Brewery District Society v. Federal Highway Administration

211 F. Supp. 2d 902, 2002 U.S. Dist. LEXIS 19619, 2002 WL 1577830
CourtDistrict Court, S.D. Ohio
DecidedMarch 29, 2002
Docket98 CV 00075
StatusPublished

This text of 211 F. Supp. 2d 902 (Brewery District Society v. Federal Highway Administration) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brewery District Society v. Federal Highway Administration, 211 F. Supp. 2d 902, 2002 U.S. Dist. LEXIS 19619, 2002 WL 1577830 (S.D. Ohio 2002).

Opinion

OPINION AND ORDER DENYING CROSS MOTIONS FOR SUMMARY JUDGMENT

MARBLEY, District Judge.

This matter comes before the Court on the Motion for Summary Judgment of Plaintiffs Brewery District Society, Den-nison Place Association and Malcolm Cochran and the Motion for Summary Judgment of Defendant Federal Highway Administration (“FHWA”). 1 This case *904 began as an attempt by Plaintiffs to save from demolition the last five remaining buildings of the old Ohio State Penitentiary (“Ohio Pen”). Those buddings have since been demolished. Remaining at issue is the propriety-of the City of Columbus’s extension of Nationwide Boulevard through .the twenty-one acre Ohio Pen site and its widening of Neil Avenue along the site, and to what extent Defendant is obligated by federal statutes designed to protect historic properties to evaluate and mitigate the adverse impact of this construction, on the Ohio Pen site. Defendant currently seeks a ruling that it has done all it need do; Plaintiffs seek an order commanding Defendant to evaluate and mitigate the adverse impact on the Ohio Pen site of the extension of Nationwide Boulevard and the widening of Neil Avenue. For the reasons that follow, the Court hereby DENIES Plaintiffs’ Motion for Summary Judgment and DENIES Defendant’s Motion for Summary Judgment.

I. INTRODUCTION

This case is complicated, both factually and legally. Since it seems to the Court that the facts giving rise to this lawsuit would be easier to follow with some background, the Court will attempt to outline the parties’ respective legal arguments here, before a recitation of the relevant facts.

a. Plaintiffs’ Position

Since the Spring/Sandusky Interchange Project (“SSI Project”) was — and is — a large-scale federal highway project, it is a “major Federal action”. As such, its implementation is subject to all relevant federal historical protection statutes. The segment B-4, which would have connected Neil Avenue to Nationwide Boulevard, became a part of the SSI Project in 1984. In 1997, argues Plaintiff, the City of Columbus (“City”) decided that it would rather have Nationwide Arena than the then-contemplated B-4, and withdrew its plans to construct B — 4 and returned, with interest, the federal monies that it had spent planning the segment and acquiring the land necessary for its construction. Because the rest of the SSI Project was proceeding, though, the City still needed the additional capacity that B-4 would have . provided, and so needed to build an alternative connector.

If the City had asked for federal funds for this connector, or even not paid back the monies it had already spent on B-4, the FHWA would have had to perform a reevaluation of the B — 4 Finding of No Significant Impact (“FONSI”) and/or consider the impact of this alternative connector before granting its approval — as it did on January 29, 1998 — of the reevaluation of the Spring/Sandusky Interchange Environmental Impact Statement. Instead, the City and the Ohio Department of Transportation (“ODOT”) decided, in an attempt to avoid the strictures of the federal historical protection statutes, to use only City funds to build a road connecting Dublin Avenue to Nationwide Boulevard (through the middle of the Ohio Pen site) and widen Neil Avenue. The FHWA “assisted” the City in this project by not threatening the withdrawal of federal funds from the rest of the SSI Project to keep the City from demolishing the Ohio Pen site until all relevant federal impact and mitigation analyses had been performed in evaluating the ' City’s plan to build an alternative to B-4. Thus, because the City could not have avoided the federal statutes by “de-federalizing” and building B-4, were B^4 contemplated such that it would have adversely impacted the Ohio *905 Pen site, the FHWA should not be allowed to “assist” the City in making an end-run around federal law by “withdrawing” from one small part of the large-scale SSI Project in order to build an alternative to B-4 segment which does adversely impact the Ohio Pen site.

Defendant’s argument is somewhat simpler. Defendant argues that the B-4 project was at all times separate and independent from the SSI Project. When the City canceled its application for B-4 funding and repaid the federal funds it had been advanced on the B-4 project, that project was terminated in its entirety; thus, federal oversight also ceased at that point. The later locally-initiated and -financed construction of the Nationwide-Dúblin connector and widening of Neil Avenue is not somehow transmogrified into a federal project merely because it will relieve some of the same congestion that B-4 would have. Even were the Court to find that B-4 was a part of the SSI Project, the FHWA was not required to consider in its reevaluation of the Spring/Sandusky Interchange Environmental Impact Statement — which it approved on January 29, 1998 — the impact of the City’s decision to cancel that segment of the project when the B-4 segment was never built by any entity.

Whether B-4 was a part of the SSI Project is a question of fact on which each side has introduced enough evidence to survive summary judgment. The question of whether the de-federalization of one segment of a federal project amounts to improper segmentation when a non-federal actor then builds an alternative to that segment is a question of law, and a matter of first impression, for the Court.

II. FACTS

The Spring/Sandusky Interchange, which is located near downtown Columbus, Ohio, originally opened to traffic in the early 1950s. In 1965, plans were initiated to construct Interstate Route 70 (“1-70”) between 1-270 and the West Innerbelt. These plans included reconstruction of both the Spring/Sandusky Interchange at 1-670 and State Route 315 (“SR 315”) and the Mound/Sandusky Interchange, which links 1-70 to 1-71 and SR 315. The Mound/Sandusky Interchange was completed in 1976. The initial plans for the construction of the SSI Project were completed in 1971.- The SSI Project. plans were later modified in response to social, economic and environmental changes. The July 11, 1978 Project Program Form for what was to become the SSI Project included in the section entitled “Purpose and Description of Work”: “The study will include consideration of the connection of SR 315 to the ’ Fronb-Marconi one-way pair.”

In December 1981, the draft Environmental Impact Statement (“EIS”) for the SSI Project was completed. In the 1981 draft EIS, the SSI Project was described as follows:

construction of a new 1.3 mile section of 1-670 between Grandview Avenue and State Route 315, the relocation construction of 1.7 miles of 1-670 between S.R. 315 and Third and Fourth Streets, and the reconstruction of 2.0 miles of S.R. 315 from 1-70 to Third Avenue.... In addition, new streets have been added to complement the local street system.

One of these proposed new streets was identified as the Regional Center Connector from West Goodale Street to Neil Avenue, “with a proposed future extension to. Nationwide Boulevard.”

The draft EIS considered two build alternatives, alternative G and alternative H, and a no-build option. Alternative G was comprised of four segments: SSI, NIB, WIB and OLEN.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ross v. Federal Highway Administration
162 F.3d 1046 (Tenth Circuit, 1998)
Taft Broadcasting Company v. United States
929 F.2d 240 (Sixth Circuit, 1991)
Hawthorn Environmental Preservation Ass'n v. Coleman
417 F. Supp. 1091 (N.D. Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
211 F. Supp. 2d 902, 2002 U.S. Dist. LEXIS 19619, 2002 WL 1577830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brewery-district-society-v-federal-highway-administration-ohsd-2002.