Bressi v. Dobroth

74 Pa. D. & C.2d 705, 1975 Pa. Dist. & Cnty. Dec. LEXIS 73
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedMay 21, 1975
Docketno. 1566
StatusPublished

This text of 74 Pa. D. & C.2d 705 (Bressi v. Dobroth) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bressi v. Dobroth, 74 Pa. D. & C.2d 705, 1975 Pa. Dist. & Cnty. Dec. LEXIS 73 (Pa. Super. Ct. 1975).

Opinion

SPORKIN, J.,

— This matter is before the court on the motion of Thomas E. Bressi, Jr. and Rodgers Bressi (jointly referred to as “Bressi”) to correct an award of arbitrators entered in favor of Richard E. Dobroth (“Dobroth”).

The facts out of which this controversy arises may be summarized as follows:

On July 20,1965, Bressi and Dobroth entered into a written contract (hereafter, “the agreement”) whereby Dobroth was to perform architectural services in connection with the development by Bressi of an apartment complex on St. Croix in the United States Virgin Islands; the agreement contemplated two stages: Stage A, which encompassed construction of 18 apartment units, and Stage B, which provided for follow-up construction of 32 additional units at the option of Bressi.1
“l.(a) The Architect shall perform professional service . . . in connection with the development by Owner of one acre of the subject tract. . . with approximately eighteen (18) apartment units, and such onsite and offsite improvements and utilities as Owner shall deem necessary (hereinafter called Stage A).
“(b) In the event that Owner shall determine to develop the [707]*707remaining two acres of the subject tract, in addition to the development referred to as Stage A, Architect shall perform professional services, as hereinafter defined, in connection with the construction of such additional building or buildings (hereinafter called Stage B).”

Dobroth was to receive as compensation for architectural services rendered in connection with Stage A, five and one-half percent of the “cost of work”; in the event Stage B was also constructed, for the total services rendered by Dobroth in connection with the two stages, he was to receive three and one-half percent of the total “cost of work”; “cost of work” was defined, in paragraph 3 of the agreement, to mean “the actual cost to Owner (Bressi), as opposed to estimates secured by either party, of the work let under a general contract to complete the building or buildings to be constructed in the stage of the Project which is the subject of the calculation.”2

Thereafter, Dobroth performed the architectural services contemplated by the agreement for Stage A and, at the express direction of Bressi, Dobroth proceeded with and completed the architectural drawings and specifications in connection with Stage B. Dobroth, in the course of performing these services received periodic fee payments from Bressi which ultimately totalled $47,500.3 The contractor to whom the architectural plans for Stage A and B were submitted, however, presented a bid which was rejected by Bressi because it exceeded the amount he had budgeted for the project.

[708]*708Subsequently, at Bressi’s request, Dobroth made architectural revisions in an effort to reduce the building costs to a more acceptable figure. For reasons not pertinent here, though, no construction based upon Dobroth’s plans was ever commenced, and when it became apparent that the project as designed by Dobroth was abandoned, Dobroth made demand upon Bressi for compensation in addition to the $47,500 he had already received, and also for recompense for the outlay of certain expenses.4 When this demand was refused by Bressi, the dispute was submitted to arbitration, as provided for in the agreement. Bressi counterclaimed, contending that the $47,500 fees paid to Dobroth constituted overcompensation by Bressi to Dobroth, and sought reimbursement from Dobroth for such alleged overpayment. After hearing extensive testimony from both sides, the arbitrators entered an award in favor of Dobroth in the amount of $16,272.47 which was comprised of $12,408 for additional compensation and $3,863.20 for expenses. This motion by Bressi to correct the award followed and is now before us.

DISCUSSION

At the outset, we must note the scope of our review. Under the Pennsylvania Arbitration Act of 1927 which governs the controversy,5 the court is empowered to modify or correct the award “[w]here the award is against the law, and is such that had it [709]*709been a verdict of the jury the court would have entered a different or other judgment notwithstanding the verdict.”: Act of April 25, 1927, P.L. 381 (No. 248), sec. 11,5 P.S. §171(d). Applying this standard to the case at bar, it is clear that the arbitrators’ determination, involving as it does the construction of a contract, constitutes a matter of law which falls squarely within the ambit of review prescribed by the Arbitration Act of 1927: Framlau Corp. v. Upper Dublin Sch. Authority Board, 219 Pa. Superior Ct. 369, 281 A. 2d 464 (1971); Baldwin v. Magen, 279 Pa. 302, 123 Atl. 815 (1924); Standiford v. Kloman, 234 Pa. 443, 83 Atl. 311 (1912). And it is equally clear, in our opinion, that the award of the arbitrators was based upon an erroneous interpretation of the agreement and must be modified.

The contentions of the parties which were clearly expostulated at the outset of the arbitration hearing, coincided, at least in part, factually. Both Dobroth and Bressi conceded that the agreement contained no express provision as to compensation to be paid for architectural services in the event of abandonment of the project, as in the instant case, where plans have been completed but prior to undertaking any construction thereof. The parties differed, however, on the legal effect of this contractual omission, Dobroth arguing that he should receive what was “fair and equitable” and Bressi contending that the proper measure of recovery was quantum meruit.

The issue for the arbitrators was thus drawn squarely: where the contract is silent as to remuneration, should compensation be in accord with a “fair and equitable” standard or on a quantum meruit basis. The arbitrators, however, for reasons [710]*710which are obscure, ignored the clear consensus of the parties and instead chose to make the finding, on which their award was based, that it was the intention of the parties that the compensation provisions of the agreement regarding termination “during” Stage A apply even where the project is abandoned prior to any undertaking of construction.6

[711]*711Although the agreement provided that if the project were terminated during, but prior to commencement of, Stage B, Dobroth would receive fees based, inter alia, upon five and one-half percent of the “contemplated cost” of completing Stage A, the agreement did not so provide with respect to abandonment where plans were submitted for both stages but construction was begun. Yet the arbitrators evidently strained the agreement provisions, beyond the four corners thereof, to compute Dobroth’s fee as based, in part, upon a similar percentage of the contemplated cost of constructing Stages A and B according to Dobroth’s plans. This constitutes, in our opinion, clear error. The issue of the intent of the parties having been foreclosed by the agreement of the parties themselves, the arbitrators, as a matter of law, should have applied a quantum meruit standard of recovery in the absence of any express contractual provision concerning payment for the services in question: Simsohn v. Wetter, 111 Pa. Superior Ct. 523, 170 Atl. 422 (1934); Jull’s Estate, 313 Pa. 42, 169 Atl. 237 (1933).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwin J. Schoettle Co. Appeal
134 A.2d 908 (Supreme Court of Pennsylvania, 1957)
Foulke v. Miller
112 A.2d 124 (Supreme Court of Pennsylvania, 1955)
Jull's Estate
169 A. 237 (Supreme Court of Pennsylvania, 1933)
Simsohn v. Wetter
170 A. 422 (Superior Court of Pennsylvania, 1933)
Peoples Natural Gas Co. v. Braddock Wire Co.
25 A. 749 (Supreme Court of Pennsylvania, 1893)
Standiford v. Kloman
83 A. 311 (Supreme Court of Pennsylvania, 1912)
Orth & Bro. v. Board of Education
116 A. 366 (Supreme Court of Pennsylvania, 1922)
Baldwin v. Magen
123 A. 815 (Supreme Court of Pennsylvania, 1924)
Framlau Corp. v. Upper Dublin School Authority Board
281 A.2d 464 (Superior Court of Pennsylvania, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
74 Pa. D. & C.2d 705, 1975 Pa. Dist. & Cnty. Dec. LEXIS 73, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bressi-v-dobroth-pactcomplphilad-1975.