Bradley v. . McDonald

113 N.E. 340, 218 N.Y. 351, 1916 N.Y. LEXIS 1575
CourtNew York Court of Appeals
DecidedJune 6, 1916
StatusPublished
Cited by26 cases

This text of 113 N.E. 340 (Bradley v. . McDonald) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradley v. . McDonald, 113 N.E. 340, 218 N.Y. 351, 1916 N.Y. LEXIS 1575 (N.Y. 1916).

Opinions

Hogan, J.

This action was commenced in August, 1906, against John B. McDonald and Rapid Transit Sub *359 way Construction Company, hereinafter designated as Construction Company,” to recover a balance alleged to be due plaintiff for work performed and materials furnished for the construction of subsection six of the New York subway, also for extra work performed and materials supplied and for additional work performed and materials supplied in connection with said work.

March 17th, 1911, during the progress of the trial and before the defendant’s case was opened, John B. McDonald died. April 8th, 1911, Georgie Annie McDonald, executrix of the last will and testament of John B. McDonald, was substituted as a party defendant without prejudice to the proceedings theretofore had in the action.

On or about February 21st, 1909, the city of New York by the board of rapid transit railroad commissioners, herein referred to as the board of commissioners, entered into a contract with John B. McDonald, wherein Mr. McDonald undertook to fully construct and equip the rapid transit railroad commonly known as the ‘1 Subway ” from the city hall in the borough of Manhattan to the terminals in the borough of The Bronx, and to operate the same as therein provided. Simultaneously with the execution of the contract Mr. McDonald was required to give security for the performance of the contract on his part, both under the agreement for construction and equipment and also as a continuing security.

The Rapid Transit Subway Construction Company was organized February 16th, 1900, to construct or aid in the construction of rapid transit railroads in the city of New York. About the date of the execution of the contract between the city and Mr. McDonald a written contract was made between Mr. McDonald and the .Construction Company, wherein the Construction Company agreed to advance to Mr. McDonald the amount of cash security required to be deposited by him with the city comptroller, and to execute as surety or to procure satisfactory sureties to execute *360 the bonds required to he furnished by Mr. McDonald. As security for the. re-payment of the sum of money to be advanced, and for the protection of the Construction Company from any liability upon the bonds, the contract provided (1) that the Construction Company should receive all moneys payable to the contractor (Mr. McDonald) under his contract, and should disburse the same; (2) that McDonald should not make sub-contracts for any portion of the work or for the purchase of any material required in carrying out the work until after the same had been first approved by the Construction Company; (3) for the purpose of more effectually carrying out the provisions of the contract, Mr. McDonald assigned to the Construction Company all payments which should become due to him from time to time under the contract made by him with the city, the amounts to be paid to the Construction Company as the same fell due; (4) the Construction Company agreed to pay out of the said moneys so received, so far as the same would be sufficient for that purpose, all amounts due and payable to subcontractors and others by the contractor (Mr. McDonald) for work done or materials furnished in carrying out the work required by the- contract with the city of New York when and as the same became due.

July 31st, 1900, Mr. McDonald entered into a contract with the plaintiff, by .the terms of which plaintiff for a valuable consideration undertook and agreed to construct the rapid transit railroad between the center of Sixtieth street and the center of One Hundred and Fourth street, known as subdivisions A and B of subsection six. Plaintiff, on the same day, entered upon the performance of the contract having first given the necessary bond required of him.

The contract amongst other things referred to the assignment of the original contract to the Construction Company and to the provisions thereof, whereby the lat-t,er company had agreed to pay out of moneys received *361 by it all amounts which might become due and payable from the contractor to sub-contractors and a waiver on the part of the sub-contractor (plaintiff herein) of the right at any time to file a lien against any 'moneys which might at any time be or become due from the city under the principal contract, and to have recourse to such moneys in the hands of the Construction Company for payment of sums to become due and payable under his contract, a copy of which was to be deposited with the Construction Company.

The fact was conceded in the pleadings and found by the referee that long prior to the commencement of the action the Construction Company had received from the city, under its agreement with Mr. McDonald, a large sum of money payable to Mr. McDonald under his contract and retained of the moneys so received more than sufficient to meet and discharge any claim established against it or its co-defendant, Mr. McDonald, on account of work performed and materials furnished by plaintiff.

The provision of the contract to which attention has been called read in connection with the agreement between Mr. McDonald and the Construction Company entitled the plaintiff to the benefit of the provision of the latter agreement as fully as though he had been specifically named therein, and he is entitled to recover from the Construction Company any amount due to him. (Lawrence v. Fox, 20 N. Y. 268; Coster v. Mayor, etc., of Albany, 43 N. Y. 399; Pond v. New Rochelle W. Co., 183 N. Y. 330; Rochester Telephone Co. v. Ross, 195 N. Y. 439.)

The contract between Mr. McDonald and the city provided for the construction and equipment of the railroad for a lump sum. The work was to be performed pursuant to specifications and contract drawings furnished by the board of commissioners which were intended to be full and complete, but in view of the magnitude of the work and the impossibility either to show in advance all details *362 or to forecast all exigencies the specifications and. drawings were to he taken as indicating the amount of work, its nature and method of construction so far as the same was distinctly apprehended. The contractor, however, became obligated to construct and equip the railroad as contemplated in the contract and specifications. The board of- commissioners reserved the right to amplify the plans, to add explanatory specifications, to furnish additional specifications and drawings within the limits of the general purview of the work, to require additional work to he done or additional materials to be furnished, or both within the general scope of a rapid transit railroad, or to require work or materials specified or provided for to be omitted. If such additional work or materials were required, then the reasonable value thereof was to be additionally paid to the contractor; if work or materials were omitted a, reasonable deduction should be made therefor.

The contract between Mr. McDonald and the plaintiff was a unit price contract, i. e.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Smith
985 F. Supp. 2d 547 (S.D. New York, 2014)
McIntyre v. United States
447 F. Supp. 2d 54 (D. Massachusetts, 2006)
Thompson v. Harris
504 F. Supp. 653 (D. Massachusetts, 1980)
Leben v. Nassau Savings & Loan Ass'n
40 A.D.2d 830 (Appellate Division of the Supreme Court of New York, 1972)
Thrasher v. Thrasher
167 S.E.2d 549 (Court of Appeals of North Carolina, 1969)
In re Credit Industrial Corp.
250 F. Supp. 582 (S.D. New York, 1965)
Denney v. Spot Martin, Inc.
328 S.W.2d 399 (Missouri Court of Appeals, 1959)
Union Bank & Trust Co. v. Gordon
254 P.2d 644 (California Court of Appeal, 1953)
Rediker v. Rediker
221 P.2d 1 (California Supreme Court, 1950)
Miller v. Miller
38 N.W.2d 35 (North Dakota Supreme Court, 1949)
Hensgen v. Silberman
197 P.2d 356 (California Court of Appeal, 1948)
Estate of Hensgen
181 P.2d 69 (California Court of Appeal, 1947)
Williams v. North Carolina
325 U.S. 226 (Supreme Court, 1945)
United States v. 21.91 Acres of Land
50 F. Supp. 797 (D. Massachusetts, 1943)
Commonwealth v. Bane
39 Pa. D. & C. 664 (Washington County Court of Quarter Sessions, 1940)
Goodloe v. Hawk
113 F.2d 753 (D.C. Circuit, 1940)
Golden v. Golden
68 P.2d 928 (New Mexico Supreme Court, 1937)
Curry v. Curry
79 F.2d 172 (D.C. Circuit, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
113 N.E. 340, 218 N.Y. 351, 1916 N.Y. LEXIS 1575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradley-v-mcdonald-ny-1916.