Brown v. Kolb

8 Pa. Super. 413, 1898 Pa. Super. LEXIS 70
CourtSuperior Court of Pennsylvania
DecidedOctober 10, 1898
DocketAppeal, No. 104
StatusPublished
Cited by5 cases

This text of 8 Pa. Super. 413 (Brown v. Kolb) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Kolb, 8 Pa. Super. 413, 1898 Pa. Super. LEXIS 70 (Pa. Ct. App. 1898).

Opinion

Opinion by

Rice, P. J.,

The plaintiff averred in his claim, that the work was done, and the materials ivere furnished, “within six months last past, to wit: between the 26th day of October, 1892, and the 28th day of August, 1893,” under a contract between him and Detrich, the general contractor, “ ratified and approved and confirmed by the said Louis J. Kolb, substituted trustee,” —who for present purposes may be treated as the owner — and “ at the instance and request of both of them.” The bill of particulars annexed to and made part of the claim contained a charge of $878 for “painting and glazing said houses according to agreement with said debtors, being commenced October 26, 1892, and finished August 28,1893,” and other charges, aggre[419]*419gating $24.40 for “ extra work as ordered by above named debtors and done upon the said houses and their credit, and finished the 28th day of August, 1893.” Credits were allowed for payments aggregating$220.35, leaving a balance of $182.50.

The plaintiff testified on the trial, that he contracted with Detrich to paint and glaze the six houses according to the specifications for $63.00 each; that Mr. Kolb was present every day and superintended the work from the beginning; that when it was partially completed Detrich gave up the job, and the plaintiff refused to go on without directions from Mr. Kolb; that thereupon the latter sent for him, and, after being informed of the terms of the contract, and of the amount ($127) that Detrich had paid thereon, told the plaintiff to go ahead and finish the work and he would pay the bill when it was done; that in accordance with these directions the plaintiff finished the work; and that after deducting the payments made by Detrich and Kolb from the amount stipulated by the contract, and adding the cost of the extra work, the amount due him was $182.05. This was what he was permitted to recover under the charge of the court. But, in addition to giving proof of the contract to do the work for a stipulated sum, the plaintiff testified from his books of account as to the work and materials actually furnished under the contract. This testimony was objected to upon the ground that it did not correspond with the amended bill of particulars. The overruling of this objection, and the subsequent refusal to strike out the testimony are the subjects of the first and second assignments of error.

It seems, that the book charges testified to, included work and materials furnished, not only to the six houses in question, but also to another house on a different street. According to the plaintiff’s testimony, the apparent variance between the book entries and the amended bill of particulars was due to-the fact that in the latter he had included only the items furnished to the houses in question. These, he alleged, he had-taken off his time reports, which have been since lost. With this explanation, assuming its truth, the jury would have no difficulty, if it had become necessary to do so, in separating from the general account testified to the items furnished to the houses in question. Thus understood, the ease is plainly dis[420]*420tinguishable from Chambers v. Yarnall, 15 Pa. 265. The attempt was, not to apportion the account between the house on Reed street and the block on Scott street, and then to apportion the sum charged to that block between the six houses composing it, but to show — in a roundabout mode it is true— the work and materials actually furnished to the latter block. It was conceded in Chambers v. Yarnall, that “though the entries ” (in the book of account) “do not specify the building, that may be done by parol evidence; and had the entries been accompanied in this instance by an offer of such proof, it would have turned the scale.” So, also, the Supreme Court has held in the last case upon the subject, “ that where there are blocks of buildings so differing in size, style, material, location or time of erection that the materials or labor going into their construction may be readily distinguished and ascertained, the lien claimant may, if he chooses, file a separate claim against each block, apportioned among its own constituent houses, although all the blocks are erected by the same contractor under one contract with the same owner:” Gordon v. Norton, 186 Pa. 168. Moreover, if it was necessary or proper to give evidence of the materials and labor furnished under the contract, as the defendant claims it was, it was a matter of some importance that the jury should have the whole account before them in order that they might understand more clearly the evidence as to the payments. Therefore, we are not prepared to say that error was committed in the admission of the evidence.

Again, it is to be observed, that the plaintiff did not claim, and was not allowed, to recover the amount of his account for the labor and materials, but only the sum stipulated by the contract. In view of the manner in which’the case was submitted to the jury the admission of the evidence was harmless, even if it was erroneous. It is too well settled to require the citation of authority, that a judgment will not be reversed for an error which could have done the appellant no harm. The first and seventh assignments of error are overruled.

The claim, as well as the bill of particulars, states that the work was done and the materials were furnished between October 26, 1892, and August 28, 1893. The extra work was itemized, but the specific date of each item was not given, it being stated that it was finished on August 28, 1893. It is suifi[421]*421ciently clear, however, that these items of work and materials were done and furnished while the work under the contract was progressing, and between the dates above mentioned, and the proofs corresponded with the averments of the claim; the lien was filed within six months from the completion of tho work, under the contract. The plaintiff testified as follows: “ I have not the dates when this extra work was done; it was done in the month of August, 1898. I could tell you by those other dates.” It is argued, that he should not have been permitted to recover for this -extra work, (1) because the precise dates when it was done were not given; (2) because it did not appear that it was done within six months before the date of the filing of the lien.

Precisely the same objections were considered in Rush v. Able, 90 Pa. 153, a case where the claim, so far as it related to extra work and materials, was not more specific as to the dates of the several items than that under consideration. As to the first objection it was said, quoting from Calhoun v. Mahon, 14 Pa. 56, and citing Bayer v. Reeside, 14 Pa. 167, and McClintock v. Rush, 63 Pa. 203, as being to the same effect: “ All that is required is such certainty as will enable those interested to discover during what period materials were delivered or the work done so as to individuate the transaction.” Whether a stricter rule applies in the case of a subcontractor furnishing extra work or materials at the instance of the contractor, and whether that rule applies in the present case are questions which we shall consider hereafter. It will, however, be proper to remark in this immediate connection that the extra work and materials for which the plaintiff claims were ordered by the owner of the buildings and not by the original contractor for its erection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mohnkern v. Pivirotto
20 Pa. D. & C. 218 (Centre County Court of Common Pleas, 1933)
Wadsworth v. Manufacturer's Water Co.
100 A. 577 (Supreme Court of Pennsylvania, 1917)
Klein v. Levenson
50 Pa. Super. 132 (Superior Court of Pennsylvania, 1912)
Mercer Milling & Lumber Co. v. Kreaps
18 Pa. Super. 1 (Superior Court of Pennsylvania, 1901)
Closser v. Township of Washington
11 Pa. Super. 112 (Superior Court of Pennsylvania, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
8 Pa. Super. 413, 1898 Pa. Super. LEXIS 70, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-kolb-pasuperct-1898.