Bradson Mercantile v. Joseph Crabtree

CourtCourt of Appeals of Tennessee
DecidedFebruary 16, 1999
Docket02A01-9710-CV-00272
StatusPublished

This text of Bradson Mercantile v. Joseph Crabtree (Bradson Mercantile v. Joseph Crabtree) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradson Mercantile v. Joseph Crabtree, (Tenn. Ct. App. 1999).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON ______________________________________________

BRADSON MERCANTILE, INC.,

Plaintiff-Appellant,

Vs. Shelby Circuit No. 79449-1 C.A. No. 02A01-9710-CV-00272 JOSEPH H. CRABTREE, JR., Individually; SHUTTLEWORTH, SMITH, McNABB & WILLIAMS, A Partnership; KENNETH R. FILED SHUTTLEWORTH, Individually; GARY K. SMITH, Individually; February 16, 1999 LELAND McNABB, Individually; BRUCE E. WILLIAMS, Individually; Cecil Crowson, Jr. Appellate C ourt Clerk ROBERT L. SABBATINI, P.C.; and ROBERT H. HARPER, Individually, as Partners of the Partnership,

Defendants-Appellees. ____________________________________________________________________________

FROM THE SHELBY COUNTY CIRCUIT COURT THE HONORABLE WILLIAM B. ACREE, JR.

Wyatt, Tarrant, & Combs; Glen G. Reid, Jr. and Ross Higman of Memphis For Plaintiff-Appellant

Glassman, Jeter, Edwards and Wade, P.C. William M. Jeter of Memphis For Defendants-Appellees

AFFIRMED AND REMANDED

Opinion filed:

W. FRANK CRAWFORD, PRESIDING JUDGE, W.S.

CONCUR:

HEWITT P. TOMLIN, JR., SENIOR JUDGE

DAVID R. FARMER, JUDGE (Not Participating) This case is before the Court on remand from the Supreme Court for this Court “to

reconsider it’s opinion in light of [the Supreme Court’s] recent decision in John Kohl & Co.

P.C. v. Dearborn & Ewing.” The Court, pursuant to the Supreme Court’s mandate, has

reconsidered the case and withdraws its previously filed opinion. This is a legal malpractice case. Plaintiff/Appellant Bradson Mercantile, Inc., (Bradson)

appeals the trial court’s order granting summary judgment on the ground that the action is barred

by the statute of limitations.

During the late 1980s and early 1990s, Bradson, as a subcontractor, provided labor for

two construction projects in Shelby County: the Mapco project1 and the Shelby Tissue project.

When it was not paid for its participation in these projects, Bradson retained Defendant/Appellee

Joseph H. Crabtree of the law firm Defendant/Appellee Shuttleworth, Smith, McNabb &

Williams (Law Firm)2 as legal counsel in 1992. Bradson alleges that it hired Crabtree to collect

the sums due and to perfect mechanic’s and materialman’s liens on the real property involved

in the projects. At some point later, Bradson learned that the lien on the Mapco project was

never perfected. In an attempt to resolve the dispute without litigation, the parties entered into

a “Tolling Agreement” on October 14, 1993. This agreement states in relevant part:

Bradson may have and asserts a claim against Crabtree and the Law Firm for breach of contract, legal malpractice, and/or negligence arising out of the representation by Crabtree and the Law Firm of Bradson relating to Bradson’s claim against MT Mechanical Contractors, Inc. and the perfection of a Mechanics and Materialmen’s Lien involving property of MAPCO Petroleum, Inc. (“the Representation”). Bradson has advised Crabtree and the Law Firm of its intention to file a lawsuit against them; and Crabtree and the Law Firm have advised their malpractice insurance carrier of the claim and desire additional time to settle or reconcile the claim of Bradson; and In order to provide the parties with a period of time to endeavor to settle or reconcile the issues, Crabtree and the Law Firm agree to extend and waive and otherwise toll any and all limitation periods or statutes of repose, both legal and equitable, including but not limited to TCA §28-3-104, applicable to any and all causes of action which Bradson may have or may assert against Crabtree and/or the Law Firm and/or its Partners, agents and employees arising from the Representation; NOW, THEREFORE, in consideration of Bradson forebearing until February 14, 1994, from taking any action against Crabtree, the Law Firm, its agents, employees or Partners, arising out of the Representation above referred to, Crabtree, individually, the Law Firm, its Partners, agents and employees hereby covenant and agree that they will not, in any way, in response to or in defense of any action brought against them or any of them by Bradson relating to the Representation raise the defense of any statute of limitation or of repose (legal or equitable) to any claim asserted by Bradson against Crabtree and/or the Law Firm, its Partners, agents and/or employees relating to the Representation.

Meanwhile, Law Firm had filed an action on behalf of Bradson with regard to the Shelby

1 This project was also referred to as the “M.T. Mechanical project.” 2 “Law Firm” will be used to refer to all individual defendants and the firm.

2 Tissue project. In addition, the contractor for the Shelby Tissue project filed a Lien Creditors’

Bill on behalf of several lien creditors, including Bradson. Subsequently, Bradson discovered

that Law Firm may have failed to comply with statutory requirements for the perfection of the

Shelby Tissue lien.3 Bradson’s Complaint alleges that although a Notice of Lien was filed in the

Shelby County Register’s office, Law Firm “failed to prepare and serve a written notice that the

lien was being claimed within the time prescribed by T.C.A. § 66-11-115(b).” In addition,

Bradson’s Complaint also alleges that Law Firm neglected to timely “prepare and serve a Notice

of Nonpayment by registered mail to Shelby Tissue and the property owner in accord with

T.C.A. § 66-11-145.”

On February 14, 1994, the parties entered into an “Extension of Tolling Agreement.”

This agreement states in relevant part:

This Agreement is for the purpose of further extending the Tolling Agreement heretofore entered into by and between the parties on October 14, 1993. . . .

The Parties have endeavored to settle or reconcile certain issues that may exist as heretofore delineated in the original Tolling Agreement and, because of additional matters that may have arisen, the parties are desirous of extending the original Tolling Agreement through May 6, 1994, pursuant to the terms and conditions of the original Tolling Agreement. All other provisions in the original Tolling Agreement shall continue to be applicable, with the tolling period being extended from February 14, 1994 through and including May 6, 1994.

Bradson asserts that it was the intent of the parties to incorporate the potential Shelby Tissue

project claim as part of the original Tolling Agreement.

In March 1994, the parties settled the Mapco dispute. The Release and Indemnification

Agreement specifically excludes the Shelby Tissue dispute and states: It is acknowledged, understood and agreed by Insurers and Lawyers that Bradson does hereby specifically reserve any and all rights and claims it may have against the Law Firm of Shuttleworth, Smith, McNabb & Williams, it [sic] partners, associates and employees including, but not limited to, claims for legal malpractice relating to or arising out of the representation of Bradson by said Lawyers relating to a project commonly identified as “Shelby Tissue” on which Lawyers agreed to and did perform and render certain services and certain work and in which the said Lawyers and Law Firm represented Bradson. . . . All parties to this Release further acknowledge that a claim has heretofore been made with regard to the “Shelby Tissue” representation and that that claim as well as any and all other claims which Bradson has or may have are not being released by this Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc.
521 S.W.2d 578 (Tennessee Supreme Court, 1975)
McKee v. Continental Ins. Co.
234 S.W.2d 830 (Tennessee Supreme Court, 1950)
Petty v. Sloan
277 S.W.2d 355 (Tennessee Supreme Court, 1955)
Ballard v. North American Life & Casualty Co.
667 S.W.2d 79 (Court of Appeals of Tennessee, 1983)
Ameraccount Club, Inc. v. Hill
617 S.W.2d 876 (Tennessee Supreme Court, 1981)
Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
State v. Thompson
832 S.W.2d 577 (Court of Criminal Appeals of Tennessee, 1991)
Sutton v. First National Bank of Crossville
620 S.W.2d 526 (Court of Appeals of Tennessee, 1981)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Warren v. Estate of Kirk
954 S.W.2d 722 (Tennessee Supreme Court, 1997)
West v. Laminite Plastics Manufacturing Co.
674 S.W.2d 310 (Court of Appeals of Tennessee, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Bradson Mercantile v. Joseph Crabtree, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradson-mercantile-v-joseph-crabtree-tennctapp-1999.