Bridwell v. Walton

27 Neb. Ct. App. 1, 925 N.W.2d 94
Nebraska Court of Appeals·Decided March 12, 2019·No. A-17-1011.·Published·Cited by 3 cases

Opinion

Pirtle, Judge.

*97 INTRODUCTION

Brett Walton and Gary Walton, doing business as Walton Contracting (collectively appellants), appeal from a jury verdict entered in Nuckolls County District Court in favor of Charles Bridwell and Sylvia Bridwell (collectively appellees) for breach of contract regarding appellants' construction of an addition to appellees' home. Appellants also appeal the jury verdict rejecting their counterclaim for unpaid work. Appellants allege that the district court erred in denying their motion to amend pleadings, in failing to dismiss the case for failure to *3 demonstrate the standard of workmanlike manner, and in denying their motion for new trial and remittitur on the basis of an excessive and unsupported jury verdict. For the reasons that follow, we affirm.

BACKGROUND

Appellees own a home in Superior, Nebraska. In 2013, they decided to have an addition to the home constructed. To this end, they contacted appellants in order to get an estimate of what such an addition would cost. Gary came to the home and examined the work to be done, including removal of the existing garage and construction of the new addition. Gary later provided a bid to appellees in the amount of $32,182.21 for labor and materials, which bid appellees accepted.

The work began in late September 2013 and included the removal of the existing garage and excavation and grading of some of the yard. The foundation was laid in October, along with the framing and the roof. Installation of windows and doors, as well as additional framing took place in November. In December, appellees met with Gary and Brett to expand the contract to cover finishing the interior of the addition, bringing the total bid to $63,207.46. Sheetrock was installed on the interior from December through March 2014.

*98 Charles had noticed and pointed out to appellants what he believed to be defects over the course of construction, including problems with the concrete, size of the crawlspace, windows, size of the doors, the way sheetrock was hung, a dip in the roof, and the way the roof was completed. Appellees provided a "punch list" to appellants in March 2014 listing the various issues they had with the project, which list was signed by both parties. Throughout March and April, work continued on the addition. Work was stopped during the month of May because appellees were out of state. On June 3, appellants returned to work and Charles had a conversation with Gary. While the parties dispute what was said during that conversation, it is undisputed that following the conversation, appellants *4 packed up their tools and left the worksite. Appellees had paid appellants $50,400 of the $63,207.46 total contract amount over the course of the construction.

Appellees brought the present action for breach of contract based on the failure to construct the addition in a workmanlike manner, and appellants filed an answer and counterclaim for unpaid work. A jury trial took place from April 25 to 27, 2017, at the conclusion of which the jury returned a verdict in favor of appellees in the amount of $40,000. The jury also found in favor of appellees on appellants' counterclaim. Appellants subsequently filed a motion for new trial and a motion for remittitur, which the district court denied.

ASSIGNMENTS OF ERROR

Appellants assign the district court erred in (1) denying their motion to amend the pleadings to conform to the evidence, (2) failing to dismiss the case for failure to demonstrate the standard of workmanlike manner, and (3) denying their motions for new trial and remittitur on the basis that the jury's verdict was excessive and unsupported.

STANDARD OF REVIEW

Permission to amend a pleading is addressed to the discretion of the trial court, and an appellate court will not disturb the trial court's decision absent an abuse of discretion. United Gen. Title Ins. Co. v. Malone , 289 Neb. 1006 , 858 N.W.2d 196 (2015).

A jury verdict will not be set aside unless clearly wrong, and it is sufficient if any competent evidence is presented to the jury upon which it could find for the successful party. Smith v. Colorado Organ Recovery Sys. , 269 Neb. 578 , 694 N.W.2d 610 (2005).

A motion for new trial is addressed to the discretion of the trial court, whose decision will be upheld in the absence of an abuse of that discretion. Id.

*5 ANALYSIS

Motion to Amend Pleadings to Conform to Evidence.

Appellants made a motion to amend the pleadings to conform to the evidence in order to include an affirmative defense of failure to mitigate damages on the basis that the issue of mold and water damage had not been pled, but had been implicitly tried. At trial, it was revealed, based upon photographs of the property, that water was infiltrating the structure. On cross-examination, appellants asked Charles what materials would be required to complete the project, assuming construction had been acceptable to the point appellants left the job, to which he responded that he was not sure, as there could be mold in the walls. Appellants did not object to this mention of mold and then further pressed Charles, asking about water damage inside *99 and outside the walls and whether he had done anything about it.

Free access — add to your briefcase to read the full text and ask questions with AI

Bridwell v. Walton, 27 Neb. Ct. App. 1, 925 N.W.2d 94 (Neb. Ct. App. 2019).

27 Neb. Ct. App. 1 (Bridwell v. Walton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

132 Ventures v. Active Spine Physical Therapy
318 Neb. 64 (Nebraska Supreme Court, 2024)
Tigerpaw Software v. Cherry
Nebraska Court of Appeals, 2021
In re Estate of Gabel
Nebraska Court of Appeals, 2019