Brosius Homes Corp. v. Bennett

96 A.2d 612, 202 Md. 433
CourtCourt of Appeals of Maryland
DecidedMay 20, 1953
Docket[No. 152, October Term, 1952.]
StatusPublished
Cited by2 cases

This text of 96 A.2d 612 (Brosius Homes Corp. v. Bennett) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brosius Homes Corp. v. Bennett, 96 A.2d 612, 202 Md. 433 (Md. 1953).

Opinion

Collins, J.,

delivered the opinion of the Court.

This is an appeal from a decree dismissing the bill of complaint of the appellant, Brosius Homes Corporation, hereinafter referred to as Brosius, for the enforcement of a mechanics’ lien.

*435 On February 23, 1951, Brosius and the appellees, R. P. Bennett and Doris E. Bennett, his wife, entered into an agreement by which Brosius, as a builder, agreed to furnish all labor and materials for the construction of a house for the appellees in Frederick County. The Bennetts agreed to pay Brosius therefor the following amounts:

Basic House, Complete, not including lot.... $7,000.00

Oil tank........................ 50.00

Septic tank and field ............ 345.00

Allowance for well, pump and pit.. 360.00

$7,755.00

Less hot water heater by owner 85.00

$7,670.00

This amount of $7,670.00 was to be paid as follows:

$1,000.00 — cash, day construction begins.

3.500.00— on or before the day the house arrives from the manufacturer.

2,000.00 — when the foundation for said house is completed.

1.170.00— balance on completion date.

The costs of all additions were to be added to the total amount due.

On November 29, 1951, Brosius filed a bill of complaint alleging the execution of the aforementioned contract; that certain extras in addition to the contract were mutually agreed upon by the parties; that extra labor and materials were provided by the appellant in the amount of $1,742.21. It also alleged that it had fulfilled its part of the agreement and that said dwelling was fully completed on or about September 27, 1951. That its “claim for work done and materials furnished as aforesaid is overdue and although request has been made on the defendants for payment, they have failed to pay the same.” There was a further allegation that Brosius had filed in the office of the Clerk of the Circuit Court for Frederick County on October 24, 1951, its claim as *436 a lien against the dwelling house and parcel of ground upon which the house was erected. This claim contains a description of the kind and amount of materials furnished and work done by appellant on the erection and construction of the dwelling and the price agreed upon. The amount claimed to be due on account of said dwelling was the final payment of $1,170.00 and the extras in the amount of $1,742.21, the total due being $2,912.21. Appellant asked that a decree be passed for the sale of the property or so much thereof as may be necessary for the purpose of collecting its claim with interest. Filed with the bill of complaint was the mechanics’ lien aforesaid.

An answer and cross bill of complaint was filed by the Bennetts in which they admitted the execution of the aforementioned contract. They admitted that certain extras were agreed upon, but denied that these extras were in the amount claimed by the appellant. They denied that the appellant had fulfilled its part of the contract. They further denied that the appellant had perfected the mechanics’ lien as alleged, due to its failure to substantially comply with the requirements of the law pertaining to such liens: They also alleged that, due to the aid and technical assistance rendered by Robert Bennett to the appellant, he was entitled to recoup. The appellees further alleged that due to the neglect and omissions of the appellant they had been put to additional expense in renting and maintaining another home. They prayed that the appellant be required to pay to the appellees the sum of $5,000.00 for damages. An answer was filed by the appellant to the cross bill denying the material allegations thereof. After taking of extensive testimony the chancellor filed a decree on November 28, 1952, dismissing appellant’s bill of complaint, without prejudice, solely on the ground that the mechanics’ lien and the bill of complaint to enforce that lien had been filed before the approval of the work by the Federal Housing Administration (the FHA) and that therefore the mechanics’ lien was defective and *437 could not be enforced by such a bill. From that decree the appellant appeals. From the record before us no action was taken on the cross bill.

The primary question before us in this case is whether the final payment was conditioned upon formal approval by the FHA. The only reference in the contract to any such approval is the following clause: “The owner agrees not to move any household goods or other material into the house until it has been completed and final approval has been received from Federal Housing Administration and/or Veterans Administration, and until the house has been accepted by the Owner and the total purchase price has been paid in full.” There is no mention in the contract about the well or of the amount of water to be furnished other than as aforesaid: “Allowance for well, pump, and pit — $360.00.”

It developed in the testimony before the chancellor that during the course of construction the FHA made five inspection reports. Apparently, the first three reports were satisfactory because the appellees paid the first three installments under the contract. The fourth report on September 17, 1951, was as follows: “Well not satisfactory to FHA. Flow as stated on form 2217 is only Y2 gallon per minute. FHA minimum flow for wells is 5 gallons per minute.”

Testimony was taken in this case on two occasions. During the taking of the testimony at the second hearing a letter, the fifth report, dated June 30, 1952, from the director of the FHA to the Farmers and Mechanics National Bank of Frederick was offered in evidence in which the FHA notified the bank that it was willing to withdraw its former report, relative to well capacity, and that it would insure the loan. At that second hearing, Mr. J. Hamilton Walker, Chief Construction Examiner and Chief of Architectural Section, FHA, testified that on the basis of tests made and submitted by Mr. J. William Brosius, the president of appellant corporation, since the pump installation, his agency was then willing to insure the loan. There was considerable testimony *438 that prior to the date of the filing of the mechanics’ lien there was sufficient water provided for ordinary household needs. Although in one part of the testimony, Mr. William Brosius testified on cross examination in answer to a question, that he understood approval by the FHA was necessary before final payment, he later corrected this by saying: “Previously when Mr. Nikirk asked me the question — just read it out to me — I didn’t have a chance to think it over or read it — but the contract specifically says that the owner shall not move these things until the house has been completed and final approval has been received from VA or FHA. However, the final approval by VA or FHA refers back to the owner moving in and paying the price in full and does not refer to payment on approval of FHA or VA, doesn’t preclude paying the balance of the contract due on the completion date. The contract calls for $1170 balance on completion date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G. Edgar Harr Sons v. Newton
155 A.2d 480 (Court of Appeals of Maryland, 1959)
Gummed Tapes (PTY) Ltd. v. Miller
155 F. Supp. 267 (E.D. Pennsylvania, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
96 A.2d 612, 202 Md. 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brosius-homes-corp-v-bennett-md-1953.