Brett v. Lovejoy
This text of Brett v. Lovejoy (Brett v. Lovejoy) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF MAINE SUPERIOR COURT CIVIL ACTION YORK, ss. DOCKET NO. CV -09-53 6 A-l!;> - Yof! - .?/Ii-/~ 0 II I
STEPHEN M. BRETT,
Plaintiff
v. JUDGMENT
PETER LOVEJOY and RIVERSIDE EXCAVATION,
Defendants
Plaintiff Stephen Brett brought this action against defendants Peter Lovejoy and
Riverside Excavation to recover for alleged defects in work the defendants performed in
2003. The defendants move for summary judgment on all claims.
BACKGROUND Mr. Brett co-owns a parcel of land in Cape Neddick, Maine. (Supp. S.M.F. <]I 1.)
The property is currently improved by a three-car garage with living space above, and a
capped foundation for a future home. (Supp. S.M.F. <]I 2.) Mr. Brett has resided in the
garage apartment since 2006. (Supp. S.M.F. <]I 3.) In the fall of 2002, Mr. Brett contracted
with the defendants to install a septic system, excavate the home and garage sites,
remove trees and stumps, and install a driveway. (Supp. S.M.F. <]I<]I 5-6.) The written
contract cannot be located. (Supp. S.M.F. <]I 7.)
Prior to the start of work, Mr. Brett determined where the home foundation
IWOUld be located and used stakes to indicate where the defendants should dig. (Supp.
S.M.P. <]I9I 11-13.) Mr. Brett inspected the excavation work before the foundation was
l'nstaIled, and the excavation work met his layout and blueprints. (Supp. S.M.F. 1:~I 14 15.) The parties later discovered that the foundation was too close to the road to
accommodate the existing septic plan, so the plan had to be revised. (Supp. S.M.F. <]I 17.)
The revised plan was approved by the town and provided to the defendants, who then
installed the system. (Supp. S.M.F. <]I<]I 19-20.)
The defendants completed their work in the spring of 2003. (Supp. S.M.F. <]I 27.)
Mr. Brett then asked them to come back to widen the driveway and fill an adjacent
gully with gravel. (Supp. S.M.F. <]I 29.) Mr. Brett testified that the gully was part of the
original contract, but that no specific driveway width had ever been specified in the
parties' agreement. (Supp. S.M.F. <]I<]I 30-31; Brett Dep. at 35-37.)
Mr. Brett filed his initial complaint on February 26, 2009. He did not serve the
defendants, and on October 22, 2009, the court ordered the case dismissed unless a
motion to retain on the docket was filed. Mr. Brett filed the motion to retain on
November 19, 2009. The court gave him until December 22, 2009, to file an amended
complaint and until February 26, 2010 to serve the defendants with process. Mr. Brett
filed his amended complaint on December 23, 2009, and never completed service. The
defendants nonetheless filed an answer on March 9, 2010. They then filed this motion
for summary judgment on November 24, 2010.
DISCUSSION
Summary judgment is appropriate where there are no genuine issues of material
fact and the moving party is entitled to judgment as a matter of law. M.R. Civ. P. 56(c);
Levine v. RB.K. Caly Corp., 2001 ME 77, <]I 4, 770 A.2d 653, 655. Mr. Brett did not file a
statement of material facts in opposition to the defendants' motion, so the defendants'
asserted facts are deemed admitted. M.R. Civ. P. 56(h)(2) (2010).
The defendants' initial argument is purely procedural. While Mr. Brett's initial
complaint was filed before the statute of limitations had run on his claims, he never
2 served the complaint on the defendants. After obtaining leave of court to retain his case
on the docket, he served his amended complaint a day after the court-imposed deadline
of December 22, 2009. By this time, the statute of limitations had run. He mailed a copy
of this complaint to the defendants, but never attempted to complete service when they
failed to file a return. The defendants filed an answer, effectively waiving their
objections to the defective service. They ask, however, that the court not allow the time
of commencement to relate back to Mr. Brett's initial filing due to his dilatory handling
of his case.
The statute of limitations on civil actions requires that they be "commenced
within [six] years after the cause of action accrues ...." 14 M.R.S.A. §752 (2010). An
action is "commenced" by filing a complaint with the court. M.R. Civ. P. 3 (2010). Mr.
Brett commenced this action on the defendants' alleged breach within six years of its
occurrence. While his handling of this action does provide ample procedural grounds
for dismissal, the motion will be addressed on the merits.
Mr. Brett's complaint alleges that the defendants breached the parties' contract in
three ways. First, the defendants allegedly installed the septic system without a
"Septitech" system, which is a treatment system that allows the septic to handle a
greater volume of waste than it otherwise would. (Supp. S.M.F. 9I9I 21-23; Brett Dep. at
16, 29.) Second, the defendants did not make the driveway as wide as Mr. Brett would
have liked, and did not return to widen the driveway after he asked them to do so in
the spring of 2006. (Supp. S.M.F. 9I 29; Amd. Compl. 9I 7.) Finally, the defendants did
not fill a certain gully with gravel. (Supp. S.M.F. 9I9I 29-30.) From these alleged defects,
Mr. Brett charges the defendants with breach of contract, promissory estoppel, unjust
enrichment, violations of the Unjust Trade Practices Act (UTPA), intentional
3 misrepresentation, negligent misrepresentation, and malice warranting punitive
damages.
The difficulty with Mr. Brett's claims is that now, after the period for discovery
has run, he has produced scant evidence supporting his claim. He cannot produce a
copy of the parties written contract. In his deposition, he stated that he knew the
defendants had not installed a Septitech tank because a representative from White
Knight, a rival system, told him so. (Brett Dep. at 30-31.) This is clear hearsay. Mr. Brett
has not otherwise verified that the system was not installed as contracted for.
Regarding the driveway and the gully, Mr. Brett admitted that a precise
driveway width was never specified in the contract. (Brett Dep. at 37.) He also admitted
that the defendants had fully completed their work within the scope of the contract
before leaving the site in 2003. (Brett Dep. at 35.) These admissions essentially deprive
Mr. Brett of a cause of action. He cannot recover in contract or under the UTPA because
the contract was performed. He cannot recover in tort because he has not produced
evidence of wrongdoing, and because the economic loss doctrine clearly bars a tort
action where the only allegation is that the defendants' work did not meet the standards
contracted for. See Bayreuther v. Gardner, 2000 Me. Super. LEXIS 140 (June 21, 2000)
(Mills, J.) (economic loss doctrine bars tort claim for defectively designed and installed
septic system); L.L. Bean, Inc. v. United States Mineral Prods. Co., 1999 Me. Super. LEXIS
323 (Dec. 3, 1999) (Crowley, J.) (plaintiff cannot recover in tort for negligently
manufactured and installed fireproofing absent allegation of personal injury or damage
to other property); see also Marquis v. Farm Fainily Mut. Ins. Co., 628 A.2d 644, 652 (Me.
1993) (no independent tort for bad-faith breach of contract).
4 CONCLUSION
In response to the Defendants' Motion for Summary Judgment, Mr.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Brett v. Lovejoy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brett-v-lovejoy-mesuperct-2011.