Brown v. 44th Street Development, LLC

48 Misc. 3d 234, 5 N.Y.S.3d 692
CourtNew York Supreme Court
DecidedMarch 19, 2015
StatusPublished
Cited by3 cases

This text of 48 Misc. 3d 234 (Brown v. 44th Street Development, LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. 44th Street Development, LLC, 48 Misc. 3d 234, 5 N.Y.S.3d 692 (N.Y. Super. Ct. 2015).

Opinion

OPINION OF THE COURT

Anil C. Singh, J.

Motion sequence Nos. 001 and 002 are consolidated for disposition.

In motion sequence No. 001, plaintiff Donald Brown moves for summary judgment on the issue of liability under Labor Law §§ 240 (1) and 241 (6) pursuant to CPLR 3212. Defendants oppose the motion.

In motion sequence No. 002, defendants 44th Street Development, LLC, and Gotham Construction Company, LLC move for summary judgment dismissing plaintiffs claims alleging violations of Labor Law §§ 200, 240 (1), and 241 (6). Plaintiff opposes the motion.

While this is clearly not the first case in New York jurisprudence involving rebar, it may be the first case to describe the dimension, form and function of this common building material.

Rebar (short for reinforcing bar), also known as reinforcing steel, is a steel bar or mesh of steel wires used as a tension device in reinforced concrete to strengthen and hold the concrete in tension (see Wikipedia, Rebar, http://en.wikipedia.org/wiki/ Rebar). Concrete is a material that is very strong in compression, but relatively weak in tension (see Wikipedia, Reinforced concrete, http://en.wikipedia.org/wiki/Reinforced_concrete). To compensate for this imbalance in concrete’s behavior, rebar is cast into it to carry the tensile loads (id.).

Walking on rebar elevated above ground level would be like walking on a steel tightrope, for garden-variety rebar is no wider than an aerialist’s tightrope.

The material facts in the instant matter are as follows.

[236]*236Plaintiff Donald Brown is a carpenter who was injured while working on the construction of a building at 550 West 45th Street in Manhattan. Defendant Gotham Construction Company, LLC was the general contractor at the work site.

Construction of the planned 32-story building began in July 2010. A portion of the building was to be a parking garage.

In February or March 2012, the building was either in the final stages of the foundation, or the foundation had just been completed.

To construct the building, rebar was installed on top of plywood forms that were put in place for the pouring of concrete.

When plaintiff arrived at the construction site two weeks before the accident, he was told by his supervisor to work in the basement to close up the walls.

The accident occurred “framing the ramp,” which was for access into the parking garage from street level; the actual parking lot was below grade. A portion of the ramp was open underneath the earth for more parking and a portion was tied into the foundation. In portions that were open underneath the earth, the distance from the ramp to the next level below was more than 10 feet and in some areas was less (but high enough to allow vehicles to pass underneath).

The rebars were in place for the floor concrete pour. The area where the rebars had been put in place was about 15 feet wide by 20 feet long. The rebar was set up in a crisscrossed manner.

On March 2, 2012, plaintiff was carrying lumber to the work area to get ready to cut. He was walking on top of the rebar that had previously been laid down above the plywood forms. He was carrying two pieces of lumber, which were 14 feet long. These were wall studs. He was carrying them on his left shoulder.

Plaintiffs accident occurred when his feet went down through the opening between the rebar. He was walking on top of the rebar because there was nothing else to walk on; there were no planks or anything else laid down to walk on. The only way to get from where he was doing the cutting and other work was to cross over the area with the rebar. As he was walking, his foot slipped down through the rebar down in the hole. The deck was about 12 to 18 inches deep. His left foot slipped off first, and then his right foot slipped. He went down to the bottom about a foot deep. His body twisted, and he went down backwards.

[237]*237The rebars that he was walking on were approximately 12 inches apart. Each piece of rebar was five-eighths to three-fourths of an inch. They crisscross each other when they are in place. The space that his left foot fell through was about a foot or more wide in all directions.

The supplemental bill of particulars alleges violations of the following statutes, law and rules: Labor Law §§ 240 (1), 241 (6) and 200; part 23 of the Industrial Code (12 NYCRR), including 12 NYCRR 23-1.7, 23-1.8, 23-1.11, 23-1.15, 23-1.16, 23-1.17, 23-1.19, 23-1.20, 23-1.21, 23-1.22, 23-1.23, 23-1.30, 23-1.31, 23-1.32, 23-1.33, 23-2.1, 23-2.2, 23-2.3, 23-2.4, 23-2.6, 23-4.1, 23-4.2, 23-4.4, 23-5.1, and 23-6.1. The supplemental bill of particulars also alleges violations of Occupational Health and Safety Administration (OSHA) regulations 29 CFR 1926.501 (b) (4) (ii) and 1926.451 (b) (2), and American National Standards Institute (ANSI) regulation section 3.1.3.

I. Discussion

The standards for summary judgment are well settled. “The proponent of a summary judgment motion must make a prima facie showing of entitlement to judgment as a matter of law, tendering sufficient evidence to eliminate any material issues of fact from the case” (Winegrad v New York Univ. Med. Ctr., 64 NY2d 851, 853 [1985]). Despite the sufficiency of the opposing papers, the failure to make such a showing requires denial of the motion (id.).

Summary judgment is a drastic remedy and should only be granted if the moving party has sufficiently established that it is warranted as a matter of law (Alvarez v Prospect Hosp., 68 NY2d 320, 324 [1986]).

A summary judgment motion should be denied if the opposing party presents admissible evidence establishing that there is a genuine issue of fact remaining (Zuckerman v City of New York, 49 NY2d 557, 560 [1980]). “In determining whether summary judgment is appropriate, the motion court should draw all reasonable inferences in favor of the nonmoving party and should not pass on issues of credibility” (Garcia v J.C. Duggan, Inc., 180 AD2d 579, 580 [1st Dept 1992], citing Assaf v Ropog Cab Corp., 153 AD2d 520, 521 [1st Dept 1989]). The court’s role is issue-finding, rather than issue-determination (Sillman v Twentieth Century-Fox Film Corp., 3 NY2d 395, 404 [1957]).

II. Liability under the Labor Law § 240 (1) Cause of Action

Labor Law § 240 (1), commonly referred to as the “scaffold law,” provides, in relevant part:

[238]*238“All contractors and owners and their agents, except owners of one and two-family dwellings who contract for but do not direct or control the work, in the erection, demolition, repairing, altering, painting, cleaning or pointing of a building or structure shall furnish or erect, or cause to be furnished or erected for the performance of such labor, scaffolding, hoists, stays, ladders, slings, hangers, blocks, pulleys, braces, irons, ropes, and other devices which shall be so constructed, placed and operated as to give proper protection to a person so employed.”

The First Department summarized the requirements of Labor Law § 240 (1) in Vasquez v Cohen Bros. Realty Corp. (105 AD3d 595 [1st Dept 2013]). The Court wrote:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pizzola v. Tutor Perini Corp.
2025 NY Slip Op 30657(U) (New York Supreme Court, New York County, 2025)
Rodriguez v. VillageFH, LLC
2024 NY Slip Op 31071(U) (New York Supreme Court, New York County, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
48 Misc. 3d 234, 5 N.Y.S.3d 692, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-44th-street-development-llc-nysupct-2015.