This text of Bridges Zoning Permit Approval - Decision on Motions (Bridges Zoning Permit Approval - Decision on Motions) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridges Zoning Permit Approval - Decision on Motions, (Vt. Ct. App. 2018).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 3-1-18 Vtec

Bridges Zoning Permit Approval DECISION ON MOTION

The present appeal is of a zoning permit issued to Robert Bridges (Applicant) by the Town of Plainfield (Town) Zoning Administrator for the construction of a single-family home and associated barn on his property located in Plainfield, Vermont. Inda Loso (Appellant) appealed that decision to the Town Development Review Board (DRB), which denied the appeal and granted the permit. Appellant then appealed that decision to this Court. Before the Court are the parties’ cross-motions for summary judgment. Applicant is represented by Daniel P. Richardson, Esq. Appellant is represented by L. Brooke Dingledine, Esq. Legal Standard Pursuant to V.R.C.P. 56(a), we grant summary judgment to a party “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). In determining whether there is any dispute over a material fact, “we accept as true allegations made in opposition to the motion for summary judgment, so long as they are supported by affidavits or other evidentiary material.” White v. Quechee Lakes Landowners’ Ass’n, Inc., 170 Vt. 25, 28 (1999) (citation omitted). When considering cross-motions for summary judgment, the Court considers each motion individually and gives the opposing party the benefit of all reasonable doubts and inferences. City of Burlington v. Fairpoint Commc’ns, Inc., 2009 VT 59, ¶ 5, 186 Vt. 332. Factual Findings We recite the following facts solely for the purposes of deciding the pending motions for summary judgment.

1 1. Applicant owns property located at the end of Cerutti Road (the Property). The Property is approximately 44.2 acres. 2. The Property is located in the Forest & Agricultural District as defined by the Town Zoning Regulations (Regulations) § 4.2. 3. The Property does not have frontage on a public road. 4. The Property was created in June 2009 when the Town granted Applicant a subdivision permit. 5. Section 3.4 of the Regulations is entitled “Required Frontage on or Access to Public Roads” and sets forth dimensional requirements for access roads, including rights-of-way. 6. Prior the issuance of the subdivision permit, Applicant submitted an application to the Town Planning Commission for approval of a right-of-way as an access to the subdivision. The right-of-way connects the end of Cerruti Road to Applicant’s lot and was created in by deed in 1917. 7. On April 6, 2009, the Planning Commission conducted a hearing and site visit to determine if the right-of-way complied with Regulations § 3.4. At the hearing, the Planning Commission orally approved the right-of-way as in compliance with § 3.4. On April 27, 2009, the Town issued the hearing minutes “To All Attendees of the Right of Way Hearing on April 6, 2009.” The minutes set forth the Town’s conclusions and the factual basis for these conclusions (the 2009 ROW Decision). The 2009 ROW Decision was not appealed. 8. Appellant owns property at the end of Cerutti Road. The deeded right-of-way is located on her property. 9. Appellant participated in the 2009 hearing and objected to the Town’s approval of the right-of-way. 10. On September 14, 2017, Applicant applied for a permit to build a single-family home with a detached barn on the Property. The Zoning Administrator granted the application on September 22, 2017. 11. Appellant subsequently appealed that decision to the DRB. The DRB affirmed the grant of the permit on December 13, 2017. Appellant then timely appealed that decision to this Court.

2 Discussion At issue within the cross-motions is Question 2 asking “[w]hether the Application and Project proposed . . . fails to comply with Section 3.4 of the Regulations . . . because the . . . lot has no frontage on a public road and is not benefited by an easement of at least 20 feet in width, and should be denied.” I. Whether the 2009 approval is final and binding on the parties. Applicant argues that the Town determined that the right-of-way complied with § 3.4 when it approved the right-of-way in the 2009 ROW Decision. As that decision was not appealed, it has since become final and binding on the parties. See 24 V.S.A. § 4472(d). Therefore, Applicant argues that the present appeal is an impermissible collateral attack on the 2009 ROW Decision and, as the final 2009 ROW Decision concluded the right-of-way complies with § 3.4, he is entitled to judgment as a matter of law. Appellant asserts that the 2009 ROW Decision is not final and binding because the Planning Commission failed to issue a written decision as required by 24 V.S.A. § 4464(b)(3). Further, Appellant argues that she never received a notice of a decision as required by § 4464(b)(3). A failure to appeal a decision results in all interested parties being bound by that decision. 24 V.S.A. § 4472(d). Decisions must be issued in writing, though meeting minutes may suffice, “provided the factual bases and conclusions relating to the review standards are provided in conformance with [§ 4464(b)].” 24 V.S.A. § 4464(b)(1). Decisions issued “shall also be mailed to every person or body appearing and having been heard at the hearing.” 24 V.S.A. § 4464(b)(3). Appellant participated in the 2009 ROW hearing at which the Planning Commission orally approved the right-of-way. Subsequent to that hearing, the Town issued the hearing minutes “To All Attendees of the Right of Way Hearing on April 6, 2009.” The minutes set forth the Town’s conclusions and the factual basis for these conclusions. Applicant asserts that he received the minutes in the mail on April 27, 2009. Based upon this Town action, Applicant offers that a final decision was issued following the 2009 ROW hearing.1

1 Applicant additionally argues that, even if the Court were to conclude no decision was rendered, the application was deemed approved on 45 days after the adjournment of the hearing if no decision were issued. 24 V.S.A. § 4464(b)(1). We note that the deemed approval remedy does not foreclose an interested persons

3 Appellant asserts in her affidavit in support of her motion for summary judgment that she never received these minutes. With respect to Applicant’s motion, we give Appellant the benefit of all reasonable doubts and inferences with respect to this assertion. The Vermont Supreme Court has recently provided guidance on the effect lack of notice has on the finality of a permit. See In re Mahar Conditional Use Permit, 2018 VT 20; see also In re Mathez Act 250 LU Permit, 2018 VT 55, ¶ 16 (interpreting Mahar in the context of an Act 250 permit). The Court noted in Mahar that the relevant appeal period beings to run when judgment is entered, not when an interested party receives notice of the decision. Mahar, 2018 VT 20, ¶ 13 (citing V.R.C.P. 77(d)(1)). This procedural rule seeks to protect the finality of judgments. Id., ¶ 16 (citations omitted). Because the applicable procedural rules seek to balance fairness and the finality of judgments, the rules “provide avenues to extend or reopen the appeal period for various reasons, including when individuals do not receive proper notice of the judgement they seek to appeal.” Id. Specifically, a party can follow the procedures set forth in V.R.A.P. 4(c), which permits the time for filing a notice of appeal to be reopened if: (1) the motion is filed within ninety days of entry of judgment or seven days of receipt of notice of judgment, whichever is earlier; (2) the court finds that the party entitled to notice did not receive it; and (4) no party would be prejudiced. V.R.A.P. 4(c), applicable here through V.R.E.C.P. 5(a)(2). Such a motion is not before the Court and the present appeal is not of the 2009 ROW Decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Burlington v. Fairpoint Communications, Inc.
2009 VT 59 (Supreme Court of Vermont, 2009)
In Re Appeal of Trahan Nov
2008 VT 90 (Supreme Court of Vermont, 2008)
Albarelli v. Albarelli
564 A.2d 598 (Supreme Court of Vermont, 1989)
In Re Appeal of Ashline
2003 VT 30 (Supreme Court of Vermont, 2003)
In Re Appeal of Fish
554 A.2d 256 (Supreme Court of Vermont, 1988)
In re Mathez Act 250 LU Permit (Sung-Hee Chung, Appellant)
2018 VT 55 (Supreme Court of Vermont, 2018)
White v. Quechee Lakes Landowners' Ass'n
742 A.2d 734 (Supreme Court of Vermont, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Bridges Zoning Permit Approval - Decision on Motions, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridges-zoning-permit-approval-decision-on-motions-vtsuperct-2018.