Bradshaw v. Weber

109 So. 492, 161 La. 789, 1926 La. LEXIS 2133
CourtSupreme Court of Louisiana
DecidedJune 28, 1926
DocketNo. 27712.
StatusPublished
Cited by1 cases

This text of 109 So. 492 (Bradshaw v. Weber) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradshaw v. Weber, 109 So. 492, 161 La. 789, 1926 La. LEXIS 2133 (La. 1926).

Opinion

THOMPSON, J.

The police jury of Vernon parish, on May 6, 1924, entered into two written contracts with W. H. Smith, Jr., for the construction of roads 2 and 3 of road district No. 2 of said parish. The contractor furnished a bond for each of said roads with the United States Fidelity & Guaranty Company .as surety.

The contracts and bonds were duly record-1 ed as provided by law.

Thereafter Smith entered, into a subcontract with H. M. Weber to do the principal *791 part of the construction • of said roads, and the said Weber furnished a bond with the ¿Etna Casualty & Surety Company as surety. The subcontract and the surety bond were likewise properly recorded.

The roads were constructed in accordance with the contract to the satisfaction of the engineer in charge, and were accepted by the police jury as the governing authority.

A dispute arose between the police jury and the contractor Smith as to the amount due the contractor when the work was finally completed, and no final settlement was made by the police jury. In consequence of this controversy, Smith defaulted in payment on his contract with Weber, and the latter defaulted in the payment of his creditors.

The plaintiff as one of the creditors of the subcontractor Weber brought this suit against Weber, the ¿Etna Casualty Surety Company, and the police jury for $3,218.94, being for feed stuff, gasoline for motor trucks, and money advanced for pay rolls.

The police jury answered and called the contractor 'Smith and his surety, United States Fidelity & Guaranty Company, into the suit, and prayed for such judgment against them as may be rendered in favor of the plaintiff against said jury.

The surety company answered, denying any liability, and alleged that, if it be true that the police jury and W. H. Smith were notified of the default of the said Weber on his contract and paid out the money then being held and which should have been held to meet such obligations after having been requested to retain the same, then and in that case the surety was discharged.

H. M. Weber appeared and alleged that W. H. Smith was indebted to him in the sum of $3,778.15 as balance due for work on the construction of said roads.

He further alleged that, by reason of the failure of Smith to pay him, he had defaulted on his contract in the payment of certain laborers and furnishers of materials whose claims had been duly recorded.

He accordingly prayed that said claimants, together with the police jury, Smith, the original contractor, and the surety on his bond, be cited as in concursus to show cause why the respective rights and claims of all the parties should not be classified and determined.

The several claimants appeared and filed answers asserting their respective claims-against Weber and the surety on his bond.

On a trial, judgment was rendered in favor of W. H. Smith and against the police jury for $8,970.01, in favor of Weber and against Smith and the United Fidelity & Guaranty Company in solido for $4,751.78, and against Smith and the surety on his bond, and against Weber and the surety on his bond in favor of the plaintiff and the several claimants for the amounts as set forth in the judgment.

W. H. Smith and the United States Fidelity & Guaranty Company hgve appealed.

Weber and the ¿Etna Casualty & Surety Company have answered 'the appeal and asked that the judgment in their favor against Smith and the United States Fidelity & Guaranty Company be increased to $6,108.-58.

The police jury seems to be satisfied with the judgment rendered against it in favor of Smith, since the attorneys for the police jury in their brief have asked that the judgment be affirmed.

The only contest in this court is (1) on behalf of Smith, who claims that his judgment against the police jury should be increased to the sum of $11,029.01, based on an estimate made by Higginbotham, and that he should have judgment against Weber and his surety for whatever amount that may be rendered' against Smith and his surety on account of any indebtedness of said Weber incurred in, the performance of his contract with Smith; (2) by Weber, subcontractor, who claims that *793 his judgment against Smith should be increased to the sum of $6,108.

In brief of counsel for Smith and his surety, it is conceded that, if Higginbotham’s estimate is accepted, then Weber should have judgment against Smith and his surety for $5,108.48.

It appears that the police jury employed W. S. Bonner as engineer to supervise the construction of the roads, with S. B. Higginbotham as assistant. Before the completion of the roads, the jury became dissatisfied with Bonner and discharged him, and the work of supervision was continued by Higginbotham.

After the dispute arose between the police jury and Smith as to the balance due Smith, the jury employed Floyd Hamilton, another engineer, to check up the work, and Smith employed Higginbotham to make an estimate of the work on his behalf.

The estimates were made by the two engineers, and, while they agreed on quite a number of the items of work, they disagreed on many of the larger items. This disagreement brought on the present litigation.

The district judge seems to have adopted in the main the estimate made by Hamilton, though he did accept some of the items on the estimate made by Higginbotham.

We take the liberty of here inserting a part of the written opinion of the trial judge:

“The following items are the ones that Smith and the police jury disagree on: On road No. 3, items 3, 19, 20, 21, 27, and 28. On road No. 2 items 3, 19, 20, 21, 25, 26, 27, and 28.”
“Relying upon that estimate of Hamilton and the items agreed to, the police jury admits that it now owes Smith the sum of $5,964.24. The items that are contested- have the same number by both parties in their estimates, except item 28, shown on estimate made by Higginbotham which is not shown by. Hamilton.”
“Item 1 on road No. 2, there is a difference in the two estimates; however same is admitted by the police jury in favor of Smith, and same will not be further considered.”
“Item 3 of road 3, district No. 2, Hamilton’s estimate on borrow is 19,062.1 yards of dirt at 30 cents per yard,- amounting to $5,718.63.”
“Higginbotham’s estimate on same is 21,-430.6 yards, amounting to $6,429.18; the difference between the two estimates being $711.17.
“On item 3 of road 2, Hamilton’s estimate is 52,409 yards for borrow at 30 cents per yard, amounting to $15,722.70.”
“Higginbotham’s estimate on same is 58,951 yards at 30 cents, amounting to $17,685.30; the difference being the amount of $1,960.70.” “The contract contains a stipulation for the building of shoulders.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silver v. Harriss
115 So. 376 (Supreme Court of Louisiana, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
109 So. 492, 161 La. 789, 1926 La. LEXIS 2133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradshaw-v-weber-la-1926.