Brandt v. Hallwood Management Co.

560 N.W.2d 396, 1997 Minn. App. LEXIS 282, 1997 WL 104322
CourtCourt of Appeals of Minnesota
DecidedMarch 11, 1997
DocketCX-96-1557
StatusPublished
Cited by17 cases

This text of 560 N.W.2d 396 (Brandt v. Hallwood Management Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandt v. Hallwood Management Co., 560 N.W.2d 396, 1997 Minn. App. LEXIS 282, 1997 WL 104322 (Mich. Ct. App. 1997).

Opinion

OPINION

THOMAS G. FORSBERG, Judge.

Appellant challenges the trial court’s summary judgment ruling that his cause of action was barred by the two-year statute of limitations under Minn.Stat. § 541.051, subd. 1(a) (1996). We reverse and remand.

FACTS

Respondent Hailwood is the property manager for the American National Bank Building in St. Paul. A major tenant in the building is the American Bank Corporation (ABC). In 1992, ABC became interested in leasing the 22nd floor but wanted to lease the space as an unimproved shell and remodel the space to suit its needs. Hailwood contracted with Minnesota Landmark Construction Company (Landmark) to tear down, or demolish, the space back to a shell. This work entailed removing the partition walls, the carpet, ceiling grid, and the light fixtures, etc. Hailwood intended to salvage the light fixtures so they could be used as replacement fixtures for other tenants. Landmark subcontracted the electrical work to respondent Royal Electric Company (REC). REC was to take down the lights, de-energize the electrical lines, - and “drop” or disconnect the light fixtures so the demolition work could proceed.

REC dispatched two electricians to perform the work, Jeff Menth and Tom Ciekin-ski. The electrical work took approximately five hours to complete and was completed on the morning of July 29, 1992. In all, the demolition work was completed within two or three days. After the demolition work was done, Kevin Brink, the senior property manager for Hailwood at the time, did a “walk-through” of the space and assumed the shell to be safe for remodeling to begin.

ABC contracted with McGough Construction Company (McGough), the general contractor, to do the remodeling work. After the demolition work was done, Brink contacted either ABC’s representative or McGough to inform them that the demolition work was completed. Approximately one month later, on August 21, 1992, a permit to remodel the space applied for. Construction started on August 25, 1992. Prior to this time, there was no work being done on the space.

On September 8, 1992, appellant Craig Brandt, a carpenter with Zintl, Inc., was the first to arrive on the job site. Ken Thompson, McGough’s superintendent, told him that everything was set and that he could begin his work wherever he wanted. On September 10,1992, as he was installing metal studs and tracks, Brandt came into contact with an energized 277-volt electrical line. The resulting electrical shock caused him to fall from the scaffold on which he was working. He fractured his neck and suffered other injuries.

On May 3, 1995, Brandt brought suit against REC, alleging that REC was negligent, careless, and reckless in the manner in which it de-energized the electrical lines. Brandt also brought suit against Hailwood, claiming negligent maintenance, operation, and inspection of the property. Brandt further alleged that both respondents misrepresented that the electrical lines were de-ener-gized.

ISSUES

I. Are appellant’s claims against Royal Electric Company barred by the two-year statute of limitation set forth in Minn.Stat. § 541.051, subd. 1(a) (1996)?

II. Do claims arising from the negligent performance of services fall within the language of Minn.Stat. § 541.051, subd. 1(a)?

*399 ANALYSIS

I.

When reviewing an appeal from summary judgment, this court asks: (1) whether there are any genuine issues of material fact and (2) whether the lower court erred in its application of the law. State by Cooper v. French, 460 N.W.2d 2, 4 (Minn.1990). On appeal, the evidence must be viewed in the light most favorable to the party against whom judgment was granted. Fabio v. Bel-lomo, 504 N.W.2d 758, 761 (Minn.1993). Construction of a statute of limitation is a question of law that this court reviews de novo. Sarafolean v. Kauffman, 547 N.W.2d 417, 419 (Minn.App.1996) (citing H.D. v. White, 483 N.W.2d 501, 502 (Minn.App.1992), review denied (Minn. July 10,1996)).

II.

The question presented in this appeal is whether an individual performing demolition work in anticipation of remodeling work is covered by the protection of Minn.Stat. § 541.051. Appellant argues that the language of the statute does not cover demolition work, that REC did not construct an improvement to real property, and that his injuries did not result from the defective and unsafe condition of any improvement made to the real property. Respondent, on the other hand, argues that the demolition work it performed was part of a “continuous remodeling process” that resulted in the construction of improvements to the real property.

Minn.Stat. § 541.051, subd. 1(a) (1996), provides that

Except where fraud is involved, no action by any person in contract, tort, or-* otherwise to recover damages for any . injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition-of an improvement to real property, nor any action for contribution or indemnity for damages sustained on account of the injury, shall be brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property or against the owner of the real property more than two years after discovery of the injury * * *.

For REC to be covered by the protection of Minn.Stat. § 541.051, subd. 1, three elements must be satisfied: (1) REC must have constructed an improvement to real property; (2) appellant’s claim must arise out of the defective and unsafe condition of the improvement; and (3) the defective and unsafe condition of the improvement must be the cause of appellant’s injuries.

Initially, we must determine whether the demolition work preformed by REC constituted the construction of an improvement to real property within the meaning of Minn. Stat. § 541.051. Appellant argues that Minn. Stat. § 541.051 is inapplicable because the language of the statute does not specifically include those individuals who perform demolition work and also, that construction work does not include demolition work. According to appellant, the plain and ordinary meaning of “construction” is distinctly different from the meaning of the word “demolition.” Conversely, respondent argues, and appellant concedes, that the demolition work performed by REC was in preparation for the construction/remodeling performed by McGough and without the demolition work, the actual construction could not have commenced. Respondent maintains that its work was simply part of a “continuous remodeling process.”

Although a strict interpretation of Minn.Stat. § 541.051 is required, courts are to give effect to the plain meaning of the statute’s words “without resort to technical legal constructions of its terms.” Pacific Indem. Co. v. Thompson-Yaeger, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schupp v. United Fire & Casualty Co.
821 N.W.2d 824 (Court of Appeals of Minnesota, 2012)
Allianz Insurance Co. v. PM Services of Eden Prairie, Inc.
691 N.W.2d 79 (Court of Appeals of Minnesota, 2005)
Merritt v. Mendel
690 N.W.2d 570 (Court of Appeals of Minnesota, 2005)
In Re Wren
685 N.W.2d 721 (Court of Appeals of Minnesota, 2004)
Nolan and Nolan v. City of Eagan
673 N.W.2d 487 (Court of Appeals of Minnesota, 2003)
Lederman v. Cragun's Pine Beach Resort
247 F.3d 812 (Eighth Circuit, 2001)
Lila Lederman v. Cragun's Pine Beach Resort
247 F.3d 812 (Eighth Circuit, 2001)
Carven v. Hickman
763 A.2d 1207 (Court of Special Appeals of Maryland, 2000)
Buck v. Freeman
619 N.W.2d 793 (Court of Appeals of Minnesota, 2000)
Witso v. Overby
609 N.W.2d 618 (Court of Appeals of Minnesota, 2000)
Johnson v. 1996 GMC Sierra, VIN: 1GTEK19R4TE551384
606 N.W.2d 455 (Court of Appeals of Minnesota, 2000)
In Re Irwin
232 B.R. 151 (D. Minnesota, 1999)
Fisher v. County of Rock
580 N.W.2d 510 (Court of Appeals of Minnesota, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
560 N.W.2d 396, 1997 Minn. App. LEXIS 282, 1997 WL 104322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandt-v-hallwood-management-co-minnctapp-1997.