Brown v. Rasin Monumental Co.

55 A. 391, 98 Md. 1
CourtCourt of Appeals of Maryland
DecidedJuly 5, 1903
StatusPublished
Cited by6 cases

This text of 55 A. 391 (Brown v. Rasin Monumental Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Rasin Monumental Co., 55 A. 391, 98 Md. 1 (Md. 1903).

Opinion

Boyd, J.,

delivered the opinion of the Court.

This is an appeal from a decree dissolving an injunction issued at the instance of the appellants against the appellee, and dismissing the bill. The appellee entered into an agreement with Messrs. Brown and Butcher, by which it authorized them to remove and sell the tar in a pond on its premises in Anne Arundel County. Messrs. Brown and Butcher subsequently assigned their interest in the agreement to the Impervious Product Company of West Virginia, with the consent of the appellee. The injunction restrained the appellee from interfering with the appellants entering on the premises of the appellee and removing therefrom the tar from the pond and *3 from hindering them in any way from exercising their rights under the contract.

The appellee answered alleging that the appellants had failed to perform their part of the contract and admitting they had notified them not to remove any of the tar and that it proposed to assert its rights under the contract. In order that the points in controversy may be better understood, we will quote in full the second and seventh paragraphs of the agreement, as they are particularly involved. They are: “Second. The parties of the second part (Brown and Butcher) shall without delay erect and within forty days complete a plant to work up the said tar, and as soon as said plant is completed, begin and thereafter diligently and continuously remove the tar from said pond. ******** Seventh. In case the parties of the second part shall fail to complete said plant within forty days, as above provided, or shall at any time suspend, for ten days the work of removing said tar from pond or shall fail to make payment in full of any accounts when due, as above provided, or to observe or perform any other condition, or undertaking on their part herein, then the party of the first part shall have the right, without further notice, to terminate this agreement and to re-enter upon said premises and hold the same together with any buildings or improvements made or placed there by parties of the second part, as if this agreement had not been made.”

It is admitted that no tar was actually removed from the pond after December 12th, 1902, before this injunction was issued (January 5th, 1903), but the appellants contend that they were ready to remove some on December 24th, but were prevented by the appellee’s failure to have some one weigh it, and it is admitted that they attempted to do so on December 26th, but were prevented by the appellee. The default on the part of the appellants relied on by the appellee is their alleged suspension for ten days of the work of removing tar from the pond.

1. As there were two Sundays between December 12th and 24th it will be well to determine at once whether they are to *4 be included in the ten days, for if they are it will be useless to examine the evidence to ascertain what was done on the 24th of that month. In American Tobacco Company v. Strick ling, 88 Md. 500, we held that when a statute provides that an act shall be done within a certain number of days exceeding seven, the general rule is that Sundays will be included in computing the time, but after quoting from the Encyclopedia of Law to that effect, we said, “Of course that rule will not apply when Sundays are expressly excluded by the statute, or the intention of the Legislature to exclude them is manifest.” In construing written contracts it is proper to look at the whole instrument to ascertain the sense in which words or expressions are used, and if we there find the intention of the parties to give a particular meaning to them that should as far as possible be adopted. Sunday is “a day” and therefore may be one of “ten days,” but the question is whether the “ten days” mentioned in this agreement include the kind of a day Sunday is, and in order to do that we must bear in mind the connection in which that term is used. When the plant ■ was completed, the appellants were at once to “begin and thereafter diligently and continuously remove the tar from said pond.” It cannot be contended that it was contemplated by the parties, in the use of those terms, that the appellants should work on Sundays. To do so unnecessarily would be a violation of the statute law of the State, and hence it cannot be presumed that the parties so intended. When then a forfeiture of their property was authorized if the appellants “shall at any time suspend for ten days the work of removing said tar from pond,” the parties manifestly referred to the kind of days when the appellants ought to be engaged in removing tar— that is to say, working days. They could not have meant that the appellants would be liable to the forfeiture if they suspended work on the days it was known, and must be presumed to have been understood, that it was to be suspended. The suspension prohibited was on the days they were under obligation to work, and not on those on which no work was contemplated. There is no provision in the agreement that indi *5 cates that the parties had any other intention in the use of this term. In the sixth paragraph they provided for payment “on or before the tenth day of each and every month,” but there is only one “tenth day” of each month, and there could be no question about what they there meant. If there be any doubt about the meaning of the expression under consideration and to suspend ten days must result in forfeiture, which is never favored in equity, it would be proper to resolve the doubt against the party seeking to enforce it, as far as the language of the parties and the principles of the law permit. As there were two Sundays between the 12th and the 24th of December, we are of the opinion that the appellants could have avoided the forfeiture by removing tar from the pond on the 24th—it being conceded that they did work on the 12th.

2. The next inquiry is, did they save a forfeiture by what they did, or were ready to do, on that day? It must be admitted that the appellants had not, up to this time, done very much in the way of removing the tar, as they had only taken out three hundred and ninety-seven tons from the time they started on September 3rd, 1901, to December 24th, 1902, but it is evident that both parties regarded the enterprise as somewhat of an experiment. Mr. Doggett, the general manager of the Impervious Product Company, testified that it was a new thing, that there was no demand for this particular product and their competitors “tried to decry the character and quality of it and interfered with us in making a market for it.” The tar had been on the property of the Rasin Company for eighteen or twenty years without profit or use to it during that time, and the conditions inserted in the agreement, together with the parol testimony, show that the representative of that company was doubtful about the success of the enterprise. The appellants agreed to pay the Rasin Company three dollars per ton for the tar taken out, and two hundred and fifty dollars per annum for the use of its property. They paid it “for tar, rental, and for the use of their cars and other articles, somewhere in the neighborhood of $2,700.” The appellants had expended about $25,000 in their plant, and in *6 carrying on and developing the business.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaboard Mut. Casualty Co. v. Profit
108 F.2d 597 (Fourth Circuit, 1940)
Profit v. Seaboard Mut. Casualty Co.
28 F. Supp. 202 (D. Maryland, 1939)
Cover v. Taliaferro
122 A. 2 (Court of Appeals of Maryland, 1923)
Osage Oil & Gas Co. v. Caulk
243 S.W. 551 (Court of Appeals of Texas, 1922)
Ballis v. Northern Brewery Co.
139 P. 326 (Oregon Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
55 A. 391, 98 Md. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-rasin-monumental-co-md-1903.