BRB Contractors, Inc. v. Akkerman Equipment, Inc.

935 F. Supp. 1156, 1996 WL 377092
CourtDistrict Court, D. Kansas
DecidedOctober 4, 1996
DocketCivil Action 95-4063-DES
StatusPublished
Cited by3 cases

This text of 935 F. Supp. 1156 (BRB Contractors, Inc. v. Akkerman Equipment, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BRB Contractors, Inc. v. Akkerman Equipment, Inc., 935 F. Supp. 1156, 1996 WL 377092 (D. Kan. 1996).

Opinion

MEMORANDUM AND ORDER

SAFFELS, District Judge.

This matter is before the court on the Motion for Summary Judgment (Doc. 77) by United States Fidelity and Guaranty Company (“USF & G”) in response to the Amended Third-Party Complaint (Doe. 39) by Akker-man Equipment Company, Inc. (“Akker-man”) against USF & G.

*1158 I. BACKGROUND

The following are what the court finds to be the uncontroverted facts relevant to USF & G’s summary judgment motion.

The Johnson County Unified Waste Water District awarded five contracts for the construction of the Mill Creek Regional Main Sewer District No. 1. One of the contracts, Contract No. 3-1, provided for the construction of the Little Mill Creek interceptor and four branch sewer lines.

Sieben Contracting, Inc. (“Sieben”) submitted the lowest bid and was awarded the main sewer contracts which included construction of the Little Mill Creek Project.

On September 24, 1993, USF & G, as surety, issued a Statutory Bond to the State of Kansas naming Sieben as principal. The bond is in the penal sum of $5,513,000.

In approximately October 1993, a representative of American Tunnelling, Michael L. Smith, approached Akkerman and requested a bid for the design, manufacture, and lease of a tunnel boring machine for use on the Little Mill Creek Project.

On November 2, 1993, Sieben entered into a subcontract with American Tunnelling to perform the tunnelling work on the Little Mill Creek Project.

On January 26, 1994, Akkerman issued a written quotation to American Tunnelling for the lease of a tunnel boring machine. The quotation stated that American Tunnelling could lease the machine from Akkerman at a rate of $59,600 for the first month, plus $50,100 for each additional month.

In the summer of 1994, American Tunnell-ing advised Akkerman that it was experiencing financial difficulties and, therefore, could not lease the tunnel boring machine from Akkerman. American Tunnelling also advised Akkerman that it was preparing to enter into an agreement with BRB Contractors, Inc. (“BRB”) for BRB to lease the boring machine from Akkerman.

In August 1994, American Tunnelling entered into a contract with BRB Contractors, Inc. to perform the tunnelling work on the Little Mill Creek Project. The agreement was entitled “Subcontract Agreement.” Throughout the Subcontract Agreement between BRB and American Tunnelling, BRB is referred to as a subcontractor of American Tunnelling. The subcontract agreement was drafted by Mike Welch, President of BRB, and forwarded to Lisa Bongino, President of American Tunnelling, for her review. On the same day that BRB entered into the agreement with American Tunnelling (August 17, 1994), BRB also entered into a written contract with Akkerman for the lease of a tunnel boring machine and related equipment.

Under the terms of the “Subcontract Agreement,” BRB agreed to provide all major equipment and supplies required on the Little Mill Creek Project. American Tun-nelling agreed to supply a crew of laborers and the technical know-how necessary to complete the project. BRB paid the payroll and related employment taxes for American Tunnelling’s crew.

American Tunnelling’s subcontract with Sieben prohibits the assignment of any monies due American Tunnelling under the agreement without the written consent of Sieben. Sieben was never asked and never agreed to an assignment of monies between American Tunnelling and BRB.

On or about August 17, 1994, BRB and Akkerman entered into a lease agreement for use of Akkerman’s tunnel boring machine on the project. American Tunnelling was not a party to the lease of the Akkerman tunnel boring machine for use on the Little Mill Creek Project. BRB and Akkerman are the only parties to the lease agreement.

In Akkerman’s Amended Third-Party Complaint, it is alleged that John Noter-mann, an employee of Akkerman, contacted an employee of USF & G, Scott Guest, to inquire as to whether Akkerman would be covered under the bond if it supplied the tunnel boring machine to the project. The phone conversation between John Noter-mann and Scott Guest occurred on August 3, 1994, during which Mr. Noterman did not advise Mr. Guest to whom the tunnel boring machine would be supplied. Mr. Guest was not told if the machine was being supplied to Sieben, American Tunnelling, BRB or to any other entity. At this point, negotiations be *1159 tween Akkerman and BRB for the lease of the tunnel boring machine had not yet commenced.

II. DISCUSSION

A. The standard for summary judgment

A court shall render summary judgment upon a showing that there is no genuine issue of material fact and that the movant is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(e). The rule provides that “the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).

The substantive law identifies which facts are material. Id. at 248, 106 S.Ct. at 2510. A dispute over a material fact is genuine when the evidence is such that a reasonable jury could find for the nonmovant. Id. “Only disputes over facts that might properly affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Id.

The movant has the initial burden of showing the absence of a genuine issue of material fact. Shapolia v. Los Alamos Nat'l Lab., 992 F.2d 1033, 1036 (10th Cir.1993). The movant may discharge its burden “by ‘showing’—that is, pointing out to the district court—that there is an absence of evidence to support the nonmoving party’s case.” Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 2554, 91 L.Ed.2d 265 (1986). The movant need not negate the nonmovant’s claim. Id. at 323, 106 S.Ct. at 2552-53.

Once the movant makes a properly supported motion, the nonmovant must do more than merely show there is some metaphysical doubt as to the material facts. Matsushita Elec. Indus. Co. v. Zenith Radio, 475 U.S. 574, 586, 106 S.Ct. 1348, 1355-56, 89 L.Ed.2d 538 (1986). The nonmovant must go beyond the pleadings and, by affidavits or depositions, answers to interrogatories, and admissions on file, designate specific facts showing there is a genuine issue for trial. Celotex, 477 U.S. at 324, 106 S.Ct. at 2553 (interpreting Fed.R.Civ.P. 56(e)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowen Engineering, Corp. v. Pacific Indemnity Co.
83 F. Supp. 3d 1185 (D. Kansas, 2015)
Digital Ally, Inc. v. Z³ Technology, LLC
864 F. Supp. 2d 1050 (D. Kansas, 2012)
Sunfresh, Inc. v. Bean Acres, Inc.
180 F. Supp. 2d 1224 (D. Kansas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
935 F. Supp. 1156, 1996 WL 377092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brb-contractors-inc-v-akkerman-equipment-inc-ksd-1996.