Brander v. Town of Warren

18 Misc. 3d 477
CourtNew York Supreme Court
DecidedDecember 7, 2007
StatusPublished
Cited by1 cases

This text of 18 Misc. 3d 477 (Brander v. Town of Warren) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brander v. Town of Warren, 18 Misc. 3d 477 (N.Y. Super. Ct. 2007).

Opinion

OPINION OF THE COURT

Donald A. Greenwood, J.

Petitioners are residents and landowners in the Towns of Warren and Stark, who challenge two special use permits issued in June of 2007 by the respondent town boards authorizing the construction of the Jordanville Wind Power Project. This CPLR article 78 petition seeks to annul and vacate actions taken and determinations made by the respondent town boards, alleging a violation of, inter alia, the State Environmental Quality Review Act (SEQRA) and the Open Meetings Law. The proposed project is for the construction of a 68-turbine wind farm in the subject towns in Herkimer County which, when fully operational, will generate 136 megawatts of electric power from the wind which will be introduced into the New York State Electric Grid.

I. Scoping

The petitioners allege that the Warren Town Board, as the SEQRA lead agency, and the respondents Jordanville Wind, LLC and Community Energy, Inc. (hereinafter CEI) engaged in scoping for the draft environmental impact statement (DEIS) for the project in a way that prevented the petitioners and other members of the public from participation and that they thus committed a fatal procedural SEQRA error. The SEQRA [479]*479implementing regulations make it clear that scoping is not required: “The primary goals of scoping are to focus the [environmental impact statement] (EIS) on potentially significant adverse impacts and to eliminate consideration of those impacts that are irrelevant or nonsignificant.” (6 NYCRR 617.8 [a].) The mandate that agencies implement such procedural mechanisms under SEQRA to the fullest extent possible reflects the legislature’s view “that the substance of SEQRA cannot be achieved without its procedure, and that departures from SEQRA’s procedural mechanisms thwart the purposes of the statute. Thus it is clear that strict, not substantial, compliance is required.” (Matter of King v Saratoga County Bd. of Supervisors, 89 NY2d 341, 347 [1996].) The record here shows that there was no formal election to conduct scoping. To the contrary, the final EIS (FEIS) indicates that the lead agency did not pursue scoping (at 52), that scoping was not conducted (at 73, 121), and that the project was not “publically scoped” (at 97, 99). The resolution passed by the Town of Warren Town Board, as lead agency, indicates that only an “informal scoping document” was prepared and circulated. (Resolution at 245.) Subsequently, when the Town of Warren issued its positive declaration on March 13, 2006 for the project under SEQRA, the town checked the box “Type I” on the required form and in the next section entitled “Scoping,” the box is checked “No.” Inasmuch as scoping is not required by the regulation and the town board, as lead agency, specifically elected not to engage in scoping at the time it issued its positive declaration, the petitioners’ argument in this respect is without merit.

II. “Hard Look” at Potential Environmental Impacts

The petitioners challenge the respondents’ compliance with SEQRA’s substantive requirements, alleging that the Town of Warren Town Board, as lead agency, failed to take the requisite “hard look” at the potential environmental impacts. The Court of Appeals has held that in reviewing an agency approval of a development project for compliance with SEQRA the substantive obligations must be viewed in the light of the rule of reason. (See Matter of Jackson v New York State Urban Dev. Corp., 67 NY2d 400 [1986].) In reviewing whether a determination was made in accordance with SEQRA and its implementing regulations a court is limited to reviewing whether “the determination was made in violation of lawful procedure, was affected by an error of law or was arbitrary and capricious or an abuse of discretion.” (Matter of Dunk v City of Watertown, 11 [480]*480AD3d 1024, 1024 [4th Dept 2004] [internal quotation marks omitted], quoting Matter of Gernatt Asphalt Prods. v Town of Sardinia, 87 NY2d 668, 688 [1996].) In so reviewing, the court may first review the agency procedures to determine whether they were lawful, and second, may review the record to determine whether the agency identified the relevant areas of environmental concern, took a “hard look” at them and made a “reasoned elaboration” of the basis for its determination. (Jackson at 417, quoting Aldrich v Pattison, 107 AD2d 258, 265 [2d Dept 1985]; see also Gernatt.)

A. Alternatives

The petitioners claim that the respondents failed to properly evaluate and analyze sufficient and acceptable alternatives to the project. The regulations require that an EIS contain a description and evaluation of the range of reasonable alternatives to the action that are feasible considering the objectives and capabilities of the project sponsor. (See 6 NYCRR 617.9 [b] [5] [v].) The petitioners contend that the respondents failed to evaluate possible alternatives involving shorter or fewer turbines, the phasing in of turbines, as well as their location, and that the respondents failed to provide the level of detail necessary to permit comparable assessment of those alternatives. In commenting on the alternatives analysis set forth in the DEIS, the Department of Environmental Conservation (DEC) noted that

“there is no record in the DEIS of specific alternative proposals that were considered in making these conclusions, and no supporting data to validate either the conclusion that the wind resource does not allow for a project of different scale then the one proposed, or that a smaller scale project is not economically viable. Data demonstrating the basis for the conclusions generated as a result of review and comparison of specific alternate proposals of different project scales or alternatively a fuller discussion of the ‘various siting constraints’ that ‘dictate the size and layout of a wind power project’ should be included in the FEIS.” (Record at 1430-1443.)

While the court’s role is not to weigh the desirability of any proposed action or choose among alternatives, but only to ensure that the agency has satisfied the substantive and procedural requirements of SEQRA and of the regulations implementing it (see Matter of Village of Westbury v Department of Transp. of [481]*481State of N.Y., 75 NY2d 62 [1989]; see also Dunk), to be meaningful, any choice among alternatives must be based on an awareness of all reasonable options, with the degree of detail required varying with the circumstances and nature of each proposal. (See Matter of Town of Dryden v Tompkins County Bd. of Representatives, 78 NY2d 331 [1991].) In the present case, the respondents failed to consider all reasonable options. Although the DEIS and FEIS mention that commentators advocated the consideration of alternative project sites or location, alternative turbine size, alternative project size, alternative project design/ layout, alternative project scale and magnitude or technologies, alternative construction phasing and the alternative of no action whatsoever, the Town of Warren, as the lead agency, declined to follow the DEC’S recommendation to perform an alternative analysis with supporting data, dismissing the recommendation as unreasonable. The FEIS contains two separate areas of discussion of alternatives.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York State Nurses Ass'n v. State University
39 Misc. 3d 588 (New York Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
18 Misc. 3d 477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brander-v-town-of-warren-nysupct-2007.