Brotherhood of Railroad Signalmen of America v. Southern Railway Co.

380 F.2d 59, 65 L.R.R.M. (BNA) 2543, 1967 U.S. App. LEXIS 6575
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 1, 1967
DocketNos. 10799-10802
StatusPublished
Cited by3 cases

This text of 380 F.2d 59 (Brotherhood of Railroad Signalmen of America v. Southern Railway Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brotherhood of Railroad Signalmen of America v. Southern Railway Co., 380 F.2d 59, 65 L.R.R.M. (BNA) 2543, 1967 U.S. App. LEXIS 6575 (4th Cir. 1967).

Opinions

SOBELOFF, Circuit Judge:

The Brotherhood of Railroad Signalmen (hereinafter Brotherhood) appeals from the District Court’s refusal to enforce in full two awards of the National Railroad Adjustment Board based upon alleged breaches by Southern Railway Company of the collective bargaining agreement in force between the parties. The sums directly involved are small, but intriguing and possibly far reaching questions are raised as to the Board’s procedure and the scope of the courts’ reviewing authority.1

Award No. 11733 (appeal No. 10,799) stems from Southern’s unilateral contracting out of work incident to the installation of three replacement poles for an electrical transmission line at High Point, North Carolina. The existing transmission line needed to be raised to permit construction of a new spur track, and this necessitated the installation of taller poles on which to string the line. Southern’s position before the Board was that its supervisor received only three days advance notice of the scheduled commencement of the construction, which would require elevation of the line before that date. It asserted that neither an electrical workers’ line gang nor a signal gang was available — one or the other of which would ordinarily perform the work —and that it therefore arranged for the vendor of the new poles also to supply the necessary men and machinery and to perform the actual installation.2 Southern’s [62]*62argument was that, faced with an emergency, its actions did not constitute a breach of the collective bargaining agreement. Brotherhood, on the other hand, contended that a crew of its members capable of installing the poles was working at Charlotte, North Carolina, only 75 or 80 miles away, and could easily have been transferred to High Point in ample time. It does not appear whether I.B. E.W.-, the electrical workers’ representative, was notified of the pendency of the Board proceeding. The Board sustained Brotherhood’s position and held that its contract had been violated.

Award No. 12300 (appeal No. 10,801) stems from Southern’s assignment of the maintenance of a newly installed electrical “car retarder system” at its Hayne Car Shop Yard near Spartanburg, South Carolina, to employees represented by a union other than Brotherhood. The purpose of the retarder system is to hold cars in place on the tracks outside the repair shop after their emergence from the paint shop, until the repairmen are ready to work on them. The system was installed by an outside contractor, and while Brotherhood initially complained that its members were entitled to both the installation and maintenance work, it limited its formal claim to the latter, conceding that with respect to the installation it was barred by its failure to assert the claim within the 60-day contractual limitations period.

Brotherhood relied on the language of the “Scope Rule” in its contract to the effect that “[s]ignal work shall include * * * generally recognized work on * * * car retarder systems * * Southern’s view was that maintenance of the retarders was not “generally recognized signal work” because that phrase historically refers to the more elaborate mechanisms used in large railroad yards to classify cars, and not to the equipment here involved, which it asserted was physically located entirely within the “[repair] shop limits and fall[s] within the Scope Rule of the Shop Crafts Agreement.” Rejecting this argument, the Board stated that “the Rule [scope rule in Brotherhood contract] contains no language limiting or restricting ‘Car Retarder Systems’ with respect to their size, their location or the purpose for which they must or may be used.” The Board also held that the union to which the Shop Craft employees belong, which had been notified of the pendency of the Board [63]*63proceedings but chose not to appear, was not a necessary party to the dispute.3

By the terms of both awards (Nos. 11733 and 12300, our appeals 10,799 and 10,801), Southern was ordered to compensate certain members of the complaining Brotherhood in the amount that would have been earned had the members been permitted to install the transmission line poles and maintain the retarders from the date of installation. The railroad was further ordered to restore to signalmen the maintenance work incident to operation of the retarders. Upon Southern’s refusal to comply with the awards, the Brotherhood instituted enforcement proceedings in the District Court under section 3, First (p) of the Railway Labor Act, 45 U.S.C.A. § 153, First (p) (1954).

The District Court agreed that the railroad violated the contract in both instances, but declined to enforce the awards of damages as determined by the Board, and limited the allowance to nominal damages of $1.00 in each case. The court reasoned that since the employees designated by Brotherhood to receive the monetary awards had been fully employed at all relevant times, they were not entitled to any remuneration for lost work. In the exercise of its authority under section 3, First (p) of the Act, the court awarded Brotherhood legal fees of $25.00 in each case.4 On appeal to this court, Brotherhood contends that the monetary awards should have been enforced in full and that the allowance of only $25.00 counsel fees in each ease was inadequate and unreasonable.5

On June 20,1966, twelve days after the District Court entered judgments in these cases, there became effective certain amendments to the Railway Labor Act restating and further restricting the scope of judicial review of Board awards.6 Brotherhood urges the applicability of these amendments to pending appeals, but the view we take of the cases makes it unnecessary to resolve this question.7

[64]*64I.

On their face, the present appeals raise solely a legal question as to the scope of judicial review of Board awards. However, we must first consider the possible effect of the Supreme Court’s recent decision in Transportation-Communication Employees Union v. Union Pacific R. R., 385 U.S. 157, 87 S.Ct. 369, 17 L.Ed.2d 264 (1966), which imposes on the Board the obligation fully to settle jurisdictional disputes in a single proceeding.8

In Transportation-Communication, the railroad installed IBM machines to perform dual functions previously assigned separately to clerks and to telegraphers. Operation of the machines was assigned to the clerks, and the telegraphers’ union protested, claiming the jobs for its members. The dispute eventually reached the Board. Although the clerks’ union was notified of the pendency of the case, it declined to participate, indicating an intention to institute separate proceedings if the jobs of any of its members should be threatened.9 The Board determined that the telegraphers were entitled to operate the machines under their contract and awarded compensation to telegraphers idled by assignment of the jobs to clerks. It did not consider whether a reasonable construction of the railroad’s contract with the clerks’ union would support assignment of the jobs to its members. The District Court denied enforcement of the award on the ground that the clerks’ union was an indispensable party and the Court of Appeals for the Tenth Circuit, and in turn the Supreme Court, affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
380 F.2d 59, 65 L.R.R.M. (BNA) 2543, 1967 U.S. App. LEXIS 6575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brotherhood-of-railroad-signalmen-of-america-v-southern-railway-co-ca4-1967.