Braun v. Watson

898 N.E.2d 75, 178 Ohio App. 3d 413, 2008 Ohio 5078
CourtOhio Court of Appeals
DecidedSeptember 29, 2008
DocketNo. 08CAE040013.
StatusPublished

This text of 898 N.E.2d 75 (Braun v. Watson) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Braun v. Watson, 898 N.E.2d 75, 178 Ohio App. 3d 413, 2008 Ohio 5078 (Ohio Ct. App. 2008).

Opinion

Hoffman, Presiding Judge.

{¶ 1} Plaintiff-appellant and cross-appellee Robert A. Braun appeals the March 10, 2008 judgment entry of the Delaware County Court of Common Pleas, overruling his objections to the magistrate’s April 20, 2007 decision with respect to an award of attorney fees, and approving and adopting said decision as an order of the court. Defendants-appellees and cross-appellants Peter Watson et al. appeal the same with respect to the trial court’s overruling their objections to the magistrate’s decision, which ordered partial enforcement of the parties’ previous settlement agreement.

STATEMENT OF THE FACTS AND CASE

{¶ 2} Appellant and appellees are neighbors. They live on adjoining parcels. Appellant was the plaintiff in a prior action against appellees relative to stormwater runoff in appellant’s backyard, case No. 04-CV-H-09-0958. On the eve of trial, the parties entered into a written settlement agreement.

{¶ 3} Section 1 of the agreement reads: “[Appellees] shall cause Buckeye Landscape (or another qualified contractor if Buckeye fails to timely perform) to re-grade the entire Disputed Area by lifting the existing sod, lowering the grade approximately 2”-3”, hauling away the excess soil and reinstalling the sod. The parties agree that the intent of the foregoing is to insure that surface water *415 flowing across [appellant’s] Lot will exit [Ms] lot onto [appellees’] Lot and drain in such a manner that water will not accumulate or “pond” on [appellant’s] Lot.”

{¶ 4} Section 2 of the agreement provides: “[Appellees] shall cause the Remedial Measures to be completed no later than October 15, 2005, subject to the scheduling priorities of Buckeye Landscape. After completing the Remedial Measures, [Appellees agree] not to alter the grade of the Disputed Area in the future or to otherwise impede the flow of surface water off of [appellant’s] Lot. At [appellant’s] expense, Hockaden and Associates shall be entitled to field verify the water will drain to from [sic] [appellant’s] Lot to the ‘original drain.’ If Hockaden and Associates concludes that the water will not so drain, then Hockaden and Buckeye Landscape will agree upon the appropriate corrective action. If Hockaden and Buckeye cannot agree as to the corrective action, the parties will agree upon an independent engineer to be the final arbiter of the issue. [Appellees agree] to cause Buckeye Landscape to complete such corrective action within 14 days of notice of the measures needed * *

{¶ 5} Appellees had Buckeye Landscape perform certain work. Appellant was not happy with the completed work, claiming it was not carried out in accordance with the agreement. Appellant ultimately filed a complaint against appellees, alleging breach of the agreement and seeMng specific performance. Appellants counterclaimed, maintaining that the agreement required the parties to submit any disputes to an independent engineer who would be the final arbiter of the issues in dispute. Appellees also filed a motion to enforce the alternative-dispute-resolution provision set forth in the agreement, requesting that the trial court issue an order to that effect. Appellant filed a motion for partial summary judgment, alleging that appellees had breached the terms of the agreement as the entire disputed area had not been regraded. The trial court denied the motion, finding that a genuine issue of material fact existed as to whether the entire disputed area had been regraded. The matter proceeded to trial before the magistrate on November 21, 2006, on this issue.

{¶ 6} The magistrate found that the agreement did not define the disputed area. Based upon an original sketch of appellees’ backyard, which was prepared by appellees’ expert, as well as the expert’s testimony, the magistrate determined the disputed area to be 30 feet by 30 feet. Appellees’ expert also testified that if excavation did not occur to the tree line on appellees’ property, the remedial measures called for in the agreement were not satisfied. Such excavation did not occur. A representative of Buckeye Landscape, who viewed the completed work, testified that the regraded/resodded area was only 20 feet by 20 feet. The magistrate concluded that appellees had not completed the remedial measures as required by the agreement. The magistrate further found that the regrading of the disputed area did not comply with the terms of the agreement. Several *416 experts testified that the regrading that had been done did not lower the grade the two to three inches required by the agreement. The magistrate recommended after the entire disputed area was regraded, any unresolved issues relative to drainage be sent to an independent arbiter.

{¶ 7} The parties each filed objections to the magistrate’s decision. Appellant objected to the magistrate’s failure to recommend appellees pay appellant’s attorney fees, expert fees, and costs as appellees were the “unsuccessful party” under Section 8.8 of the agreement.

{¶ 8} Appellees objected to the magistrate’s finding in favor of appellant, finding the disputed area to be 30 feet by 30 feet, finding that the regrading did not comply with the terms of the agreement and granting their motion to enforce only in part.

{¶ 9} The trial court overruled all of the objections and adopted the magistrate’s decision via judgment entry filed March 10, 2008.

{¶ 10} It is from this entry that appellant appeals, raising as his sole assignment of error:

{¶ 11} “I. The trial court erred in failing to award to plaintiff-appellant Robert A. Braun his attorneys’ fees experts’ fees and costs because the plain language of the parties’ settlement agreement provided that the ‘unsuccessful party shall pay the other party’s attorneys’ fees experts’ fees and costs.’ ”

{¶ 12} Appellees cross-appeal, assigning as error:

{¶ 13} “I. The trial court erred in adopting the magistrate’s recommendation that the court grant the appellees/cross-appellants’ motion to enforce the settlement agreement in part.

{¶ 14} “II. The trial court erred in adopting the magistrate’s determination that appellees/cross-appellants did not cause buckeye landscape to execute the work called for in the settlement agreement.

{¶ 15} “HI. The trial court erred in determining that the magistrate’s recommendation to find in favor of appellant represents a legal determination that appellees/cross-appellants breached the terms of the settlement agreement.”

APPEAL I

{¶ 16} In his sole assignment of error, appellant maintains that the trial court in failing to order appellees to pay his attorney fees, expert fees, and costs as required by the clear and unambiguous language of the agreement, specifically Section 8.8.

*417 {¶ 17} Section 8.8 of the agreement provides: “Should either party be required to enforce this Agreement, the unsuccessful party shall pay the other party’s attorneys’ fees, experts’ fees and costs in an amount to be determined by the Court.”

{¶ 18} Appellees contend that they do not fall within the definition of “unsuccessful party” because the magistrate’s decision with respect to appellant merely amounted to a declaration as to what constitutes the disputed area.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
898 N.E.2d 75, 178 Ohio App. 3d 413, 2008 Ohio 5078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/braun-v-watson-ohioctapp-2008.