Brooks v. BCF Piping, Inc.

426 S.E.2d 282, 109 N.C. App. 26, 1993 N.C. App. LEXIS 187
CourtCourt of Appeals of North Carolina
DecidedFebruary 16, 1993
Docket9110SC1000
StatusPublished
Cited by4 cases

This text of 426 S.E.2d 282 (Brooks v. BCF Piping, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks v. BCF Piping, Inc., 426 S.E.2d 282, 109 N.C. App. 26, 1993 N.C. App. LEXIS 187 (N.C. Ct. App. 1993).

Opinion

*28 JOHNSON, Judge.

In 1989, Stowe-Pharr Mills (hereafter Stowe-Pharr) in McAden-ville, North Carolina, hired BCF Piping, Inc. (hereafter BCF) to perform refurbishing services in one area of its plant. BCF delivered a welding machine to the job site to be used by BCF’s employees. Before the welding machine was delivered to Stowe-Pharr, it was inspected by a BCF employee, Mr. Ellis. Mr. Ellis determined that the welder was properly wired internally and that its grounding circuit was properly wired.

The standard practice between BCF and Stowe-Pharr was for BCF to deliver the welding machine without a male end plug. It was not contested that this is the standard practice throughout the industry because of the various plug configurations.

At the site, the plug was wired to the power cord by Bill Fiddler, an employee of Stowe-Pharr. On Saturday, 27 May 1989, Stowe-Pharr employees used this particular welding machine to work on a project totally unrelated to BCF’s work. A Stowe-Pharr employee was electrocuted when he touched both the welding machine and another piece of grounded equipment.

After an investigation by Safety Compliance officer, Mike Peak, BCF was issued a Citation for a violation of 29 CFR § 1926.21(b)(2) (1992), for failure to instruct each employee in the recognition and avoidance of unsafe conditions, and the regulations applicable to control or eliminate any hazards; a violation of 29 CFR § 1926.351(c)(5) (1992), for failure to ground the frame of an arc welder; and a second violation of 29 CFR § 1926.351(c)(5), for failure to check the grounding circuit of an arc welder, so as to ensure that the circuit between the ground and the grounded power conductor had resistance low enough to permit sufficient current to flow to cause the fuse or circuit breaker to interrupt the circuit.

BCF contested the Citation set forth above and prevailed in a 25 April 1990 hearing before the Administrative Law Judge (hereafter ALJ). The Commissioner petitioned the North Carolina Safety Health and Review Board (hereafter Board). After hearing evidence and hearing the arguments of counsel, the Board concluded that the ALJ’s order dismissing the Citation should be affirmed. Pursuant to North Carolina General Statutes § 95-141 (1985) and North Carolina General Statutes § 150B-43 (1991), the Commissioner sought judicial review before the Superior Court of Wake *29 County. After considering arguments and briefs, Judge Brannon reversed the order of the Board dismissing the Citation; and held that the “three serious violations contained [in the Citation are] affirmed in all respects.” BCF gave timely notice of appeal to this Court.

This case is governed by the North Carolina Administrative Procedure Act, North Carolina General Statutes § 150B-1 (1991) which establishes a uniform system of administrative rule making and adjudicatory procedures for agencies. Accordingly, the applicable scope of judicial review is set forth in North Carolina General Statutes § 150B-51 (1991), which governs the judicial appeal from agency decisions in contested matters:

The Court reviewing a final decision may affirm the decision of the agency or remand the case for further proceedings. It may reverse or modify the agency’s decision if the substantial rights of the petitioner have been prejudiced because the agency’s findings, inferences, conclusions, or decisions are:
(1) In violation of constitutional provisions;
(2) In excess of the statutory authority or jurisdiction of the agency;
(3) Made upon lawful procedure;
(4) Affected by other error of law;
(5) Unsupported by substantial evidence admissible under G.S. 150B-29 (a), 150B-30, or 150B-31 in view of the entire record as submitted; or
(6) Arbitrary or capricious.

’’The proper standard to be applied depends on the issues presented on appeal. The nature of the contended error dictates the applicable scope of review.” Utilities Comm. v. Oil Company, 302 N.C. 14, 21, 273 S.E.2d 232, 236 (1981).

Our courts have held that if it is alleged that an agency’s decision was based on an error of law, then a de novo review is required. Brooks, Comr. of Labor v. Grading Co., 303 N.C. 573, 281 S.E.2d 24 (1981). “When the issue on appeal is whether a state agency erred in interpreting a statutory term, an appellate court may freely substitute its judgment for that of the agency and employ de novo review.” Id. at 580-81, 281 S.E.2d at 29, quoting *30 Savings and Loan League v. Credit Union Comm., 302 N.C. 458, 465, 276 S.E.2d 404, 410 (1981). A review of whether an agency decision is supported by sufficient evidence requires the court to apply the whole record test. Thompson v. Board of Education, 292 N.C. 406, 233 S.E.2d 538 (1977). The whole record test is also applied when the court considers whether an agency decision is arbitrary or capricious. High Rock Lake Assoc. v. Environmental Management Comm., 51 N.C. App. 275, 276 S.E.2d 472 (1981).

The issues before this Court are (1) whether the trial court erred in ruling that BCF’s reliance on the plant’s qualified electrician was insufficient as a matter of law; and (2) whether the trial court committed reversible error in ruling that BCF failed to train its employees to recognize the hazards associated with their working environment.

In recognition of the issues, we will apply a de novo review for the first assignment of error and the “whole record test” for the second assignment of error.

The whole record rule requires the court, in determining the substantiality of evidence supporting the Board’s decision, to take into account whatever in the record fairly detracts from the weight of the Board’s evidence. Under the whole evidence rule, the court may not consider the evidence which in and of itself justifies the Board’s result without taking into accoimt contradictory evidence or evidence from which conflicting inferences could be drawn.

Thompson, 292 N.C. at 410, 233 S.E.2d at 541.

By BCF’s first assignment of error, it contends that the trial court erred in ruling that BCF’s reliance on the plant’s qualified electrician was insufficient as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spaulding v. Honeywell International, Inc.
646 S.E.2d 645 (Court of Appeals of North Carolina, 2007)
Commissioner of Labor v. Weekley Homes, L.P.
609 S.E.2d 407 (Court of Appeals of North Carolina, 2005)
Dawkins Ex Rel. Estate of Dawkins v. United States
226 F. Supp. 2d 750 (M.D. North Carolina, 2002)
Baker v. Ivester
563 S.E.2d 245 (Court of Appeals of North Carolina, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
426 S.E.2d 282, 109 N.C. App. 26, 1993 N.C. App. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-v-bcf-piping-inc-ncctapp-1993.