Bristol & Plainville Tramway Co. v. Eveline

94 A. 290, 89 Conn. 382, 1915 Conn. LEXIS 46
CourtSupreme Court of Connecticut
DecidedJune 10, 1915
StatusPublished
Cited by2 cases

This text of 94 A. 290 (Bristol & Plainville Tramway Co. v. Eveline) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bristol & Plainville Tramway Co. v. Eveline, 94 A. 290, 89 Conn. 382, 1915 Conn. LEXIS 46 (Colo. 1915).

Opinion

Beach, J.

On the face of this appeal-record the nonsuit was justified, because there is no evidence whatever to support the essential allegations of' negligence and of defective workmanship. The underlying question, however, was whether, on the face of the contract, the plaintiff had any cause of action enforceable by a suit on the bond. This question having been determined adversely to the plaintiff was decisive of the merits, and might logically have resulted in a judgment for the defendant in the usual form, instead of a judgment as of nonsuit. But since the nonsuit was based upon the ruling as to the construction of the contract, the correctness of this ruling may be challenged on an appeal from the refusal to set aside the nonsuit (Dunnett v. Thornton, 73 Conn. 1, 46 Atl. 158), and as the contract itself is made part of the complaint and annexed to it as an exhibit, no finding of fact is necessary in order to bring the ruling before this court for revision.

The third and fourth assignments of error, for exclusion of evidence, stand upon a different footing. They are not properly before us because not founded upon a finding of fact identifying the rulings appealed from, as required by § 792 of the General Statutes and § 5 of the Rules of this Court (Practice Book, 1908, p. 266). We have several times held that the certification of the entire evidence as part of the record on appeal is not of itself a sufficient basis for assignment of error in excluding or admitting evidence. Dennison v. Waterville Cutlery Co., 80 Conn, 596, 69 Atl. 1022; *386 Cadwell v. Canton, 81 Conn. 288, 70 Atl. 1025; Summa v. Dereskiawicz, 82 Conn. 547, 74 Atl. 906. This rule applies not only to appeals from a denial of a motion for a new trial on the ground that the verdict was against the evidence, and from a decision setting aside a verdict, but also to appeals from the denial of a motion to set aside a nonsuit. On such appeals the question whether the trial court erred in holding that the plaintiff had not made out a prima facie case is often affected by the rulings of the trial court in excluding evidence offered by the plaintiff for that purpose; and the same reason exists in such appeals as in any others for requiring the rulings on evidence, if appealed from, to be identified by a finding of the trial court. Otherwise the assignments of error may, as they do in this case, amount to an attempted appeal at large from all rulings made in respect of the subject-matter referred to therein, or from all rulings made during the examination of the witness named therein; leaving the selection of the particular rulings appealed from to be made at some subsequent time or to be ascertained by searching the entire evidence.

In this case, however, it happened that the rulings upon evidence are founded upon and involved in the interpretation of the contract, and they will be practically disposed of in determining the question whether the written contract excludes on its face any obligation on the contractor’s part to perform the work of making the joints. The contract and accompanying papers annexed to the complaint comprise a notice to contractors, general and particular specifications, a form of proposal for bid, the contract proper, and the bond sued on. The general character of the work is variously entitled in these papers. The specifications are entitled “Specifications for the Construction of a System of Gas Mains for The Bristol & Plainville *387 Tramway Company,” and this title suggests that the specifications were intended to cover a completely finished and jointed system of gas-mains. On the other hand, the bond sued on describes the contract as a contract “for the performance of certain work in connection with the excavating, laying and back-filling cast iron gas-pipe and fixtures therewith,” and this suggests with equal force that the contract was not for furnishing a completely finished system of gas-mains. The same inference is to be drawn from the notice to contractors, which was accompanied by the specifications and form of contract, and contains the company’s estimate of the quantities of work to be done as follows: “The company’s estimate of the quantities of work to be done, by which each of the bids will be compared, is as follows:—

“Trenching, laying, back-filling and re-surfacing
20,000 linear feet four (4) inch cast iron pipe and specials;
2.000 linear feet six (6) inch cast iron pipe and spe-
cials;
4,800 linear feet eight (8) inch cast iron pipe and specials;
8,300 linear feet ten (10) inch cast iron pipe and specials;
9.000 linear feet twelve (12) inch cast iron pipe and
specials.”

Pursuant to this notice the defendant contractor submitted a proposal to furnish all labor and materials called for by the specifications, for the following sums:—■

“ 1. For laying, back-filling, and excavating trench as required linear feet four (4) inch pipe nine 1/4 cents per ft. (9-1/4). 2. Same linear feet six (6) inch pipe eleven 1/4 cents per ft. (11-1/4). 3. Same linear feet eight (8) inch' pipe eleven 3/4 cents per ft. (11-3/4). 4. Same linear feet ten (10) inch pipe twelve 1/4 cents *388 per ft. (12-1/4). 5. Same linear feet twelve (12) inch pipe fifteen 1/4 cents per ft. (15-1/4). 6. Same linear feet per foot. 7. Rock excavation one dollar and seventy-five cents per cu. yd. ($1.75/100).”

This proposal was accepted and the contract, under the heading of "Prices and Payments,” provides for the contractor’s compensation as follows:—■

"Excavating, laying, and back-filling cast iron gas pipe and specials, drips, and gates,
20,000 linear feet four (4) inch per foot 9 1/4 cents $1,850.00;
2.000 linear feet six (6) inch per foot 11 1/4 cents
$225.00;
4,800 linear feet eight (8) inch per foot 11 3/4 cents $564.00;
8,300 linear feet ten (10) inch per foot 12 1/4 cents $1,016.75;
9.000 linear feet twelve (12) inch per foot 15 1/4 cents $1,372.50.”

In all of these papers there is constant reference to the specifications, and in the specifications the only direct reference to joint-making is contained in the section entitled "Pipe Laying,” of which the material portions are as follows:—

"Pipe laying shall be so conducted as to preclude the possibility of cracking any pipe in placing the same in the trench. Each pipe must be placed well home against the preceding one. All pipe cutting and fitting must be done without extra charge outside of the price per foot for laying the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon v. Indusco Management Corp.
320 A.2d 811 (Supreme Court of Connecticut, 1973)
Taft Realty Corp. v. Yorkhaven Enterprises, Inc.
150 A.2d 597 (Supreme Court of Connecticut, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
94 A. 290, 89 Conn. 382, 1915 Conn. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bristol-plainville-tramway-co-v-eveline-conn-1915.