Brooks Towers Corporation, and Cross-Appellees v. The Hunkin-Conkey Construction Company and Federal Insurance Company, and Cross-Appellants

454 F.2d 1203, 1972 U.S. App. LEXIS 11553
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 1, 1972
Docket71-1094, 71-1095
StatusPublished
Cited by7 cases

This text of 454 F.2d 1203 (Brooks Towers Corporation, and Cross-Appellees v. The Hunkin-Conkey Construction Company and Federal Insurance Company, and Cross-Appellants) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks Towers Corporation, and Cross-Appellees v. The Hunkin-Conkey Construction Company and Federal Insurance Company, and Cross-Appellants, 454 F.2d 1203, 1972 U.S. App. LEXIS 11553 (10th Cir. 1972).

Opinion

BARRETT, Circuit Judge.

This appeal is taken by Brooks Towers Corporation, hereinafter called the Owner, and its co-plaintiffs, Central Bank and Trust Company and the First National Bank of Denver, lending institutions, from the $786,386.24 judgment awarded the Hunkin-Conkey Construction Company and Federal Insurance Company, hereinafter called the Contractor, upon its counterclaim for damages representing the balance due under a contract for the construction of Brooks Towers, a 42-story commercial and apartment building in Denver. The Contractor has filed a cross-appeal.

This diversity suit involved a two-week trial to the Court without jury.

The Contract — Contentions—Court Findings

The original construction contract price was $7,600,000.00. Pertinent provisions, for purposes of this opinion, became operative on June 8, 1966, when work commenced. They are:

“Within fifteen months after acceptance (June 8, 1966) of said notice to proceed
“(a) commercial and office space is to be substantially completed as a shell area and be ready for customization by others in accordance with plans and specifications,
“(b) garage floor areas shall be substantially completed with 20% of said garage area being reserved for Contractor storage and usage,
“(c) approximately 175 apartment suites on a contiguous block of lower floors shall be substantially completed and ready for final decoration by others,
*1205 “Substantial completion of the entire Work shall be accomplished in eighteen (18) months after acceptance of said notice to proceed.”

Substantial completion was defined as meaning “when the Work is ready for occupancy for its intended purposes, except for customization for tenants and ‘punch list’ items to be completed by Contractor.” By its terms, unless relieved by excusable delays, substantial completion should have been accomplished by December 8, 1967. The Contract provided further that:

“If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner, the Architect, or any employee, agent or contractor of either, or by deletions, alterations, or additions ordered in the Work, or by labor disputes, fire, accidents, severe weather conditions, unusual delay in transportation or any other causes beyond the Contractor’s control, then the times herein fixed for the completion of the Work shall be extended for a period equivalent to the time lost by reason of any one of the causes aforesaid. The Contractor shall promptly notify the Owner in writing of the facts relating to any of the above described causes of delay and Contractor’s estimate of the revised dates of completion of the Work.” (Emphasis ours.)

The Owner contends that it is entitled to damages by reason of failure of the Contractor to meet either the partial completion or substantial completion dates in the contract schedule. It contends that the building was not completed until November of 1968. The Owner seeks damages for lost rentals, additional interest payments charged, defective work, temporary housing of tenants and other losses.

The Contractor counterclaimed, alleging that by reason of excusable delays the building was substantially completed on June 1, 1968. The Contractor sought a total judgment of $1,029,947.93.

The trial court found that: (1) the Owner, at pretrial, asserted that the Contractor was required to complete the building in December, 1967, and that it was not completed until November, 1968; (2) the parties agreed upon a procedure with respect to changes in the work (deletions, alterations, or additions) which involved, in each instance, a “Quotation” from the Contractor setting forth the number of additional calendar days to be extended beyond the original Contract period for completion of the work, directed to the Owner’s Architect, who approved extensions of time total-ling 185 calendar days; (3) in addition to the extensions of time approved by the Owner’s Architect, the Contractor was entitled to 30 calendar days by reason of labor disputes and severe weather conditions; and (4) that substantial completion of the work occurred on June 8, 1968, except for noncustomized apartment units on floors 40 and 41 which were not completed until October 11, 1968, but that the Owner did not 'offer evidence of any loss of rental damage thereby. The Court had previously ruled that the Owner was entitled to a set-off of $28,170.00 representing the measure of damages for failure of the Contractor to comply with Bulletin 15 relating to work to be performed on concrete balconies.

Partial and Substantial Completion

The Owner complains that the trial court erred in failing to make any findings relating to “partial completion”, i. e., the occupancy aimed for within the 15 month period. The parties understood that both the “partial” and “substantial” completion schedules were extremely tight and that the construction schedule required clockwork precision in order to accomplish these objectives. These schedules were strictly tied to the original plans and specifications.

Max Ratner, the Owner’s Architect, acknowledged that major changes were made from the original plans and specifications, with particular reference to the third floor and the upper floors. These changes affected both structural and mechanical engineering changes. *1206 Ratner acknowledged that many of the changes affected the sequence of the work, thus creating delays. The Contractor had undertaken a “critical path scheduling” study before submitting its bid on this project. This involves breaking a construction job down into its smallest working components and scheduling the work in proper sequences. The importance of meeting a “critical path schedule” is evident. Chat Paterson, Vice-President of the Owner, testified that the Owner, too, relied upon its own critical path schedule.

There is substantial evidence in this voluminous record that: (a) “partial completion” was accomplished through the 20th floor by December 11, 1967, some three months behind the contract schedule; (b) the major change relating to the third floor had occurred during this time; and (c) the Contractor had requested some 78 days extension of time, relating entirely to changes in the scope of the work which, together with delays during the first 15 months resulting from strikes and weather conditions, are justified in this record.

The trial court properly treated and considered damages only in relation to the “substantial completion” covenants of the Contract. The Court found that substantial completion was not required of the Contractor until July 1, 1968. We hold that this finding is supported by substantial evidence.

Extensions of Time

The overriding dispute in this case involves the extensions of time which the Contractor was entitled to. The trial court found that the Owner’s Architect, Ratner, had approved extensions of 185 days, exclusive of 30 days delay resulting from labor disputes and severe weather conditions — or a total of some 215 days extension.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haberl v. Bigelow
855 P.2d 1368 (Supreme Court of Colorado, 1993)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Moore v. Kuehn
602 S.W.2d 713 (Missouri Court of Appeals, 1980)
William F. Klingensmith, Inc. v. District of Columbia Ex Rel. Reliance Insurance
370 A.2d 1341 (District of Columbia Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
454 F.2d 1203, 1972 U.S. App. LEXIS 11553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-towers-corporation-and-cross-appellees-v-the-hunkin-conkey-ca10-1972.