Brister v. Ikenberry

300 S.W.3d 588, 2009 Mo. App. LEXIS 1811, 2009 WL 4927436
CourtMissouri Court of Appeals
DecidedDecember 22, 2009
DocketED 92993
StatusPublished
Cited by3 cases

This text of 300 S.W.3d 588 (Brister v. Ikenberry) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brister v. Ikenberry, 300 S.W.3d 588, 2009 Mo. App. LEXIS 1811, 2009 WL 4927436 (Mo. Ct. App. 2009).

Opinion

SHERRI B. SULLIVAN, P.J.

Introduction

Christopher Brister (Appellant) appeals from the summary judgment entered by the trial court in favor of Ozark Border Electric Cooperative (Respondent) on Appellant’s landowner liability claim against Respondent for injuries Appellant sustained while working as an employee of *590 Midwestern Power Line Inc. (MPL), a contractor of Respondent, on Respondent’s property. We reverse and remand.

Factual and Procedural Background

On May 31, 2002, Appellant was severely injured while installing split bolts on a cross-arm of an electric power pole and connecting the primary neutral to the ground when he was shocked by approximately 8,330 volts of electricity. At the time of his injury, Appellant was employed as a digger or groundman by MPL, which had contracted in October 2001 with Respondent, an electrical cooperative regulated under Chapter 394, 1 to carry out a rural electric project called “Missouri-33Butler” (the Project). The Project involved the relocation of an existing power line running alongside Highway 60 owned by Respondent to a new power line location necessitated by a Missouri Department of Transportation road project to expand Highway 60 from two to four lanes. In carrying out the relocation, the objective was to supply power to customers without interruption. The majority of work done by MPL was on energized lines, while Respondent estimates that about 20% of its work was done on energized lines. Respondent hired MPL because its employees primarily work on energized lines, according to Stanley Estes (Estes), Respondent’s General Manager.

The contract between MPL and Respondent was called the “Missouri-33-Butler, 2002 System Improvement Contract” or “Distribution Construction Contract (Labor Only)” (the Contract).

Appellant was installing split bolts on the cross-arm of the pole on the day of the accident because the split bolts had not been installed while the pole was on the ground, which is how the installation is normally done. 2 Once the Project was deemed “finished,” a “clean-up” or “punch” list was composed of tasks remaining to be completed. One item on the punch list was to install the split bolts on the pole that was no longer on the ground, but mounted in the ground with the lines attached and energized. The pole and line involved had been constructed and put in place by MPL. The line was energized at 14,400 volts when Appellant climbed the pole to install the split bolts.

Appellant had not worked with energized lines before. Appellant did not use and was not advised to use a bucket truck, rubber gloves or sleeves when making the repairs. When Appellant was working on the line, the breaker switch had been set to the “normal re-close” position. The normal re-close position causes the power to reestablish its continuity despite contact with the line, and therefore allows a person making contact with the power line to be continually shocked as opposed to the power cutting off after the person’s initial contact with the line. The “non-reclose” position, or protective relaying setting, would have caused the power to shut off once Appellant made contact with the line and endured the initial shock.

On May 29, 2007, Appellant filed suit against Respondent and the other named *591 individual respondent MPL employees for his injuries. 3 Appellant’s suit against all other individual respondents remains pending. This appeal only concerns Respondent, with regard to the trial court’s summary judgment in its favor, as follows.

Respondent filed its motion for summary judgment on July 21, 2008. On August 5, 2008, Appellant filed a motion for leave to file a first amended petition (FAP), and a request for continuance of Respondent’s summary judgment motion in order for Appellant to conduct discovery. On January 20, 2009, Appellant filed his response to Respondent’s summary judgment motion, and Respondent thereafter filed its reply thereto.

Count I of Appellant’s FAP alleged that the respondents who were employees and/or owners of MPL, had not trained Appellant as a lineman and that he had never worked close to an energized electrical line. Appellant also alleged that rubber gloves and rubber sleeves were not provided to him by them, which were required for work in close proximity to energized power lines and that he had not been trained to use rubber gloves and sleeves in these circumstances. Appellant claimed the individual respondents were negligent in directing Appellant to complete the installation of the split bolt on the subject pole in close proximity to energized lines without directing Respondent to de-ener-gize the line; without providing the proper training and safety equipment; and in failing to provide Appellant an insulated bucket truck lift from which to work.

In Count II of his FAP, Appellant claimed Respondent had contractual right of control and actual control over the details of the manner in which work was performed by MPL and the physical aetivities of the employees of MPL at the time of Appellant’s injuries. Appellant further alleged Respondent was aware that a dangerous condition existed with regard to the power lines and poles which involved an unreasonable risk of danger to Appellant.

Respondent’s motion for summary judgment asserted that Respondent was not liable to Appellant as the landowner because MPL was an independent contractor and Appellant was covered under MPL’s workers’ compensation policy. Respondent further averred that it had relinquished possession and control of the premises to MPL and that Respondent did not maintain substantial control over either the physical activities of MPL and its employees or the details of the manner in which the work was done so as to impose liability, either under a theory of negligence or vicarious liability.

On March 16, 2009, after hearing argument from both parties, the trial court granted summary judgment in favor of Respondent. The trial court found that Respondent “presented sufficient summary judgment facts to establish that it did not control the manner in which the work was done” and that none of the facts “establish that [Respondent] sufficiently controlled the physical activities of [MPL] employees or the details of the manner in which the work was done such as to impose liability on [Respondent].” Upon Appellant’s request, the trial court amended its judgment to find there was “no just reason for delay of the appeal of this judgment pursuant to Rule 74.01(b).” This appeal follows.

Points on Appeal

In his first point, Appellant contends that the trial court erred in granting Re *592 spondent’s motion for summary judgment because Respondent did not meet its burden of proof concerning the independent contractor exception to the general rule of a landowner’s liability to an invitee, as the court simply assumed that MPL was an “independent contractor” to whom Respondent relinquished “possession and control of the premises” when there were genuine issues of material fact regarding both of those necessary findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ricky Spaulding v. Conopco
740 F.3d 1187 (Eighth Circuit, 2014)
Huggins v. FedEx Ground Package System, Inc.
592 F.3d 853 (Eighth Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
300 S.W.3d 588, 2009 Mo. App. LEXIS 1811, 2009 WL 4927436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brister-v-ikenberry-moctapp-2009.