Brear v. Washington State Highway Commission

389 P.2d 276, 63 Wash. 2d 815, 1964 Wash. LEXIS 548
CourtWashington Supreme Court
DecidedFebruary 13, 1964
Docket36646
StatusPublished
Cited by5 cases

This text of 389 P.2d 276 (Brear v. Washington State Highway Commission) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brear v. Washington State Highway Commission, 389 P.2d 276, 63 Wash. 2d 815, 1964 Wash. LEXIS 548 (Wash. 1964).

Opinion

Finley, J.

Walter Brear, plaintiff-respondent, brought the present action to foreclose a statutory lien for the contract price of crushed rock he supplied to Washington Asphalt Company, defendant-appellant, for use in constructing the approaches to the Hood Canal bridge. The amount due Brear from Washington Asphalt on account of this bridge job (contract #6151) is not in dispute, and Brear has received payment on the amount due, less the sum of $2,934.16, claimed and withheld by Washington Asphalt Company as a setoff. The propriety of the alleged setoff, the principal issue in this appeal, involves overpayments allegedly made to Brear on previous contract work on the Krain-Veazie road (contract #6239), and concerns the *816 amount Brear was entitled to be paid for crushed rock for that job.

Thus, while the present lawsuit was brought to collect an amount claimed to be due for crushed rock delivered on the bridge job, the only issue or dispute concerns or relates to the previous and separate Krain-Veazie road job (contract #6239). It may be helpful in distinguishing between the contracts to keep in mind the diagrams set out below, following this paragraph. In each instance, or contract, the state of Washington was the “buyer,” and contracted with a general contractor (a different one for each job), who engaged Washington Asphalt to do paving work. Washington Asphalt, in turn, engaged Brear to supply crushed rock for use in the paving operations; and Brear (also in each instance) ultimately assigned his interests (payments due) to the Olympia State Bank & Trust Company (additional plaintiff) for financing purposes.

Road Contract #6239 Bridge Contract #6151

State of Washington State of Washington

Bass Const. Company John Hopkins Company

Washington Asphalt Washington Asphalt

Walter D. Brear Walter D. Brear

Olympia Bank & Trust Olympia Bank & Trust Company Company

On the Krain-Veazie road job (contract #6239), the payments by Washington Asphalt to Brear totaled $37,-889.80. At the time of payment, this figure was based upon preliminary estimates of the quantity of Brear’s crushed rock which Washington Asphalt would use in the road. However, when the final determinations were made as to the amount, used, and the state’s final computations became available, Washington Asphalt claimed that it had made overpayments in the amount now claimed as a setoff, $2,934.16. Brear, on the other hand, claimed that an additional balance remained due of $648.24. All parties agree *817 that Brear was entitled to payment only for the amount of his crushed rock which Washington Asphalt actually used in the road construction; but they disagree as to how much crushed rock was used and as to how the amount should be determined. While Brear claims the right to rely upon the final quantities certified to the state by its resident engineer, Washington Asphalt denies that such figures accurately represent the actual amount of rock used in the road. The following items or amounts, representing crushed rock supplied by Brear, were certified to the state by its resident engineer and were the amounts on which the state based its payment to the general contractor, Bass Construction Company:

Item 17 ................ 10,308 tons

Item 18................ 9,187 tons

But, Washington Asphalt alleges that a lesser quantity of crushed rock was actually used, and that payment by Bass Construction to Washington Asphalt was based upon such lesser quantities as follows:

Item 17 .............. 8,997.7 tons

Item 18 .............. 7,715.0 tons

Washington Asphalt agrees that Brear was entitled to all payments which Washington Asphalt received from Bass Construction for Brear’s crushed rock. But the total payments actually made by Washington Asphalt to Brear on Road Contract #6239 were in excess of this, coming within $600 of the larger, “certified,” tonnage figures based upon the aforementioned preliminary estimates, made as the job progressed. To recoup from Brear the amount of the allegedly excessive payments, Washington Asphalt deducted this from the sum admittedly due Brear on the Bridge Contract #6151.

Bass and Washington Asphalt, in appellant’s brief, explain the discrepancy between the official state figures and their method of computing payment to Brear in the following manner:

“Bass Construction Company had done extra work consisting of digging culverts, making manhole connections, *818 installing guideposts and doing shoulder work, for which it had made a claim with the King County resident engineer in the sum of $6,267.78. After negotiating this with the resident engineer, Bass Construction Company settled with the resident engineer on a sum of $5,842.20 for Bass’ extra work. This sum of $5,842.20 in extra work was handled by the resident engineer’s increasing on the final pay estimate quantities of rock as follows:
“To item 17 he added........1,310 tons
“To item 18 he added........ 1,472 tons
“Total.................... 2,782 tons
“This is the 2,782 tons which is in dispute in this litigation. Bass’ contract price for this tonnage was $2.10. Therefore, this pay procedure netted him the $5,842.20 upon which he and the resident engineer had agreed for his extra work.”

Both Bass and the King County resident engineer testified that the above indicated “conversion factor” was actually used by them; that the amount of “rock tonnage” so added to the figures supplied to the state in fact represented no rock, but rather work done by Bass; and that the only reason for using the conversion factor was to “cut red tape” in requesting additional payment for the extra work done by Bass. They stated that Brear should be paid for the actual, not the fictitious, amounts of crushed rock used, and they would determine this amount by subtracting the amount of the conversion factor from the totals certified to the state of Washington records.

The trial court, sitting without a jury, found, however, that Washington Asphalt was estopped to deny liability for the total amount of gravel reflected in the state’s final figures. Judgment was entered for the plaintiffs (1) in the amount of the claimed setoff, $2,934.24, (2) for an additional sum of $531.24 (the additional amount necessary to bring the payment up to the state certified tonnages less $117 due the defendants for a certain bulldozer rental), and (3) for attorney’s fees of $2,500. Washington Asphalt has appealed.

The basis of the estoppel found by the trial court was a letter from Mr. Wilcox, vice-president of Washington As *819 phalt, to Walter A. Johnson, president of the Olympia State Bank & Trust Company, dated March 31, 1960, wherein Wilcox states:

“Payment made to you thus far on above contract is for rock in stockpile. The price of $1.20 per ton is for asphaltic concrete in place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weidner Property Management, LLC v. Brian Cutsforth
Court of Appeals of Washington, 2023
Reilly v. Sageser
467 P.2d 358 (Court of Appeals of Washington, 1970)
S & D Paving Co. v. Douglas County
428 P.2d 720 (Washington Supreme Court, 1967)
Brear v. Washington State Highway Commission
407 P.2d 423 (Washington Supreme Court, 1965)
Nakanishi v. Foster
393 P.2d 635 (Washington Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
389 P.2d 276, 63 Wash. 2d 815, 1964 Wash. LEXIS 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brear-v-washington-state-highway-commission-wash-1964.