Brower Co. v. Baker & Ford Co.

431 P.2d 595, 71 Wash. 2d 860, 1967 Wash. LEXIS 1030
CourtWashington Supreme Court
DecidedAugust 24, 1967
Docket38428
StatusPublished
Cited by7 cases

This text of 431 P.2d 595 (Brower Co. v. Baker & Ford Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brower Co. v. Baker & Ford Co., 431 P.2d 595, 71 Wash. 2d 860, 1967 Wash. LEXIS 1030 (Wash. 1967).

Opinion

Hamilton, J.

Plaintiffs, as subcontractors, commenced this action against defendant, their prime contractor, to recover the balance allegedly due for work performed in constructing a radar transmitter station for the federal government in Alaska. Judgment was entered in favor of defendant on the basis of evidence indicating an overpayment. Plaintiffs appeal.

*861 The work involved was extensive, urgent, and unique. Plaintiffs’ portion of the project included supplying, fabricating and installing flooring and acoustical tile in the buildings designed to house the radar equipment. Several changes in design and plans were made as the work progressed. When the work was completed, the parties were unable to agree as to the amounts due and owing under the subcontract as modified or altered by the various change orders put into effect during construction. This lawsuit followed. The trial was lengthy, the testimony protracted, and the issues presented were predominantly factual. No useful purpose would be served in extensively detailing the evidence.

Plaintiffs at all times contended that they fully performed under the basic subcontract and are entitled to the fixed sum or sums therein agreed upon, and, further, that as changes developed in the project they submitted estimates of the added costs created by such changes which quotations, when accepted and acted upon by the parties, in turn became fixed sum additions to the basic subcontract.

Defendant, however, contended that plaintiffs did not perform all of the work contemplated by the basic subcontract, and that the parties at the outset agreed that any added costs arising out of probable changes, with one exception, would be determined and adjusted at the conclusion of plaintiffs’ work. In this latter respect, defendant asserts plaintiffs’ estimates submitted prior to commencement of work under the change orders involved were not firm bids but simply preliminary approximations and subject to re-evaluation when the work was completed.

The evidence in support of the respective contentions of the parties was conflicting. The trial court, sitting without a jury, weighed and evaluated the evidence and subscribed to defendant’s theory. Under this theory, the trial court found the overpayment and entered judgment accordingly. On appeal, plaintiffs essentially attack the trial court’s findings of fact with respect to the extent of the flooring work contemplated by the basic subcontract, the extent of plaintiffs’ performance of both the flooring and acoustical work, *862 and the arrangement between the parties as to the pricing of any changes in the course of the work.

The basic subcontract involving the flooring provides, in pertinent part, as follows:

3. That the labor and materials to be furnished, and the work to be performed by the Subcontractor are as follows: Complete installation of floor covering and plywood and tile panels and fasteners in strict compliance with the original contract documents. Freight on panels from Seattle to jobsite by Baker & Ford Co.
(d) The Contractor may, without invalidating this Subcontract, order extra work or make changes by altering, adding to, or deducting from the work; the price herein being adjusted accordingly. All such work shall be executed under the conditions hereof, and of the Main Contract, except that any claim for extension of time caused thereby must be agreed upon at the time of ordering such change.

The acoustical tile work was done under a letter confirming plaintiffs’ bid.

Defendant presented testimony to the effect that it was contemplated under the flooring contract that plaintiffs would furnish 103,000 square feet of flooring, and install 57,000 square feet thereof. Further evidence adduced by defendant indicated that during the course of the work plaintiffs’ installing obligation was reduced to 22,320 square feet, with the remaining footage being installed by another contractor. Thus, defendant asserted, it was entitled to adjust the stated price of the subcontract under paragraph (d) thereof, and the trial court so found.

Plaintiffs contend that the trial court erred in receiving evidence relating to the square footage involved upon the basis that such violates the parol evidence rule. We cannot agree.

None of the contract documents introduced in evidence reveal the amount of footage involved nor the amount to be installed by plaintiffs or any other contractor. For aught that appears in the basic subcontract, plaintiffs were required to install all of the flooring. Admittedly *863 plaintiffs did not do so, for they contended that provisions contained in the pertinent specifications contemplated some installation by others. The extent of plaintiffs’ obligation, as well as that of other contractors, to install flooring was thus rendered unclear and in this respect the pertinent contract documents were ambiguous. The trial court was entitled to receive and consider extrinsic evidence to clarify the ambiguity. Ladum v. Utility Cartage, Inc., 68 Wn.2d 109, 411 P.2d 868 (1966). We find no error in the admission of the challenged evidence.

The remaining contentions of plaintiffs with respect to the deduction claimed by defendant upon the flooring subcontract, and allowed by the trial court, go to the weight, credibility, and evaluation of the testimony of the witnesses. In this respect the trial court accepted defendant’s evidence, which, in turn, amply supports the trial court’s finding. We will not disturb such a finding on appeal. Wells & Wade Hardware, Inc. v. Wenatchee, 64 Wn.2d 103, 390 P.2d 701 (1964).

Plaintiffs next challenge an adjustment in price claimed by defendant and allowed by the trial court with respect to the first change ordered in the course of the flooring work. We are persuaded that the trial court erred with regard to this item.

Briefly, the circumstances are as follows: Early in the work, the government determined that asphalt tile on certain of the floor panels would not be suitable and directed that vinyl tile be applied and that the underside of the panels be sealed. Defendant called for an estimate from plaintiffs as to the probable cost of the change. Plaintiffs submitted a figure in excess of $45,000, which defendant rejected. Thereafter, plaintiffs submitted a revised figure in the neighborhood of $43,000. Again, defendant rejected the estimate, following which plaintiffs and defendant mutually agreed upon the sum of $35,000. Plaintiffs then performed the work. How and upon what basis the $35,000 figure was reached is not spelled out in the evidence, nor does the evidence indicate what items in plaintiffs’ initial cost breakdowns were diminished or deleted in arriving at the *864 agreed price. Now, however, defendant contends that an item of $2,273.42, allocated to labor subsistence and accompanying markups appearing in plaintiffs’ initial cost breakdowns should be deducted because plaintiffs did not in fact furnish such subsistence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dalton v. State
124 P.3d 305 (Court of Appeals of Washington, 2005)
Brust v. McDONALD'S CORPORATION
660 P.2d 320 (Court of Appeals of Washington, 1983)
Green v. Lupo
647 P.2d 51 (Court of Appeals of Washington, 1982)
Lynch v. Higley
510 P.2d 663 (Court of Appeals of Washington, 1973)
Corinthian Corp. v. White & Bollard, Inc.
442 P.2d 950 (Washington Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
431 P.2d 595, 71 Wash. 2d 860, 1967 Wash. LEXIS 1030, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brower-co-v-baker-ford-co-wash-1967.