BRM Construction, Inc. v. Marais Gaylord, L.L.C.

181 P.3d 283, 2007 Colo. App. LEXIS 1209, 2007 WL 1839799
CourtColorado Court of Appeals
DecidedJune 28, 2007
DocketNo. 06CA0559
StatusPublished
Cited by3 cases

This text of 181 P.3d 283 (BRM Construction, Inc. v. Marais Gaylord, L.L.C.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BRM Construction, Inc. v. Marais Gaylord, L.L.C., 181 P.3d 283, 2007 Colo. App. LEXIS 1209, 2007 WL 1839799 (Colo. Ct. App. 2007).

Opinion

Opinion by

Judge J. JONES.

Defendant, Marais Gaylord, LLC (Marais), appeals the district court's order confirming an arbitration award in favor of plaintiff, BRM Construction, Inc. (BRM). We affirm.

I. Background

Marais and BRM entered into a contract pursuant to which BRM agreed to serve as the general contractor for construction of a residential condominium project on land owned by Marais. Toward the end of the project, both parties claimed that the other owed them money under the contract.

On June 8, 2004, BRM filed suit against Marais to foreclose a mechanic's lien on the property and asserting claims for breach of contract and promissory estoppel. Simultaneously, BRM filed an ex parte motion to stay the action pending arbitration of BRM's claim for payment, as required by the contract. The district court granted that motion. Marais filed a motion to vacate the stay, contending that BRM had failed to comply with two conditions precedent to arbitration: specifically, that a claim must first be submitted to the project architect for resolution and also must be submitted within twenty-one days of the occurrence giving rise to the claim. The court issued an order staying the action pending arbitration, effectively denying Marais' motion.

Marais moved for clarification of the court's stay order. The court entered another order stating that submission of the claim to the architect was not a condition precedent to arbitration because the claim arose after the date of final payment set forth in the contract, March 15, 2004.

The case proceeded to arbitration. The arbitrator ordered BRM to submit its claims to the architect, and BRM did so. The architect, however, did not render a decision on BRM's claims. The arbitrator awarded BRM $423,577.68, of which $18,514.17 was to be paid from escrow directly to a subcontractor.

BRM filed an application with the district court to confirm the arbitration award pursuant to § 183-22-222, C.R.S.2006, the successor provision to former § 18-22-2183, Colo. Sess. Laws 1975, ch. 154 at 576, which was in effect when the parties entered into the contract, and therefore applicable to this case. See §§ 13-22-208, 18-22-2830, C.R.S.2006; Colo. Sess. Laws 2004, ch. 3683, § 5 at 1782. Marais opposed the motion and moved to vacate the award, again contending that BRM had failed to comply with conditions precedent to arbitration. Marais argued that such failure constituted grounds to vacate the award under § 18-22-2283, C.R.S.2006, the successor provision to former § 18-22-214, Colo. Sess. Laws 1975, ch. 154 at 576, because the arbitrator had exceeded his powers, see Colo. Sess. Laws 1975, ch. 154, § 18-22-214(1)(a)(III) at 576, and there was no agreement to arbitrate the dispute, see Colo. Sess. Laws 1975, ch. 154, § 18-22-214(1)(a)(V) at 576.

On December 15, 2005, the district court entered an order confirming the arbitration award and entering judgment in BRM's favor on its breach of contract claim. The court dismissed BRM's promissory estoppel claim as moot, and vacated the stay, thus permitting BRM to prosecute its mechanic's lien claim. BRM filed an amended complaint to foreclose its mechanic's lien. The court subsequently entered an order certifying its order confirming the arbitration award as final pursuant to C.R.C.P. 54(b).

Marais timely appeals the district court's order confirming the arbitration award.

II. Discussion

Marais contends that the arbitration award should be vacated because of BRM's alleged failure to comply with conditions precedent to arbitration. We conclude, however, that the issue whether BRM failed to comply with procedural conditions precedent to arbitration was for the arbitrator to decide, and that an arbitrator's resolution of that issue, even [285]*285if erroneous, is not a ground for vacating or refusing to confirm the award.

The General Assembly enacted the Colorado Uniform Arbitration Act in 1975. "The purpose of the Act was to provide a uniform statutory framework for arbitration and to encourage settlement of disputes through the arbitration process." Sopko v. Clear Channel Satellite Servs., Inc., 151. P.3d 663, 666 (Colo.App.2006); accord Lane v. Urgitus, 145 P.8d 672, 678 (Colo.2006).

If a party challenges whether a particular dispute must be arbitrated, the court must resolve one to three questions (depending on the answers to the first two, and assuming that all issues regarding arbitrability, including contract formation, have not been entrusted by the agreement to the arbitrator. See Galbraith v. Clark, 122 P.3d 1061, 1064 (Colo.App.2005)). First, does the agreement contain a valid and binding arbitration clause? Second, if so, who decides whether a particular dispute falls within the seope of the arbitration clause, the court or the arbitrator? Third, if the court is to decide whether a particular dispute falls within the scope of the arbitration clause, does the dispute fall within the scope of the arbitration clause? City & County of Denver v. Dist. Court, 989 P.2d 1858, 1868 (Colo. 1997); see also Eychner v. Van Vleet, 870 P.2d 486, 489 (Colo.App.1993).

The first question entails determining, to the extent such matters are disputed, (1) whether the contract in question contains a provision requiring arbitration of disputes, and (2) whether that clause is valid. Seq, eg., City & County of Denver, supra, 989 P.2d at 1865 (addressing validity of clause giving party's representative power to decide the claim); Lambdin v. Dist. Court, 903 P.2d 1126, 1129-30 (Colo.1995) (holding arbitration agreement that conflicted with Wage Claim Act void); Shotkoski v. Denver Inv. Group Inc., 134 P.3d 518, 515-17 (Colo.App.2006) (addressing whether illegal provision in contract rendered entire contract, and therefore arbitration clause contained therein, unenforceable); R.P.T. of Aspen, Inc. v. Innovative Communications, Inc., 917 P.2d 340, 342-43 (Colo.App.1996) (decision whether contract violated antitrust laws, and was therefore void, was necessary before arbitration award could be confirmed). The court's inquiry as to the validity of the arbitration clause is "limited to specific challenges to 'the agreement to arbitrate," not the broader contract containing the arbitration provision." Ingold v. AIMCO/Bluffs, LLC. Apartments, 159 P.3d 116, 120 (Colo.2007) (quoting in part former § 18-22-204(1)) (emphasis in In-gold). The arbitrator must decide challenges to the enforceability of the contract as a whole. Ingold, supra, 159 P.3d at 120.

The parties here agree that the contract contains a provision requiring arbitration of disputes, and that the provision is valid.

As to the second question-whether the court or the arbitrator decides if a dispute falls within the seope of the arbitration clause-Marais contends, relying on City & County of Denver, supra, that the contract is silent and therefore that the court must decide it. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Colorado, 2026
PFW, Inc. v. Residences at Little Nell Development, LLC
2012 COA 137 (Colorado Court of Appeals, 2012)
Braata, Inc. v. Oneida Cold Storage Co. LLP.
251 P.3d 584 (Colorado Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
181 P.3d 283, 2007 Colo. App. LEXIS 1209, 2007 WL 1839799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brm-construction-inc-v-marais-gaylord-llc-coloctapp-2007.