Brandenburg v. SF & G. CO., INC.

114 A.2d 604, 207 Md. 413, 53 A.L.R. 2d 378, 1955 Md. LEXIS 319
CourtCourt of Appeals of Maryland
DecidedJune 13, 1955
Docket[No. 172, October Term, 1954.]
StatusPublished
Cited by4 cases

This text of 114 A.2d 604 (Brandenburg v. SF & G. CO., INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandenburg v. SF & G. CO., INC., 114 A.2d 604, 207 Md. 413, 53 A.L.R. 2d 378, 1955 Md. LEXIS 319 (Md. 1955).

Opinion

COLLINS, J.,

delivered the opinion of the Court.

This is an appeal from a judgment entered in favor of the appellee, defendant, as the result of an instructed verdict granted at the end of the appellant’s, plaintiff’s, case.

On April 12, 1954, the plaintiff, Claude F. Brandenburg, filed a declaration in assumpsit against the defendant, S. F. & G. Company, Inc., alleging that he had performed work for the defendant in superintending carpentry work and general supervision of construction of apartments, that he had not been paid for his work, and asking damages therefor.

After demand, a bill of particulars was filed by the plaintiff stating that he had entered into an oral agreement with the defendant to perform and supervise work on Sections A, B and C of defendant’s apartment construction at a salary of $150.00 per week, plus a bonus of $10.00 for each apartment unit completed. He was in fact paid by the defendant $150.00 per week and $10.00 as bonus for each of the 250 apartment units in Sections A, B and C. Before Sections A, B and C were completed the defendant, through its agents, assigned the plaintiff the same duties on Sections D, E, F and G of the whole project and continued to pay plaintiff $150.00 per week. The construction of Sections A, B, C, D, E, F and G was continuous and uninterrupted and work on the new sections was begun before' earlier *415 sections were completed. Plaintiff supervised the work of the complete development from the time he first orally contracted to do the- work about June, 1950, until all the units were completed and occupied in June, 1952. At no time was he informed by the agents and officers of the defendant that he would not be paid the $10.00 bonus on each apartment In additon to the salary of $150.00 per week. It was understood by him that as the new work on Sections D, E, F and G was assigned to him he was to be paid for such new work at the same rate he was paid for Sections A, B and C, that is, $150.00 per week, plus a bonus of $10.00 for each apartment unit completed in Sections D, E, F and G. Neither the defendant nor anyone acting in its behalf complained of the work done by the plaintiff and his work was accepted as fully performed. Six hundred and fifty-five apartments were completed in Section D, E, F and G for which the plaintiff is entitled to $6,550.00 or $10.00 for each apartment completed. After the apartments were completed in Sections D, E, F and G he demanded the bonus of $6,550.00 from the agents and officers of the defendant and they refused to pay the said bonus. After the construction was completed on all the apartments the agents of the defendant hired the plaintiff to generally supervise the maintenance and care of the apartment development at a salary of $150.00 per week. Plaintiff and the agents and officers of defendant mutually agreed orally that, if either party was dissatisfied with the other, they would give thirty days notice to terminate the agreement. When the plaintiff demanded his bonus of $6,550.00 on Sections D, E, F and G from the agents of defendant on or about February 15, 1954, they refused to pay the bonus to him and he, thereupon, gave defendant thirty days notice that he was quitting. The agents of defendant, thereupon, told him that he had had no vacation since he started work. Therefore, he could stop work at that time and they would pay him his regular salary through the end of March, 1954, at the rate of $150.00 per week.

*416 At the trial of the case plaintiff testified in part that he entered into a written contract with the defendant about May, 1949, to do carpentry work on Sections A and B. Subsequent to the execution of that contract about June, 1950, the former carpentry contract was cancelled by all the parties and an oral agreement was entered into between the parties by which plaintiff was to be paid $150.00 per week, plus a bonus of $10.00 per apartment, and five percent of all he saved defendant on 250 apartment units in Section A, B and C. This agreement will be referred to herein as the June, 1950, agreement. The plaintiff proceeded under that oral agreement and was paid $150.00 per week for his work on Sections A, B and C. After Sections D, E, F and G were started plaintiff requested and was paid $2,500.00 representing $10.00 per apartment for Section A, B. and C of the project. Before Sections A, B and C were completed work was started on Sections D, E, F and G and the agents of defendant assigned the plaintiff to work on the new sections of the project and continued to pay him $150.00 per week. At one time in his testimony plaintiff stated that there was never any other agreement made after that of June, 1950. He further stated that after work was started on Sections D, E, F and G he moved into one of the apartments and was told that he would not be charged any rent for it, as they wanted him there from 45 to 50 hours a week “most Saturdays, either half a day or all day I would put in.” He later testified that for the 655 apartments in Sections D, E, F and G it was “their agreement” that he was to receive a bonus of $10.00 per apartment. Although Sections D, E. F and G were completed in 1952, he did not ask for his bonus of $6,550.00 until February, 1954, as he had not needed the money before that time, but when he made the demand, he needed the money in a lump sum to go back into business. He again testified that there was no agreement other than the agreement of June, 1950. He took it for granted that he was to get the same bonus for Sections D, E, F and G. There was *417 never any change in the agreement after it was originally made. After testimony was offered by the plaintiff, in colloquy with the trial judge, the following was said: “The Court: No, he [Claude F. Brandenburg] says very definitely, that his agreement was to A, B and C, that he never had any understanding about D, E, F, and G, never talked to the boys. Mr. Porter: [attorney for plaintiff] We concede that point.”

The defendant moved for a directed verdict claiming that plaintiff had offered no evidence to establish a contract that he was to be paid by the defendant $10.00 for each apartment constructed in Sections D, E, F and G. The trial judge, finding that there was nothing to establish “a new or an extension of that agreemnt on D, E, F and G,” directed a verdict for the defendant and entered a judgment for costs. From that judgment appellant appeals.

Assuming, without deciding, that there was no agreement other than that of June, 1950, by which the appellee agreed to pay the appellant the sum of $150.00 per week and the $10.00 bonus for each apartment completed in Sections A, B and C, and without any further reference to pay, the appellant was instructed to continue the same work on Sections D, E, F and G, and he performed said work, and there was no denial of these facts, we are of opinion that there was sufficient evidence from which the jury could have found that the same agreement applied to Sections D, E, F and G and that appellant was to recieve the same pay.

It is said in 1 Williston, Contracts, Rev. Ed., Sec. 90: “Where a contract of employment for a definite time is made and the employee’s services are continued after the expiration of the time, without objection, the inference is that the parties have assented to another contract for a term of the same length with the same salary and conditions of service, following the analogy of a similar rule in regard to leases.” In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brazil v. Menard, Inc.
D. South Dakota, 2022
CPC Health Corp. v. Goldstein (In Re CPC Health Corp.)
81 F. App'x 805 (Fourth Circuit, 2003)
Labrecque v. Sunbird Boat Co., Inc.
873 F. Supp. 946 (D. Maryland, 1994)
Lerner v. Ammerman
467 A.2d 187 (Court of Special Appeals of Maryland, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
114 A.2d 604, 207 Md. 413, 53 A.L.R. 2d 378, 1955 Md. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandenburg-v-sf-g-co-inc-md-1955.