Breck Construction v. Air Liquide America

CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 21, 2001
Docket00-20586
StatusUnpublished

This text of Breck Construction v. Air Liquide America (Breck Construction v. Air Liquide America) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Breck Construction v. Air Liquide America, (5th Cir. 2001).

Opinion

UNITED STATES COURT OF APPEALS For the Fifth Circuit

No. 00-20586

BRECK CONSTRUCTION COMPANY, INC.

Plaintiff-Counter Defendant-Appellant,

VERSUS

AIR LIQUIDE AMERICA CORPORATION; AIR LIQUIDE PROCESS & CONSTRUCTION, INC.

Defendants-Counter Claimants-Appellees.

Appeal from the United States District Court For the Southern District of Texas (H-98-CV-2533) November 21, 2001

Before SMITH, DUHÉ and WIENER, Circuit Judges.

Per Curiam:1

Plaintiff and counter-defendant, Breck Construction Co., Inc.

appeals a summary judgment holding it liable for damages under a

construction contract. Contracting with Breck were Air Liquide

America Corporation (“ALAC”), owner of a plant in Longview, Texas,

and Air Liquide Process & Construction, Inc. (“ALPC”), the

engineer, both of whom are defendants and counter-claimants

(collectively called “AL”).

Breck sued AL on sworn account for overdue invoices, for

1 Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. breach of contract, and for fraud. AL countersued for breach of

contract and breach of warranty pertaining to a tower erected by

Breck which leaned some inches from vertical and rust damage

discovered in the gear box of a compressor installed by Breck. On

cross motions for summary judgment, the district court found for

AL, denying Breck’s claims and awarding AL damages, minus amounts

withheld on Breck’s invoices. Breck appeals. Also at issue are

the denial of Breck’s claim for statutory attorney’s fees and

multiple claims of abuse of discretion in pre-trial matters. For

the following reasons, we reverse and remand.

DISCUSSION

A. Rust Damage. Breck challenges the district court’s summary

judgment finding it liable for rust damage to the gear box of the

compressor. We have independently reviewed the summary judgment

evidence and find the undisputed evidence as follows: AL ordered

the compressor new from Cooper Industries, who delivered it in

parts directly to Breck, who then assembled and installed it at the

Longview plant. At some point after installation, rust damage,

gasket residue, and standing water were found in its gear box. The

contract charged Breck with the responsibility to

exercise due care and attention in the handling of all equipment and material supplied to him, to eliminate or minimize the possibility of damage before, during and after installation, and [to] provide suitable and adequate forms of protection and storage to maintain said equipment and material in a clean, functional and sound state. 3 R. 870.

The question whether a party fails to exercise due care in

2 performing its duties is ordinarily a question for a factfinder.

See Harle v. Krchnak, 422 S.W.2d 810, 815 (Tx. App.-Houston [1st

Dist.] 1967. writ ref’d n.r.e.)(discussing “reasonable care” in

negligence context); McBrayer v. Teckla Inc., 496 F.2d 122 (5th Cir.

1974)(discussing “in a reasonable and businesslike manner” in Texas

contract).

As in Harle, this record contains evidence that Breck

exercised “some degree of care.” Some evidence suggests that Breck

sought to follow the manufacturer’s installation guidelines by

refusing to break the manufacturer’s seals or open the gear box

cover unless in the presence of a manufacturer’s representative.

AL had agreed to provide all technical representatives at no cost

to Breck when required during equipment installation, and Breck

requested AL to schedule a visit from a Cooper authorized

representative. When AL refused due to budgetary constraints and

instructed Breck to proceed with assembly without the inspection

and supervision of a factory representative, Breck promptly began

assembly and mounting of the compressor in July 1997, without

opening the gear box. 11 R. 3796-95; 16 R. 5583; 3 R. 802, 700,

702, 699, 685-82.

There is evidence, too, that if a vendor’s representative had

been present at the assembly of the compressor, he would

customarily have opened and inspected the internals of the gear

box, and that he alone was authorized to remove inspection plates

3 to check the gear box.2 Evidence suggests that ALAC waived the

presence of factory representative at the compressor assembly, and

that ALPC assured Breck it would not be responsible for rust. 11

R. 3795, 3800; 3 R. 687-82; 20 R. 6945, 6946.

Additional evidence established that AL requested Breck to

nitrogen purge the compressor, to prevent oxidation and rust.

Other evidence suggests that water was already present when the

compressor was assembled, and that no one knows when the rust

formed. According to Breck’s expert Papacostas, a nitrogen purge

would not drive out settled puddles of water or remove accumulated

rust. Finally on the issue of nitrogen purge, the installation

manual prohibits alteration of the equipment without the presence

of a Cooper representative; also, the contract would prohibit

nitrogen purge without written permission of ALPC.3 11 R. 3795; 3

R. 700.

From the foregoing evidence, a fact finder might conclude that

Breck met its contractual duty by exercising all the care that was

2 A factory representative did come in October 1997 for “final assembly, line-up, and start-up” of the compressor. At that time ALPC directed Breck to disassemble the compressor to open ports for inspection, and extensive corrosion was then discovered. 3 R. 699. 3 The contract provides, “In handling and installing . . . newly supplied equipment, the Contractor . . . shall not modify, rework or in any other way change the said equipment, except with the prior written permission of the Engineer.” 3 R. 869.

4 “due” under the circumstances to protect the gear box and

compressor upon their arrival. Summary judgment is inappropriate

when the evidence is susceptible of different conclusions or

different inferences by the trier of fact. Chen v. City of

Houston, 206 F.3d 502, 506 (5th Cir. 2000), cert. denied, 121 S.Ct.

2020 (2001). Swanson v. General Servs. Admin., 110 F.3d 1180, 1191

(5th Cir.) cert. denied, 522 U.S. 948 (1997). Summary judgment is

inappropriate even where the parties agree on the basic facts, but

disagree about the factual inferences that should be drawn from

those facts. Impossible Electronic Techniques, Inc. v. Wackenhut

Protective Systems, Inc.,669 F.2d 1026, 1031 (5th Cir. 1982).

Accordingly, summary judgment on this issue is reversed and the

matter remanded for trial.

B. The Argon Tower. Breck also appeals the summary judgment

holding it liable for AL’s expenses to re-establish verticality of

the argon tower. The district court based its judgment on finding

that the tower declined from vertical by 3.5” within a year, and

holding that Breck warranted that the tower would not decline by

more than 1" in a year. We first address the scope of Breck’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Breck Construction v. Air Liquide America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/breck-construction-v-air-liquide-america-ca5-2001.