Brockwell Contract v. Kearny Bd.

20 A.3d 1165, 420 N.J. Super. 273
CourtNew Jersey Superior Court Appellate Division
DecidedJune 20, 2011
DocketA-1806-10T4
StatusPublished
Cited by3 cases

This text of 20 A.3d 1165 (Brockwell Contract v. Kearny Bd.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brockwell Contract v. Kearny Bd., 20 A.3d 1165, 420 N.J. Super. 273 (N.J. Ct. App. 2011).

Opinion

20 A.3d 1165 (2011)
420 N.J. Super. 273

BROCKWELL & CARRINGTON CONTRACTORS, INC., Plaintiff-Respondent,
v.
KEARNY BOARD OF EDUCATION and Hall Construction, Inc., Defendants-Respondents, and
Dobco, Inc., Defendant-Appellant.

No. A-1806-10T4

Superior Court of New Jersey, Appellate Division.

Argued January 24, 2011.
Decided June 20, 2011.

*1166 Charles F. Kenny argued the cause for appellant (Peckar & Abramson, attorneys; Michael E. Smilow, River Edge, on the brief).

Robert T. Lawless, Florham Park, argued the cause for respondent Brockwell & Carrington (Hedinger & Lawless, attorneys; Mr. Lawless, of counsel and on the brief).

Connell Foley, attorneys for respondent Kearny Board of Education (Thomas S. Cosma and Jessica Palmer, Roseland, on the brief).

Lindabury, McCormick, Estabrook & Cooper, attorneys for amicus curiae The Mechanical Contractors Association of New Jersey, Inc. (Edward J. Frisch, of counsel; Mr. Frisch and Bruce P. Ogden, Westfield, on the brief).

Before Judges A.A. RODRÍGUEZ, GRALL and LEWINN.

The opinion of the court was delivered by

A.A. RODRÍGUEZ, P.J.A.D.

In this appeal from a public bidding dispute regarding a school building project, the central issue is the construction and application of N.J.A.C. 17:19-2.13(c). This regulation provides in pertinent part that, "[a] firm shall not be awarded a contract which, when added to the backlog of uncompleted construction work ... would exceed the firm's aggregate rating." The dispute is whether this requirement applies to subcontractors as well as general contractors. We hold that the regulation applies to both subcontractors and contractors pursuant to the Public Schools Contract Law (PSCL), N.J.S.A. 18A:18A-1 to -59, and the Educational Facilities Construction and Financing Act (EFCFA), N.J.S.A. 18A:7G-1 to -48.

The Kearny Board of Education (Board) opened bids for the "Kearny High School — Aircraft Noise Abatement and Renovations Project" (Project) on September 15, 2010. Dobco, Inc. (Dobco) was the lowest bidder, followed by Brockwell & Carrington (B & C). The Board awarded the contract to Dobco. Dobco's bid identified Environmental Climate Control, Inc. (ECC) as the heating, ventilation and air-conditioning (HVAC) subcontractor for the Project. ECC indicated that it would perform its portion of the HVAC work for $7,500,000. In connection with Dobco's bid, ECC submitted a "Notice of Classification" and a "State of New Jersey Form DBC 701 (Form 701)." These forms are required by the Division of Property Management and Construction (DPMC), which classifies contractors by permissible aggregate work volume based upon the given contractor's submissions detailing financial ability. It is undisputed that, at the time the bid was submitted, ECC's aggregate limit was $15,000,000. With Dobco's bid, ECC also submitted a Form 701 indicating that it had a backlog of uncompleted contracts *1167 totaling $3,500,000. Therefore, it could bid on this project as Dobco's subcontractor without exceeding its $15,000,000 aggregate limit.

B & C challenged Dobco's bid, asserting defects in the bid. B & C claimed that the HVAC work was valued at near $9,500,000 and ECC had therefore underbid the project. B & C also claimed that it had received a Form 701 from ECC for an unrelated contract a month earlier in which ECC had disclosed a backlog of uncompleted contracts exceeding $9,000,000. According to B & C, therefore, not only was ECC's Form 701 for the Project likely incorrect, but by bidding $7,250,000 on the Project, ECC had exceeded its aggregate limit.

The Board investigated. Peter Pivko, the architect for the Project, relayed Dobco's explanation that ECC had bid the project at $7,250,000 because Dobco planned on completing a portion of the HVAC work itself. Martin Hestor, the ECC estimator, determined that ECC's backlog of uncompleted contracts was actually $10,125,579 at the time of the bid submission. When this backlog was added to ECC's $7,250,000 bid on the Project, the sum exceeded ECC's aggregate limit.

B & C moved by way of order to show cause to disqualify Dobco's bid. Judge Maurice J. Gallipoli granted the order to show cause. In opposition, Dobco submitted the certification of Kenneth O'Boyle, ECC's president, asserting that:

As of August 31, [2010,] ECC's uncompleted contract work had a dollar value of $10,125,579; $3,231,329.20 of the work is being self-performed, $4,193,983.30 is being subcontracted, and $2,700,267.00 reflects the value of materials being purchased. As of September 30, [2010,] the dollar value of uncompleted work was reduced to $8,227,191.15; $2,603,211.35 of the work is being self-performed, $3,917,452.80 is being subcontracted, and $1,706,527.00 reflects the value of materials being purchased.

On the return date, Dobco and the Board argued that N.J.A.C. 17:19-2.13 and N.J.S.A. 18A:7G-37, generally do not apply to subcontractors; and, that N.J.A.C. 17:19-2.1(a) requires only that a subcontractor possess, rather than comply with a valid classification and rating. Specifically, Dobco argued that although N.J.A.C. 17:19-2.11(b) and -2.1(a) explicitly refer to subcontractors, the only section that requires the backlog calculation, N.J.A.C. 17:19-2.13(c), refers only to a "firm." Given the separate treatment given to subcontractors in other sections, Dobco argued that subcontractors are not included in the broad use of "firm" in N.J.A.C. 17:19-2.13(c).

In a November 29, 2010 written opinion, Judge Gallipoli rejected these arguments. He relied primarily on the EFCFA and our holding in Advance Electric Co. v. Montgomery Township Board of Education, 351 N.J.Super. 160, 175, 797 A.2d 216 (App.Div.2002), where we held that:

the Legislature has determined that the classification of bidders, as accomplished by the Treasurer's regulations, is a reasonable method by which to qualify both bidders and their subcontractors. ...
This conclusion is buttressed by the requirement in [the PSCL,] N.J.S.A. 18A:18A-26[,] that bidders be classified, and that a board of education can only accept bids from those "qualified in accordance with such classification."
[(emphasis added).]

This interpretation supports the broad legislative intent of "insur[ing] that quality work will be provided." Id. at 176, 797 A.2d 216.

Judge Gallipoli found that ECC was a "firm" within the meaning of N.J.A.C. *1168 17:19-2.13(c) and subject to its terms. Thus, the judge decided that ECC was subject to the aggregate rating limit set by N.J.A.C. 17:19-2.13(a). He also determined that the legislative intent articulated in 35 N.J.R. 1701(a) demonstrated that "the 85-percent deduction[1] was not intended to benefit a subcontractor, but a contractor seeking the award of a prime contract." Based on these findings and analysis, the judge concluded that Dobco's bid was materially defective, and denied Dobco the opportunity to cure its bid. The judge ordered the Board to award the contract B & C, the next lowest responsible bidder.

Dobco appealed and sought a temporary stay. We granted this request and expedited the appeal. No. M-2081-10 (App. Div. Dec. 10, 2010).

On appeal, Dobco raises three contentions. First, pursuant to N.J.S.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
20 A.3d 1165, 420 N.J. Super. 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brockwell-contract-v-kearny-bd-njsuperctappdiv-2011.