific extras, ah of which Simonis conferred with Brown about on or before October 21, 1993. (Tr. pp. 113-115).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grogan v. Garner
498 U.S. 279 (Supreme Court, 1991)
Miller Brewing Company v. Jos. Schlitz Brewing Co.
605 F.2d 990 (Seventh Circuit, 1979)
Clark v. Lesher
299 P.2d 865 (California Supreme Court, 1956)
Borg-Warner Corp. v. Avco Corp.
850 P.2d 628 (Alaska Supreme Court, 1993)
People v. Sims
651 P.2d 321 (California Supreme Court, 1982)
Gudger v. Manton
134 P.2d 217 (California Supreme Court, 1943)
Henn v. Henn
605 P.2d 10 (California Supreme Court, 1980)
Bernhard v. Bank of America National Trust & Saving Association
122 P.2d 892 (California Supreme Court, 1942)
McCrary v. Barrack (In Re Barrack)
201 B.R. 985 (S.D. California, 1996)
Saylor v. Saylor (In Re Saylor)
178 B.R. 209 (Ninth Circuit, 1995)
Raymond v. Pickering (In Re Pickering)
182 B.R. 268 (D. Montana, 1995)
Mueller v. J. C. Penney Co.
173 Cal. App. 3d 713 (California Court of Appeal, 1985)
Jackson v. City of Sacramento
117 Cal. App. 3d 596 (California Court of Appeal, 1981)
Garcia v. Borelli
129 Cal. App. 3d 24 (California Court of Appeal, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
205 B.R. 939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-simonis-in-re-simonis-casb-1997.