Brown v. Langner

58 N.E. 743, 25 Ind. App. 538, 1900 Ind. App. LEXIS 130
CourtIndiana Court of Appeals
DecidedNovember 27, 1900
DocketNo. 3,091
StatusPublished
Cited by4 cases

This text of 58 N.E. 743 (Brown v. Langner) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Langner, 58 N.E. 743, 25 Ind. App. 538, 1900 Ind. App. LEXIS 130 (Ind. Ct. App. 1900).

Opinion

Wilby, C. J.

—Appellants Morse and Morse were partners and building contractors. Appellants Brown and Brown were partners and also building contractors. As such, they entered into a contract with the board of school trustees of the city of Washington, in Daviess county, Indiana, for the erection of a public school building. Appellee and one Thankmar Langner were plastering contractors, under the firm name of Carl Langner & Co., and as such, contracted with appellants to plaster said school building for an agreed sum. The amount fixed by the contract was paid them. Before the beginning of this action, Thankmar Langner assigned all of his interest in the contract to appellee, and the latter bróught this action to recover for extra work and certain expenses incurred in carrying out his contract. The amended complaint is in a single paragraph, to which a demurrer for want of facts was overruled. The issues were joined by an answer and reply; trial by jury; verdict and judgment for appellee.

The errors assigned are that the court erred in overruling the demurrer to the complaint; that the court erred in overruling the motion to strike out parts of the complaint; that the court erred in overruling the motion for a new trial, and in permitting appellee to file a remittitur. These several questions will be disposed of in their order.

The complaint and the exhibits thereto are of great length and we will notice the averments of the former only in so far as may be necessary to determine its sufficiency. It is averred that the contract between appellants and the school board was executed by appellants Morse and Morse, for and on behalf of all the appellants; that the contract between appellants and appellee and his partner was signed by Morse and Morse only, for and on behalf of appellants; [540]*540that appellee and his partner did not sign such contract, but that they accepted the same and did the work thereunder. The several items for which a recovery is asked are: (1) Certain expenses incurred in going from Evansville to Washington with employes, to begin the work, upon notice from appellants that the building was ready for plastering, when such building was not in fact ready, and appellee had to return with his men; (2) for doing extra work and furnishing extra material not embraced in the contract; (3) for extra work in plastering blackboards; (4) for extra work and materials in plastering vestibule arches; (5) for extra work and materials required to be done and furnished by appellee in plastering and straightening crooked walls; (6) for extra work required of appellee by reason of the fact that appellants failed properly to protect said building from cold, whereby certain of the plastering froze, and appellee was required to take it off and replace it with new plaster; (7) for extra work in taking off and replacing a large quantity of inferior laths furnished by appellants, they being required to furnish good laths under their contract; (8) for extra work in tinting divers ceilings, which was not required by the contract. The contracts between appellants and the school board, and appellants and appellee are in writing and are made exhibits to the complaint. A copy of the specifications ,for the building is made a part of the contract. It must be conceded that if either of the items above enumerated is a just charge against the appellants, the complaint is good as against a demurrer for want of facts. In view of the averments of the complaint, and the provisions of the contract between appellants and appellee, we are inclined to the view that "at least one of said items is recoverable in this action. The complaint avers that appellee resided in Evansville, Indiana. We judicially know the location of the cities of Evansville and Washington, and know that they are about sixty miles apart. The contract between appellant and appellee provides that when the building became [541]*541ready for plastering, appellants were to notify appellee of that fact in writing, and appellee was required to complete his work in four weeks from the receipt of such notice. The complaint avers that appellants did notify appellee in writing that the building was ready for plastering, and that upon receipt of such notice he immediately went from Evansville to Washington for the purpose of commencing said work, and took with him a large number of men who were in his employment, and was, ready and prepared to commence said work at once; that when he arrived there, he found that said building was not ready for plastering, and he was compelled to return to Evansville with his men, whereby he incurred a large expense, etc. The failure of appellants to have the building ready for plastering after notifying appellee that it was ready, and he incurred expense in attempting to comply with his contract, is such a breach of the contract as will render appellants liable for resulting damages. A party will not be permitted to take advantage of, his own wrong to escape liability for resulting injury. This averment of the complaint shows an actionable breach of the contract, and even if no other breach is properly charged, the complaint would be sufficient as against a demurrer for want of facts. Counsel for appellants indulge in some argument to the effect'that appellants were not required by the terms of their contract to give appellee notice in writing when the building would be ready for plastering. The contract required by its express terms that appellee should complete his work “within four weeks from the time of receiving a written notice from the' parties of the first part [appellants] that said parties and building are ready for said parties of the second part, ready for said plastering work.” The contract further provided that for every day in excess of the four woeks specified in which to complete the work, the appellee should forfeit $50 per day. We must construe this contract to mean that when appellants had the building ready for plastering they were [542]*542required, to give appellee written notice thereof, and. it was his duty to complete the work within the time prescribed. He had a right to rely upon the information given him in writing and to proceed at once to the' performance of the duty required of him by the contract.

The next question discussed by counsel is the overruling of the motion to strike out parts of the complaint. This question is not presented by the record for our consideration. The motion and -the ruling thereon are not brought into the record by a proper bill of exceptions. The motion to strike out was filed and overruled January 5, 1899, to which ruling the appellants excepted and were given ten days in .whichAo file their “special bill of exceptions on the ruling of the court on said motion to strike out.” No such bill of exceptions was filed within the time given by the court. Appellants’ motion for a new trial was overruled February 2, 1899, and sixty days time was given in which to prepare and file a bill of exceptions. Within this time, appellants did file their general bill of exceptions. This paper is entitled: “Bill of exceptions and statement of the evidence.” In the general bill of exceptions, appellants have embraced the motion to strike out, but the bill fails to show that the court made any ruling thereon, or that any exceptions were reserved. The rule that when time is given in which to file a bill of exceptions it must be filed within the limit of the time given has so often been decided that it stands unchallenged.

The record does not show that appellants filed a special bill of exceptions embracing the motion to strike out, and the ruling thereon, within ten days given in which to file it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Casualty & Surety Co. v. State
256 N.E.2d 398 (Indiana Court of Appeals, 1970)
Lipnik v. Ehalt
132 N.E. 410 (Indiana Court of Appeals, 1921)
Ochs v. M. J. Carnahan Co.
76 N.E. 788 (Indiana Court of Appeals, 1906)
Midland Railway Co. v. Trissal
65 N.E. 543 (Indiana Court of Appeals, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
58 N.E. 743, 25 Ind. App. 538, 1900 Ind. App. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-langner-indctapp-1900.