Brown & Root, Inc. v. United States

116 F. Supp. 732, 126 Ct. Cl. 684, 1953 U.S. Ct. Cl. LEXIS 127
CourtUnited States Court of Claims
DecidedDecember 1, 1953
DocketNo. 49396
StatusPublished
Cited by2 cases

This text of 116 F. Supp. 732 (Brown & Root, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown & Root, Inc. v. United States, 116 F. Supp. 732, 126 Ct. Cl. 684, 1953 U.S. Ct. Cl. LEXIS 127 (cc 1953).

Opinion

Jones, Chief Judge,

delivered the opinion of the court :

Plaintiff sues to recover $3,000 which the defendant is said to have improperly withheld from the final payment on a contract between the parties for the construction of a 16-mile water pipeline during 1943. This sum was retained by defendant on the ground that it was required to pay the claims of certain owners of property adjacent to the pipeline for injuries caused by plaintiff. The nature of the case requires a rather full statement of the facts.

Plaintiff is a Texas corporation engaged in the business of general construction contracting. By contract dated June 29, 1943, between plaintiff and defendant, the latter acting through the Federal Works Agency, it was agreed that plaintiff would construct a 36-inch cast iron water pipeline from Calallen to Corpus Christie, Texas, a distance of 16 miles. The plaintiff was to furnish all materials and perform the work in accordance with the specifications for the sum of $940,725. It was provided that the Government would furnish a right-of-way 50 feet in width and that any additional right-of-way or easements required should be provided by the contractor. This and other provisions relating to responsibility for damages due to the contractor’s negligence and various specifications here relevant are set out in detail in finding 3 and will be dealt with more specifically in connection with the various claims.

The defendant acquired title to an easement for a 50-foot right-of-way by filing “Declarations of Taking” in condemnation proceedings, but the question of compensation was not settled until after the completion of the contract, when settlement was made for the 50-foot permanent easement, damages to the surface on the 50-foot right-of-way, along with other claims against the Government as well as those against the contractor.

[687]*687Pursuant to its obligation under the contract to furnish engineering-architectural supervision of the construction, defendant employed the firm of Myers and Noyes, architect engineers, who acted in that capacity until completion of the contract. Actual day-to-day control of the work was carried out by plaintiff’s vice president, Mr. J. M. Dellinger.

The work was completed well within the contract time and on November 24, 1943, Myers and Noyes certified to the contracting officer, Federal Works Agency, that “* * * all work has been performed according to contract. We recommend * * * acceptance of the project and payment of the final estimate.” The pipeline was placed in use on December 8, 1943. Shortly thereafter the contracting officer’s assistant regional engineer advised plaintiff that $3,000 would be withheld from the final payment on the contract pending the disposition of the claims of five adjacent landowners for damage done by plaintiff beyond the 50-foot right-of-way. Plaintiff protested this action, contending that the contract had been complied with and any liability which it might have incurred to the landowners was the sole responsibility of plaintiff which defendant had no right to settle. At one point plaintiff offered its bond for $3,000 as assurance that recovery could be had against it for any legitimate claim. The bond was refused and defendant’s agents proceeded to settle various claims for lump-sum payments, irrespective of whether they were asserted against the Government or the contractor. Subsequent to these actual payments the F. W. A. officials in charge estimated the portion of the settlements which they regarded as allocable to plaintiff, and plaintiff was charged accordingly. The total so charged was $2,070, and plaintiff was offered the remaining $930 of the $3,000 withheld. This was refused on the ground that in settling these claims against plaintiff the defendant acted as a volunteer, and plaintiff was entitled to the full $3,000 withheld from the contract price. Pursuant to the dispute clause of the contract,1 the matter was appealed to the Administrator, Federal Works Agency, who made findings of fact and [688]*688affirmed the action taken by the contracting officer.’ Suit in this court was subsequently instituted.

It is unquestioned that plaintiff is entitled to the full contract price unless, as defendant asserts, plaintiff breached the contract and damage to defendant resulted. Defendant contends that it has shown such a breach by plaintiff and that the damages suffered are represented in the amounts which it was obligated to pay the landowners. Having alleged a breach of contract, the burden is on the Government to prove damages, which in this case involves establishing that it was obligated, to pay the amounts expended. Spartan Aircraft Co. v. United States, 120 C. Cls. 327; General Steel Products Corp. v. United States (D. C. N. Y.), 36 F. Supp. 498; see also Anno, 38 A. L. R. 566, 589. It should be noted in passing that while defendant argues that certain portions of this case are exceptions to the general rule of liability in independent contract situations, the plaintiff’s status as an independent contractor is not in dispute.

Inasmuch as the amount deducted from the contract price was expended in five separate settlements, each involving somewhat distinct factual situations, we deem it expedient to deal with each in turn.

I. The Band Morgan Settlement

According to defendant’s evidence, Mr. Morgan owned, or represented owners of, five parcels of land through which the pipeline passed and on which an easement 50 feet wide and 1,191.2 rods in length had been obtained by the Government in the “Declaration of Taking” referred to, supra. Prior to the settlement here in question Mr. Morgan is alleged to have asserted claims to defendant’s investigators totaling $5,984.74, which a summary of the investigators’ records show to have been broken down as follows:2

[689]*689(a) 1,191.2 rods of 50-foot easement_$1,191.20

<b) Crop damage on 50-foot easement, one-half bale per acre at $128.50 per bale_ 1,452.05

(c) Crop damage on additional 30-foot strip used by contractor outside 50-foot right-of-way_ 866.09

(d) Clay on topsoil (over right-of-way)_ 225.40

(e) Cattle killed from eating poisoned cotton_ 500.00

<f) 35 acres of land flooded, crops lost due to interference with drainage- 1,750.00

Total- $5,984.74

It appears that this entire claim was settled by defendant for $4,044.09 and $1,070 of this amount was charged to plaintiff on the theory that plaintiff had (1) violated the contract by using a strip 80 feet in width rather than confining its work to the 50-foot right-of-way; and (2) violated the contract with defendant in that the backfill over the pipeline was left more than 6 inches high, thus causing the flooding of Mr. Morgan’s land. The defendant asks us to hold that it was obligated to pay this $1,070 to Mr. Morgan and that this obligation arose because of a breach of duty by the plaintiff. The evidence before us is insufficient to warrant such a holding.

Assuming, arguendo, that the two items of alleged injury mentioned above resulted from a breach of contract by plaintiff, we have no basis for arriving at a reasonable estimate of what defendant was in fact obligated to pay the landowner in settlement. There is no direct evidence on the extent of the injury actually suffered by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blake Construction Co. v. United States
585 F.2d 998 (Court of Claims, 1978)
United States v. 3.08 Acres of Land
209 F. Supp. 652 (D. Utah, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 732, 126 Ct. Cl. 684, 1953 U.S. Ct. Cl. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-root-inc-v-united-states-cc-1953.