Brooks v. Forest Farms, Inc.

357 S.E.2d 604, 182 Ga. App. 901, 1987 Ga. App. LEXIS 1867
CourtCourt of Appeals of Georgia
DecidedMay 20, 1987
Docket73878
StatusPublished
Cited by4 cases

This text of 357 S.E.2d 604 (Brooks v. Forest Farms, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks v. Forest Farms, Inc., 357 S.E.2d 604, 182 Ga. App. 901, 1987 Ga. App. LEXIS 1867 (Ga. Ct. App. 1987).

Opinion

Carley, Judge.

Appellee-defendant Forest Farms, Inc., purchased realty and exe[902]*902cuted a promissory note and deed to secure debt in favor of the several members of the Martin family (the Martins) who were the sellers of the property. Thereafter, appellee sold the property to appellant-plaintiff Brooks, who assumed the indebtedness that appellee owed to the Martins. Subsequent to appellant’s purchase of the property, he entered into a separate agreement with appellee, which agreement contained the following provision: “ASSUMPTION OF LIABILITY, INDEMNITY. [Appellant] assumes all liability for payment of the existing indebtedness (to the Martins or otherwise) on the Property and to idemnify and hold [appellee] harmless from all claims, actions, demands, liabilities and costs asserted against or reasonably incurred by [appellee] as obligor under any such indebtedness accruing from the date hereof [November 27, 1984,] until such time as said indebtedness is paid in full. In consideration of the within indemnity, [appellee] agrees that it will not modify or amend any such indebtedness and shall immediately notify [appellant] of any demand, notice, or claim thereto pertaining.”

After entering into this agreement, appellant failed to make a timely payment on the note that was held by the Martins. On February 8, 1985, appellee received a letter from the Martins, the purpose of which was to accomplish the following: to declare the existence of a default; to accelerate the entire indebtedness; to give notice of the intent to institute foreclosure proceedings; and, to give notice of the enforcement of the provision in the note relative to attorney’s fees if the accelerated indebtedness was not paid within 10 days. Within the 10 days following its receipt of the Martins’ letter, appellee did not undertake either to pay the Martins the accelerated indebtedness or to notify appellant of its receipt of the Martins’ demand and notice. Apparently, it was not until March 4, 1985 that appellee informed appellant of its receipt of the Martins’ letter. After he had finally been informed of the consequences of his default, appellant sought to restrain the Martins’ foreclosure proceedings. When his efforts to restrain the foreclosure proceedings proved unsuccessful, appellant paid the Martins the entire accelerated balance of the indebtedness, including the attorney’s fees to which the Martins were entitled under the note.

Appellant then filed this action against appellee, asserting that appellee had breached the agreement of November 27, 1984 by failing to give appellant immediate notification after its receipt of the Martins’ letter on February 8, 1985. As the result of this alleged breach, appellant sought to recover the attorney fees that he had incurred in his unsuccessful effort to restrain the Martins’ foreclosure proceedings, as well as the attorney fees that he had ultimately paid to the Martins. Appellee answered, denying the material allegations of appellant’s complaint and raising numerous defenses. Thereafter, appel[903]*903lee and appellant filed cross-motions for summary judgment. The trial court conducted a hearing on the motions and entered an order which denied appellant’s motion and granted summary judgment in favor of appellee. Appellant appeals from that order, enumerating as error both the denial of summary judgment in his favor and the grant of appellee’s motion for summary judgment.

1. The first issue for resolution is the construction and interpretation of the November 27, 1985 agreement. “ ‘Where no matter of fact is involved, the construction of a plain and definite contract, if needed, is a matter of law for the court. But a contract is not ambiguous, even where difficult to construe . . . unless and until an application of the pertinent rules of interpretation leaves it uncertain as to which of two or more possible meanings represents the true intention of the parties.’ [Cits.] ‘ “(E)ven ambiguous contracts may be construed by the courts, and a jury question is presented only when the application of the rules of construction fails to resolve the ambiguity.” ’ [Cits.] The construction and interpretation of a contract, being a matter of law for the court, may properly be disposed of by summary judgment. [Cit.]” Stern’s Gallery of Gifts v. Corporate Property Investors, 176 Ga. App. 586, 593-594 (4) (337 SE2d 29) (1985).

Appellee urges that the contractual provision for the giving of notification to appellant is properly construed as creating only a condition precedent to its own right to seek enforcement of the indemnity provision against appellant. Contractual “ [conditions may be precedent or subsequent. A condition precedent must be performed before the contract becomes absolute and obligatory upon the other party.” OCGA § 13-3-4. Thus, appellee asserts that a failure on its part to give timely notification cannot be construed as providing appellant with his own independent claim for breach of contract, but could only result in affording appellant a defense against indemnification.

In determining whether the contractual provision in issue contemplates appellee’s act of notification as only a condition precedent to appellant’s obligation to indemnify, consideration must be given to “the literal definitions of the words, along with their context.” Cowen v. Snellgrove, 169 Ga. App. 271, 274 (3) (312 SE2d 623) (1983). The agreement between the parties in this case “did not provide that [appellee] should be permitted [to seek idemnification from appellant] ‘on condition that,’ or ‘if,’ or ‘provided,’ [appellee had given notification to appellant]; nor are there other words of conditions contained in the agreement necessary to make this a condition precedent. [Cits.]” Self v. Smith, 216 Ga. 151, 153 (1) (115 SE2d 355) (1960). Instead, the provision clearly provides for appellant’s own personal agreement to indemnify appellee, “[i]n consideration of [which] indemnity [agreement by appellant, appellee] agree[d]” that it would neither modify nor amend the indebtedness owed to the Martins and [904]*904that it would also give certain notification to appellant. (Emphasis supplied.) It is clear and unambiguous that appellee’s “agree[ment]” is intended to be the “consideration” that is afforded to appellant for appellant’s return agreement to indemnify appellee. Thus, the language in question is not to be construed as merely a condition precedent to appellant’s liability to appellee on the indemnification agreement. Compare Tuzman v. Leventhal, 174 Ga. App. 297 (329 SE2d 610) (1985). Appellant agreed to an otherwise unconditional indemnification of appellee with regard to the indebtedness and, in return, appellee unconditionally agreed not to modify or amend that indebtedness and also to give certain notification to appellant. “The parties each being free to make such agreement or to refrain from so doing, their mutual promises and covenants afford consideration the one to the other. [Cits.]” Benton v. Roberts, 41 Ga. App. 189, 190 (3a) (152 SE 141) (1929).

Appellee further urges that, if its duty to give notification to appellant is absolute rather than merely conditional, then its absolute duty would not extend to the giving of notification to appellant of the Martins’ letter of February 8, 1985. The agreement provides that appellee “will not modify or amend any . . . indebtedness [secured by the property] and shall immediately notify [appellant] of any demand, notice, or claim

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horwitz v. Weil
569 S.E.2d 515 (Supreme Court of Georgia, 2002)
Graphic Prep, Inc. v. Graphcom, Inc.
426 S.E.2d 183 (Court of Appeals of Georgia, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
357 S.E.2d 604, 182 Ga. App. 901, 1987 Ga. App. LEXIS 1867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-v-forest-farms-inc-gactapp-1987.