Bridgewater Corp. v. Massachusetts Bay Transportation Authority

7 Mass. L. Rptr. 275
CourtMassachusetts Superior Court
DecidedApril 29, 1997
DocketNo. 965614F
StatusPublished

This text of 7 Mass. L. Rptr. 275 (Bridgewater Corp. v. Massachusetts Bay Transportation Authority) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridgewater Corp. v. Massachusetts Bay Transportation Authority, 7 Mass. L. Rptr. 275 (Mass. Ct. App. 1997).

Opinion

Barrett, J.

On January 30, 1997, this matter was before the Court for hearing on plaintiffs’ motions for summary judgment and a permanent injunction. In support of their summary judgment motion, plaintiffs Bridgewater Corporation (“Bridgewater") and W.H. Maze Company (“Maze”) argue that they are entitled to judgment as a matter of law that defendant Massachusetts Bay Transportation Authority (“MBTA”) breached the parties’Tri-Party Agreement (“Agreement”). Specifically, plaintiffs argue that the MBTA failed to remediate oil releases on the MBTA’s property in Bridgewater, Massachusetts, in accordance with the terms of the Agreement. As to the permanent injunction, plaintiffs argue that they will suffer irreparable harm, in the form of a civil penalty, if the MBTA is not ordered to remediate the oil releases.

The MBTA opposes both motions, arguing that a genuine issue of material fact exists regarding whether a “materially different scope of work” is required to complete the remediation. If that is so, the MBTA argues, it is not in breach because a clause in the Agreement renders the Agreement null and void in its entirety. The MBTA further argues that the Agreement is voidable due to a mutual mistake of fact. The MBTA opposes the plaintiffs’ request for a permanent injunction, arguing that plaintiffs have an adequate remedy at law.

For the reasons discussed below, plaintiffs’ motions are DENIED.

BACKGROUND

The following facts, and reasonable inferences therefrom are viewed in the light most favorable to the MBTA as the nonmoving party. Beal v. Board of Selectmen of Hingham, 419 Mass. 535, 539 (1995).

From October 1972 until November 1992, Bridgewater was the owner of property located at 106 Hale Street in Bridgewater, Massachusetts (“the Bridgewater parcel”). Maze was a tenant, and operated a nail factory. As part of the manufacturing process, oil was used to harden the nails. Maze stored this oil in four underground storage tanks (“tanks”); these tanks contained both virgin and waste oil. These tanks were physically located on property which bounds the Bridgewater parcel on the east (“the MBTA parcel”).2 The MBTA parcel is currently used for a freight railroad, but is being improved for use as a passenger railroad, as part of the Old Colony Railroad Project.3

In April 1992, the tanks were excavated and removed from the MBTA parcel by Bridgewater. When the tanks were removed, two of the tanks were observed to be leaking oil and/or hazardous materials into the soil and groundwater. The Massachusetts Department of Environmental Protection (“DEP”) was notified, and subsequently issued “Notices of Responsibility" to Bridgewater, Maze, and the EOTC.4 These notices recited that Bridgewater, Maze and the MBTA were responsible; pursuant to G.L.c. 21E, for the oil release and were obligated to assess and remediate the resulting contamination.

In response, Bridgewater and Maze undertook containment actions, including constructing collection lagoons and a recovery well and trench, in consultation with DEP. By March 1995, however, these efforts had not resulted in complete remediation of the contamination, and the parties disputed who was responsible for remediating the soil and groundwater contamination on the MBTA properly.

In November 1994, the parties began negotiations concerning the nature and scope of the remaining remediation, as well as who was responsible for performing the remediation. At the conclusion of the negotiations, on June 15, 1995, the MBTA, Bridgewater and Maze entered into the Agreement.

The Agreement provides in pertinent part as follows.

[276]*276E. Each Party for itself denies any and all responsibility and/or liability alleged in any Notice of Responsibility and any and all responsibility and/or liability for any other release . . .
G. The Parties wish to provide for the permanent remediation of the alleged Release and to allocate responsibility among them for the costs thereof. . . .
2. Nature of Work to be Performed The Private Parties intend to conduct, and the MBTA agrees to cooperate with, a complete and final remediation of the alleged Release such that no further actions will be necessary in order for such alleged Release to pose no significant or otherwise unacceptable risk to health, safety, public welfare or the environment during any foreseeable period of time (collectively, the “Work”). The Parties anticipate that the Work will include, without limitation, . . . the implementation of [an Immediate Response Action plan approved by the DEP] . . . including the physical removal and proper disposal of all [contaminants],
3. Physical Removal and Disposal Work to be Conducted by MBTA Contractor In order to perform the physical removal and disposal of the Contaminant (the “Physical Work” portion of the Work) [the MBTA contractor performing the commuter rail track upgrades shall perform the Physical Work], . . . The MBTA' shall cause the MBTA Contractor to implement and perform all Physical Work under the [Immediate Response Action] plan approved by DEP in accordance with this Agreement, such . . . plan and all applicable law. . . . The MBTA shall cause the MBTA Contractor finally to complete all such Physical Work no later than that date which is four (4) months after the date DEP approves the . .. plan for the Physical Work . . . (emphasis added).
4. Cost Sharing Subject to offset as provided below on account of the fees and expenses incurred due to the [Licensed Site Professional retained by Bridgewater and Maze], [Bridgewater and Maze] collectively shall reimburse the MBTA the aggregate sum of $150,000 (subject to such offset, the “Reimbursable Amount”) within thirty (30) days after [the physical work is completed and certain other conditions are met]. The Parties agree that the Reimbursable Amount is the portion of the costs of such Work equitably allocable to the Private Parties, after taking all facts and circumstances into account. [Bridgewater and Maze] shall be solely responsible for all fees, costs and expenses of the [Licensed Site Professional, subject to offset], . . . The MBTA shall be solely responsible for paying all costs of performing the Physical Work. . . . The Reimbursable Amount has been determined by the Parties based on their mutual expectation that DES will approve an [Immediate Response Action] plan which calls materially for the excavation and soil and free phase oil disposal work contemplated by the Excavation Contingency Plan prepared by [the Licensed Site Professional], Notwithstanding any contrary provision of this Agreement, if DEP requires a materially different scope of Work from that contemplated by the [Excavation Contingency Plan[ or requires any other work in excess of the [Excavation Contingency Plan] (the “Excess Work”), then this Agreement shall be of no force or effect as to such Excess Work and the Parties shall negotiate in good faith an equitable adjustment on account of such Excess Work, provided, however, that if any post-Physical Work monitoring and reporting is required by DEP, then the MBTA shall reimburse the Private Parties promptly upon request one-half the actual, invoiced cost of such monitoring and reporting. . . . (emphasis added).
6. Miscellaneous . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Whirty v. Lynch
539 N.E.2d 1064 (Massachusetts Appeals Court, 1989)
Maloney v. Sargisson
465 N.E.2d 296 (Massachusetts Appeals Court, 1984)
LaFleur v. C.C. Pierce Co.
496 N.E.2d 827 (Massachusetts Supreme Judicial Court, 1986)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Beatty v. NP CORP.
581 N.E.2d 1311 (Massachusetts Appeals Court, 1991)
Schwanbeck v. Federal-Mogul Corp.
592 N.E.2d 1289 (Massachusetts Supreme Judicial Court, 1992)
Allstate Insurance v. Bearce
589 N.E.2d 1235 (Massachusetts Supreme Judicial Court, 1992)
The DOVER POOL & RACQUET CLUB, INC. v. Brooking
322 N.E.2d 168 (Massachusetts Supreme Judicial Court, 1975)
Shea v. Bay State Gas Co.
383 Mass. 218 (Massachusetts Supreme Judicial Court, 1981)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Beal v. Board of Selectmen
646 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1995)
Lumber Mutual Insurance v. Zoltek Corp.
647 N.E.2d 395 (Massachusetts Supreme Judicial Court, 1995)
Starr v. Fordham
648 N.E.2d 1261 (Massachusetts Supreme Judicial Court, 1995)
Nashua Corp. v. First State Insurance
648 N.E.2d 1272 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
7 Mass. L. Rptr. 275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridgewater-corp-v-massachusetts-bay-transportation-authority-masssuperct-1997.