Brooke Drywall of Columbia, Inc. v. Building Construction Enterprises, Inc.

361 S.W.3d 22
CourtMissouri Court of Appeals
DecidedDecember 20, 2011
DocketWD 73355
StatusPublished
Cited by14 cases

This text of 361 S.W.3d 22 (Brooke Drywall of Columbia, Inc. v. Building Construction Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooke Drywall of Columbia, Inc. v. Building Construction Enterprises, Inc., 361 S.W.3d 22 (Mo. Ct. App. 2011).

Opinion

KAREN KING MITCHELL, Presiding Judge.

This is a surety bond case. The surety guaranteed payments due from the contractor to its subcontractors. Under the agreement between the contractor and one of its subcontractors, attorneys’ fees were due the “prevailing party” in any litigation arising from the agreement. A dispute arose over payments to the subcontractor. After lengthy litigation, the contactor and the surety settled with the subcontractor for the entire principal sum in dispute. The parties then submitted to the court the issues of whether the subcontractor was owed attorneys’ fees and/or interest on the principal sum.

The primary issues here are whether the subcontractor was the “prevailing party,” and, if it was, whether the surety is liable for attorneys’ fees, given that the bond did not specifically mention them. The subcontractor’s entitlement to interest on the principal amount is also at issue. We hold that, given that the parties submitted the interest issue to the court and the subcontractor prevailed, the subcontractor was the prevailing party and was therefore entitled to attorneys’ fees pursuant to its agreement with the contractor. Furthermore, the language of the surety’s bond was broad enough to cover all “payments due” from the contractor to its subcontractors, and therefore the surety was liable for the subcontractor’s attorneys’ fees. The subcontractor’s agreement with the contractor provided that the former was entitled to interest on the principal amount due. Accordingly, we affirm.

Facts and Procedural Background 1

Appellant Building Construction Enterprises, Inc. (“Contractor”) submitted the winning bid for a construction project at the University of Missouri, Rolla, which is now called the Missouri University of Science & Technology (“University”). Contractor and University entered into a contract for the project (“University agreement”).

Contractor obtained a surety bond (“the bond”) for the University construction project from Appellant Hartford Fire Insurance Company (“Surety”). The bond provides as follows:

if [Contractor] shall faithfully perform and fulfill all the covenants, agreements, terms, conditions, requirements or undertakings of [the University agreement] and promptly make payment for materials incorporated, consumed or used in connection with the work set forth in [the University agreement] ... and all insurance premiums, both compensation and all other kinds of insurance, on said work, and for all labor performed on such work, whether by subcontractor or otherwise, at not less than the prevailing hourly rate of wages for work of a similar character (exclusive of maintenance work) in the locality in which the work is performed and not less than the prevailing hourly rate of wages for legal holiday and overtime work, as provided for in [the University *25 agreement] and in any and all duly authorized modifications of [the University agreement] that may be hereafter made, with or without notice to the Surety, then, this obligation shall be void and of no effect, but it is expressly understood that if [Contractor] should make default in or should fail to strictly, faithfully and efficiently do, perform and comply with any or more of the covenants, agreements, terms, conditions, requirements or undertakings, as specified in or by the terms of [the University agreement], then this obligation shall be valid and binding upon [Contractor and Surety] and this bond shall remain in full force and effect; and the same may be sued on at the instance of any material man, laborer, mechanic, subcontractor, individual, or otherwise to whom such payment is due, in the name of the [University], to the use of any such person.

Contractor then entered into a contract (“the subcontract”) with Respondent Brooke Drywall of Columbia, Inc. (“Subcontractor”) for the performance of part of the work for the University construction project. The relevant portions of the subcontract are as follows:

12.1 Final payment, constituting the entire unpaid balance of the Subcontract Sum, shall be made by the Contractor to the Subcontractor when the Subcontractor’s Work is fully performed in accordance with the requirements of the Subcontract Documents, the Architect has issued a certificate for payment covering the Subcontractor’s completed Work and the Contractor has received payment from the [University]. If, for any cause which is not the fault of the Subcontractor, a certificate for payment is not issued or the Contractor does not receive timely payment or does not pay the Subcontractor within three working days after receipt of payment from the Owner, final payment to the Subcontractor shall be made upon demand.
[[Image here]]
15.2 Payments due and unpaid under this Subcontract shall bear interest from the date payment is due at such rate as the parties may agree upon in writing or, in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
[[Image here]]
Article 15.6
In the event the parties hereto elect to engage the services of an attorney with respect to any dispute arising out of, resulting from or in connection with the performance or non-performance of construction relating to the [University] Project, the party prevailing with respect to any such dispute, in addition to all other damages owing to it, shall also be paid by the non-prevailing party all attorney fees, costs and expenses, including those of any consultants or experts, sustained, suffered or incurred in any manner with respect to such dispute.

Due to forces beyond the parties’ control (a worldwide shortage of steel), Subcontractor did not complete its portion of the subcontract on time, nor did Contractor complete the global project on time. University withheld payment from Contractor, and Contractor withheld payment from Subcontractor. In the spring of 2005, Subcontractor made demand for final payment.

Subcontractor sued Contractor and Surety for payment of the principal amount due ($300,000), plus interest and attorneys’ fees. After lengthy litigation, the parties settled for the entire principal amount but reserved the issues of interest and attorneys’ fees for the circuit court to decide. The circuit court found that Contractor and Surety were both liable for *26 interest and attorneys’ fees and entered judgment accordingly. This appeal follows.

Standard of Review

As in any court-tried case, “we will affirm the circuit court’s judgment unless there is no substantial evidence to support it, it misstates or misapplies the law, or it goes against the weight of the evidence.” Howard v. Turnbull, 316 S.W.3d 431, 436 (Mo.App. W.D.2010). As always, “[qjuestions of law such as contract interpretation are reviewed de novo.” Reece & Nichols Realtors v. Zoll, 201 S.W.3d 516, 518 (Mo.App. W.D.2006).

Legal Analysis

I. Whether Subcontractor was entitled to interest on the principal amount

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
361 S.W.3d 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooke-drywall-of-columbia-inc-v-building-construction-enterprises-inc-moctapp-2011.