Brooks v. United States

194 F.2d 185, 1952 U.S. App. LEXIS 2747
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 2, 1952
Docket6357_1
StatusPublished
Cited by2 cases

This text of 194 F.2d 185 (Brooks v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks v. United States, 194 F.2d 185, 1952 U.S. App. LEXIS 2747 (4th Cir. 1952).

Opinion

SOPER, Circuit Judge.

This suit, under the Federal Tort Claims Act, 28 U.S.C.A. § 921 et seq., 1 was brought by Alphine B. Brooks, Administratrix of Birvin Brooks, to recover damages for the death of Birvin Brooks which occurred on July 27, 1945 as the result of an explosion in a fire pump house located on government property, while employed by the R. S. Jordan Company, a plumbing contractor doing work for the United States. The Jordan Company’s insurance carrier paid Brooks’ dependents $6,000 under the North Carolina Workmen’s Compensation Act, and joined in the suit as a co-plaintiff, demanding that any damages recovered be first applied to reimburse it for the monies it had paid out. 2

On and after November 14, 1942 the United States owned a Naval Air Base near Elizabeth City, North Carolina, on which were located several buildings and installations, including a fire pump house which furnished the extra water supply needed to protect the Base against fire. On November 14, 1942 the United States entered into a contract with the Consolidated Vultee Aircraft Corporation (Convair) under which the Navy turned over the Base and its facilities to Convair for use by Convair in servicing and modifying military aircraft. Under the contract Convair had full possession and control of all the facilities at the Air Base, except space for Navy personnel stationed at the Base for inspections of operations and installations to see that the contract was properly performed; and Convair *187 was in charge of the entire operation at the Base, employed the personnel and carried out the business of protecting the property from fire.

The pump house was a part of the facilities provided for protection of the Base against fire. It was situated on the Pasquotank River, a short distance from the shore, and was constructed entirely of concrete and steel and contained three rooms or compartments — one on the ground level covering the entire floor space, and two below, in a subterranean ■chamber below the water level, separated from each other by a reinforced concrete partition. One of the lower compartments was known as a wet well and the other, a dry well. Entrance to the dry well, with which we are concerned, was allowed by a three foot square opening through the concrete floor of the upper room. A stationary steel ladder led down to the concrete floor below. The upper compartment contained two gasoline engines, two electrically driven pumps, numerous switches, and some of the pumping equipment. Part of the pumping equipment was located in the dry well below as was a sump pump which had been installed to pump out water that might leak into and accumulate on the floor of the dry well. The sump pump was driven by an electric motor which was put into action when a float installed near the floor was raised sufficiently by the rise of the water to operate an electric switch; and when the float would drop to a predetermined point as a result of the fall of the water level, the electric motor would cease operating. When in proper working order, the entire operation of the sump pump and electric motor was automatic.

The dry well was IS feet square and 18 feet deep. It was entirely enclosed in concrete except for the opening from the main floor above. It was lighted by an electrically operated bulb in the ceiling of the dry well which was protected by a guard. •

Two one-half inch galvanized iron pipes ran along the ceiling of the dry well and were connected at one end through the concrete wall to a gasoline storage tank situated on the outside of the building, and at the other end, up through the concrete floor to the gasoline engines in the upper compartment. One pipe supplied gasoline to the engines and the other served as a return pipe to carry the overflow of gasoline in the carburetors back to the storage tank outside of the building. This latter pipe was equipped with a gate valve in the dry well chamber, which when opened would cause any gasoline in the return pipe to drain out into the dry well itself. At the time of the explosion this gate valve was closed; but on one occasion prior to the explosion it was found to be in a leaky condition and repaired. The main gas line contained threaded and not welded unions, and a seeping leakage was discovered at such a union just after the explosion.

In 1944, while the Base and its facilities were operated and controlled by Convair, the government entered into a contract with Doyle & Russell, general contractors, for the installation of certain additional facilities on the property, including the installation of a third pump in the fire pump house. On September S, 1944 Doyle & Russell entered into a contract with the R. S. Jordan Company for the installation of this third pump. Under the contract, as the District Judge found, both the contractor and the subcontractor were to perform the work according to their own methods, by their own employees, and subject to no control by the government except as to the end result. During the progress of the work a government inspector visited the site of operations from time to time to ascertain whether the work was proceeding in accordance with the plans and specifications.

At the time of the explosion, the R. S. Jordan Company was engaged in certain work preliminary to the placing of the third pump on the upper floor. It was necessary to make certain connections through the ceiling of the dry well and an air drill had been used to cut a hole through the six inch concrete and steel *188 ceiling for this purpose. There is dispute as to how long before the accident this work was done; there is no doubt that employees of the sub-contractor had been engaged immediately before the accident in erecting a wooden staging within the well, close to the ceiling, upon which the workmen might stand in connecting the third pump, and this staging was partially completed at the time of the accident.

On the morning of the' explosion, there was an accumulation of water upon the floor of the dry well, and the motor of the sump pump had not started automatically upon the rise of the water as it was designed to do. The deceased, an unskilled laborer and helper who had been employed by the R. S. Jordan Company about a year and a half, went down into the dry well for the purpose of starting the sump pump motor. He made one or more unsuccessful attempts to start it by “pushing on the switch,” and as “he pushed the switch again” a flash, and an explosion followed by fire occurred, resulting in fatal burns and injuries to the deceased from which he died the next day. One other Jordan Company employee was just starting down the steel ladder into the dry well at the time of the explosion and he was thrown up and out of the well and against some machinery in the upper room.

At the time Brooks entered the dry well, the air therein was highly saturated with explosive vapors caused by gasoline leaking from a union in the gasoline supply pipe running across the ceiling of the well. The District Court found that “The explosion was caused by the ignition of the explosive vapors in the air within the dry well by a spark originating from the electric switch when ‘pushed’ or moved by the deceased in his effort to start the motor and pump, and the explosion was the proximate cause of the fatal injuries to deceased.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hite v. Maritime Overseas Corporation
380 F. Supp. 222 (E.D. Texas, 1974)
Carey v. United States
183 F. Supp. 727 (M.D. North Carolina, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
194 F.2d 185, 1952 U.S. App. LEXIS 2747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-v-united-states-ca4-1952.